COVID-19 made payment delays to contractors much worse

Codes and Standards

COVID-19 made payment delays to contractors much worse

Only one in ten companies is always getting paid in full.


By Peter Fabris, Contributing Editor | July 1, 2021

The COVID-19 pandemic appears to have made payment delays to contractors much worse, according to a report from construction software firm Levelset.

Just 9% of companies always get paid on time, a decline of 60% from last year, says Levelset’s 2021 Construction Cash Flow & Payment Report. Just one construction contractor in 10 always gets paid in full, a 75% drop from before the pandemic.

GCs typically fare better than subs. General contractors are four times more likely than subcontractors to get paid within 30 days, and 50% more likely to get paid in full. One in five subcontractors and suppliers often have to wait more than 60 days for payment.

A full 56% of subcontractors wait more than 60 days to collect retained funds, compared to just 16% of general contractors.

Related Stories

| Apr 5, 2012

New IgCC green building code is a ‘game changer,’ AIA official says

An AIA official calls the new International Green Construction Code (IgCC) a “game changer” for sustainable construction.

| Apr 5, 2012

Model energy codes add thousands to cost of new apartment construction, study says

New energy codes could add thousands of dollars to the construction costs of each individual apartment residence in a multifamily building, according to new research commissioned by the National Multi-Housing Council and the National Apartment Association.

| Apr 5, 2012

LEED 2012 will include new requirements for data centers

The U.S. Green Building Council’s updated LEED 2012 standards will require two systems to be modeled for each project in order to show power utilization effectiveness.

| Mar 30, 2012

CSI webinar: Durable & energy efficient building envelope design, April 24

This seminar will review recent changes in North America energy codes, examples of building enclosure wall assemblies being considered for code compliance, potential moisture management and durability challenges, and design tools that could be used to assess and minimize potential problems.

| Mar 30, 2012

Improved construction that followed seismic codes helped avert loss of life in Mexico temblor

A magnitude-7.4 earthquake that shook Mexico from Mexico City to Acapulco damaged hundreds of homes and sent thousands fleeing from swaying office buildings, yet no one was killed, according to early reports.

| Mar 30, 2012

Chicago may allow people to live in retail spaces

The Chicago City Council’s Zoning Committee approved a zoning change that will allow up to 50% of work space in low-intensity business districts to be used for living space.

| Mar 30, 2012

LEED growing fast in the housing rental market

Last year, developers of 23,000 U.S. multifamily housing units applied for LEED certification.

| Mar 30, 2012

Forest Stewardship Council critical of proposed LEED 2012 changes

According to the Forest Stewardship Council (FSC), the third draft of LEED 2012, if approved as written, would represent a step backward from the current Certified Wood Credit.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021