As costs rise, Building Teams turn to novel energy-saving schemes for data centers [2013 Giants 300 Report]

As costs rise, Building Teams turn to novel energy-saving schemes for data centers [2013 Giants 300 Report]

Shrinking IT budgets and rising operational costs have led data center operators and corporate clients to scrutinize project budgets.


By David Barista, Editor-in-Chief | August 20, 2013
Many AEC firms that specialize in data centers report growth in the retrofit mar
Many AEC firms that specialize in data centers report growth in the retrofit market. An example is the 450,000-sf EMC Cloud Data Center in Durham, N.C., which was built in a former IBM warehouse. The buildings original exterior was kept in place, and its loading docks were repurposed as air-side economizers. Symmes Maini and McKee Associates led the design team. DPR Construction was the construction manager. PHOTO: ROBERT BENSON PHOTOGRAPHY

While the once white-hot data center construction market has cooled off in recent years, the outlook for this sector remains quite rosy. Each year, businesses and institutions spend billions on data center construction and retrofit projects to keep up with the nation’s insatiable demand for data storage and processing. 

The data center sector is conservatively estimated at $13-15 billion annually—larger than the hospitality, amusement/recreation, and water supply sectors, according to U.S. Census Bureau data. And the emergence of cloud computing and storage, combined with the “never delete anything” mindset of consumers and businesses, will only drive demand for data storage and processing.  

“The data center market should generally follow the growth of Internet traffic, and Internet traffic continues to grow strongly,” says Craig Deering, AIA, LEED AP, National Practice Leader – Critical Facilities with HDR Architecture.

According to a May 2013 report from Cisco Systems, IP traffic volume in North America is expected to grow to 40 exabytes a month by 2017, a 23% cumulative annual growth rate. Cisco predicts global IP traffic will increase threefold over the next five years. Driving this steep growth are the explosion of networked devices, especially wireless gadgets, and the emergence of video as a dominant content type. Cisco predicts that traffic from wireless and mobile devices will exceed wired devices by 2016, and video will reach 69% of global consumer Internet traffic by 2017.

TOP DATA CENTER ARCHITECTURE FIRMS

 
2012 Data Center Revenue ($)
1 Corgan $27,534,191
2 Gensler $23,330,000
3 HDR Architecture $16,295,000
4 Integrated Design Group $14,598,910
5 PageSoutherlandPage $14,450,000
6 Reynolds, Smith and Hills $4,360,000
7 Callison $3,973,699
8 Little $3,655,590
9 RTKL Associates $3,634,000
10 EwingCole $3,000,000

TOP DATA CENTER ENGINEERING FIRMS

 
2012 Data Center Revenue ($)
1 Fluor $235,678,900
2 Syska Hennessy Group $36,735,434
3 Jacobs Engineering Group $36,700,000
4 H&A Architects & Engineers $35,427,599
5 URS Corp. $26,229,049
6 Environmental Systems Design $10,575,892
7 Parsons Brinckerhoff $10,300,000
8 H.F. Lenz $7,357,000
9 Science Applications International Corp. $6,760,598
10 AKF Group $6,602,000

TOP DATA CENTER CONSTRUCTION FIRMS

 
2012 Data Center Revenue ($)
1 DPR Construction $895,882,459
2 Balfour Beatty $753,194,214
3 Holder Construction $710,000,000
4 Turner Corporation, The $501,750,000
5 Whiting-Turner Contracting Co., The $490,093,045
6 Mortenson Construction $307,360,000
7 Structure Tone $285,725,000
8 Skanska USA $236,396,858
9 Gilbane $130,362,000
10 Carlson Design Construct $128,000,000

Giants 300 coverage of Data Centers brought to you by System Sensor www.systemsensor.com

What does this mean in terms of construction spending growth? If the Data Center Dynamics annual census of the industry is any indication, the data center construction market will remain one of the fastest-growing sectors in the country. According to DCD Intelligence’s most recent survey of nearly 3,800 data center owner/operators and 1,600 vendors, data center facility investment was up 23% on the Coasts and 50% in the central U.S. in 2011-12.

“Calculating the size of the data center market is challenging,” says Deering, “but no matter how you look at it, there’s no doubt that the data center market stands on its own as a distinct and meaningful sector.”

Achieving a lower cost of computing

Shrinking IT budgets and rising operational costs have led data center operators and corporate clients to scrutinize project budgets. As a result, AEC firms are being tasked with finding solutions for lowering the overall cost of computing and operating and maintaining the facilities. 

This, in turn, is driving innovation in data center design, including the use of advanced cooling schemes, energy-efficient IT equipment, and higher-density environments. Advanced technologies like KyotoCooling, which utilizes heat wheels to reduce the cooling load on the building’s HVAC system, are becoming more common in U.S. data center projects. In addition, a growing number of data center operators are choosing to build new facilities in northern climates to take advantage of the cooler outdoor air temperatures.  

Advancements in server technology, combined with a recent change to ASHRAE’s TC 9.9 Datacom guidelines, means that Building Teams can deliver facilities that operate at higher internal temperatures, greatly reducing cooling costs.   

“The top end of the allowable range now is 80.6°F, up from 76°F previously,” says Ronald Vokoun, DBIA, LEED AP BD+C, Mission Critical Market Leader – Western Region with JE Dunn Construction. “Generally speaking, for every 1.8°F that you raise the temperature in your data center, you save 2-4% of your total energy bill. That’s a pretty high and immediate ROI.”

Rising costs are forcing many companies to outsource their data hosting through co-location and cloud services. This trend is leading to the construction of more mega-data center facilities, like CyrusOne’s new Chandler, Ariz., complex, which will eventually house more than 

1 million sf of data center space. By 2015, just 2% of the world’s data centers will contain 60% of the floor space, up from 52% in 2010, according to a report from Gartner Inc. 

“We will continue to see the concentration of data center floor space into a small community of dominant global players,” says HDR’s Deering.

Retrofits: A growth market

An emerging market for AEC firms is data center retrofits. The first wave of data centers—built during the dot-com boom of the late 1990s—are woefully outdated and are prime for retrofitting. Even the facilities built years later are behind the technology curve, and operators will be looking to upgrade their servers and infrastructure to meet the computing demands of today’s market.      

“Many companies are looking at the ‘capex’ versus ‘opex’ dollars and realizing that they can strike a meaningful balance between the two by simply updating, retrofitting, or renovating their existing facilities,” says Jerry Sumrell, PE, Vice President, Mission Critical with RS&H. “This presents new challenges to the design industry, as we will be devoting more time to working in live data center environments with all of the associated risks that come with it. It’s akin to performing open-heart surgery—you have to keep the facility running 24/7 while adding new equipment, decommissioning existing equipment, and transferring power/cooling from one piece of equipment to another.”

Read BD+C's full Giants 300 Report

Related Stories

Giants 400 | Aug 26, 2021

2021 Data Center Giants: Top architecture, engineering, and construction firms in the U.S. data center facilities sector

Corgan, Holder Construction, Jacobs, and Whiting-Turner top BD+C's rankings of the nation's largest data center facilities sector architecture, engineering, and construction firms, as reported in the 2021 Giants 400 Report.

Hotel Facilities | Aug 26, 2021

Building hotels with modules, with citizenM's Menno Hilberts

In this exclusive interview for HorizonTV, Menno Hilberts, Managing Director of Project Management with hotelier citizenM, explains how the company is employing modular construction to help double its presence in the U.S. 

Sports and Recreational Facilities | Aug 25, 2021

The rise of entertainment districts and the inside-out stadium

Fiserv Forum, home to the 2021 NBA Champion Milwaukee Bucks, proved that the design of the space outside a stadium is just as important as inside.

Architects | Aug 19, 2021

BD+C Events

Building Design+Construction's annual events include the Women in Design+Construction conference and the ProConnect meeting series.

Multifamily Housing | Aug 19, 2021

Multifamily emerges strong from the pandemic, with Yardi Matrix's Doug Ressler

Yardi Matrix's Doug Ressler discusses his firm's latest assessment of multifamily sales and rent growth for 2021.

Resiliency | Aug 19, 2021

White paper outlines cost-effective flood protection approaches for building owners

A new white paper from Walter P Moore offers an in-depth review of the flood protection process and proven approaches.

Resiliency | Aug 19, 2021

White paper outlines cost-effective flood protection approaches for building owners

A new white paper from Walter P Moore offers an in-depth review of the flood protection process and proven approaches.

Wood | Jul 16, 2021

The future of mass timber construction, with Swinerton's Timberlab

In this exclusive for HorizonTV, BD+C's John Caulfield sat down with three Timberlab leaders to discuss the launch of the firm and what factors will lead to greater mass timber demand.

Multifamily Housing | Jul 15, 2021

Economic rebound leads to record increase in multifamily asking rents

Across the country, multifamily rents have skyrocketed. Year-over-year rents are up by double digits in nine of the top 30 markets, while national YoY rent growth is up 6.3%. Emerging from the pandemic, a perfect storm of migration, enhanced government stimulus and a hot housing market, among other factors, has enabled this extremely strong growth.

K-12 Schools | Jul 9, 2021

LPA Architects' STEM high school post-occupancy evaluation

LPA Architects conducted a post-occupancy evaluation, or POE, of the eSTEM Academy, a new high school specializing in health/medical and design/engineering Career Technical Education, in Eastvale, Calif. The POE helped LPA, the Riverside County Office of Education, and the Corona-Norco Unified School District gain a better understanding of which design innovations—such as movable walls, flex furniture, collaborative spaces, indoor-outdoor activity areas, and a student union—enhanced the education program, and how well students and teachers used these innovations.

boombox1
boombox2
native1

More In Category


Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021