As costs rise, Building Teams turn to novel energy-saving schemes for data centers [2013 Giants 300 Report]

As costs rise, Building Teams turn to novel energy-saving schemes for data centers [2013 Giants 300 Report]

Shrinking IT budgets and rising operational costs have led data center operators and corporate clients to scrutinize project budgets.


By David Barista, Editor-in-Chief | August 20, 2013
Many AEC firms that specialize in data centers report growth in the retrofit mar
Many AEC firms that specialize in data centers report growth in the retrofit market. An example is the 450,000-sf EMC Cloud Data Center in Durham, N.C., which was built in a former IBM warehouse. The buildings original exterior was kept in place, and its loading docks were repurposed as air-side economizers. Symmes Maini and McKee Associates led the design team. DPR Construction was the construction manager. PHOTO: ROBERT BENSON PHOTOGRAPHY

While the once white-hot data center construction market has cooled off in recent years, the outlook for this sector remains quite rosy. Each year, businesses and institutions spend billions on data center construction and retrofit projects to keep up with the nation’s insatiable demand for data storage and processing. 

The data center sector is conservatively estimated at $13-15 billion annually—larger than the hospitality, amusement/recreation, and water supply sectors, according to U.S. Census Bureau data. And the emergence of cloud computing and storage, combined with the “never delete anything” mindset of consumers and businesses, will only drive demand for data storage and processing.  

“The data center market should generally follow the growth of Internet traffic, and Internet traffic continues to grow strongly,” says Craig Deering, AIA, LEED AP, National Practice Leader – Critical Facilities with HDR Architecture.

According to a May 2013 report from Cisco Systems, IP traffic volume in North America is expected to grow to 40 exabytes a month by 2017, a 23% cumulative annual growth rate. Cisco predicts global IP traffic will increase threefold over the next five years. Driving this steep growth are the explosion of networked devices, especially wireless gadgets, and the emergence of video as a dominant content type. Cisco predicts that traffic from wireless and mobile devices will exceed wired devices by 2016, and video will reach 69% of global consumer Internet traffic by 2017.

TOP DATA CENTER ARCHITECTURE FIRMS

 
2012 Data Center Revenue ($)
1 Corgan $27,534,191
2 Gensler $23,330,000
3 HDR Architecture $16,295,000
4 Integrated Design Group $14,598,910
5 PageSoutherlandPage $14,450,000
6 Reynolds, Smith and Hills $4,360,000
7 Callison $3,973,699
8 Little $3,655,590
9 RTKL Associates $3,634,000
10 EwingCole $3,000,000

TOP DATA CENTER ENGINEERING FIRMS

 
2012 Data Center Revenue ($)
1 Fluor $235,678,900
2 Syska Hennessy Group $36,735,434
3 Jacobs Engineering Group $36,700,000
4 H&A Architects & Engineers $35,427,599
5 URS Corp. $26,229,049
6 Environmental Systems Design $10,575,892
7 Parsons Brinckerhoff $10,300,000
8 H.F. Lenz $7,357,000
9 Science Applications International Corp. $6,760,598
10 AKF Group $6,602,000

TOP DATA CENTER CONSTRUCTION FIRMS

 
2012 Data Center Revenue ($)
1 DPR Construction $895,882,459
2 Balfour Beatty $753,194,214
3 Holder Construction $710,000,000
4 Turner Corporation, The $501,750,000
5 Whiting-Turner Contracting Co., The $490,093,045
6 Mortenson Construction $307,360,000
7 Structure Tone $285,725,000
8 Skanska USA $236,396,858
9 Gilbane $130,362,000
10 Carlson Design Construct $128,000,000

Giants 300 coverage of Data Centers brought to you by System Sensor www.systemsensor.com

What does this mean in terms of construction spending growth? If the Data Center Dynamics annual census of the industry is any indication, the data center construction market will remain one of the fastest-growing sectors in the country. According to DCD Intelligence’s most recent survey of nearly 3,800 data center owner/operators and 1,600 vendors, data center facility investment was up 23% on the Coasts and 50% in the central U.S. in 2011-12.

“Calculating the size of the data center market is challenging,” says Deering, “but no matter how you look at it, there’s no doubt that the data center market stands on its own as a distinct and meaningful sector.”

Achieving a lower cost of computing

Shrinking IT budgets and rising operational costs have led data center operators and corporate clients to scrutinize project budgets. As a result, AEC firms are being tasked with finding solutions for lowering the overall cost of computing and operating and maintaining the facilities. 

This, in turn, is driving innovation in data center design, including the use of advanced cooling schemes, energy-efficient IT equipment, and higher-density environments. Advanced technologies like KyotoCooling, which utilizes heat wheels to reduce the cooling load on the building’s HVAC system, are becoming more common in U.S. data center projects. In addition, a growing number of data center operators are choosing to build new facilities in northern climates to take advantage of the cooler outdoor air temperatures.  

Advancements in server technology, combined with a recent change to ASHRAE’s TC 9.9 Datacom guidelines, means that Building Teams can deliver facilities that operate at higher internal temperatures, greatly reducing cooling costs.   

“The top end of the allowable range now is 80.6°F, up from 76°F previously,” says Ronald Vokoun, DBIA, LEED AP BD+C, Mission Critical Market Leader – Western Region with JE Dunn Construction. “Generally speaking, for every 1.8°F that you raise the temperature in your data center, you save 2-4% of your total energy bill. That’s a pretty high and immediate ROI.”

Rising costs are forcing many companies to outsource their data hosting through co-location and cloud services. This trend is leading to the construction of more mega-data center facilities, like CyrusOne’s new Chandler, Ariz., complex, which will eventually house more than 

1 million sf of data center space. By 2015, just 2% of the world’s data centers will contain 60% of the floor space, up from 52% in 2010, according to a report from Gartner Inc. 

“We will continue to see the concentration of data center floor space into a small community of dominant global players,” says HDR’s Deering.

Retrofits: A growth market

An emerging market for AEC firms is data center retrofits. The first wave of data centers—built during the dot-com boom of the late 1990s—are woefully outdated and are prime for retrofitting. Even the facilities built years later are behind the technology curve, and operators will be looking to upgrade their servers and infrastructure to meet the computing demands of today’s market.      

“Many companies are looking at the ‘capex’ versus ‘opex’ dollars and realizing that they can strike a meaningful balance between the two by simply updating, retrofitting, or renovating their existing facilities,” says Jerry Sumrell, PE, Vice President, Mission Critical with RS&H. “This presents new challenges to the design industry, as we will be devoting more time to working in live data center environments with all of the associated risks that come with it. It’s akin to performing open-heart surgery—you have to keep the facility running 24/7 while adding new equipment, decommissioning existing equipment, and transferring power/cooling from one piece of equipment to another.”

Read BD+C's full Giants 300 Report

Related Stories

| Dec 29, 2011

Seismic safety in question at thousands of California public schools

California regulators responsible for enforcing earthquake safety laws have failed to certify more than 16,000 construction projects in California public schools, increasing the risk that some projects may be unsafe, according to a state audit report.

| Dec 29, 2011

GreenWizard offers cloud-based LEED credit management, assessment

The company recently began offering companies the ability to run assessments for design credits, in addition to traditional product-specific LEED credits.

| Dec 27, 2011

Clayco awarded expansion of Washington University Data Center in St. Louis

Once completed, the new building addition will double the size of the data center which houses sophisticated computer networks that store massive amounts of genomic data used to identify the genetic origins of cancer and other diseases. 

| Dec 27, 2011

Ground broken for adaptive reuse project

Located on the Garden State Parkway, the master-planned project initially includes the conversion of a 114-year-old, 365,000-square-foot, six-story warehouse building into 361 loft-style apartments, and the creation of a three-level parking facility.

| Dec 27, 2011

Nova completes $60M Clearwater Conference Center

Comprising an entire city block, the 450,000 sq. ft. facility features over 400 meeting rooms, six theaters, a full-service health spa, complete with an indoor running track, and a commercial kitchen that can efficiently accommodate over 1,000 diners

| Dec 27, 2011

BD+C's Under 40 Leadership Summit update

The two-day Under 40 Leadership Summit continued with a Leadership Style interactive presentation; Great Solutions presentations from Under 40 attendees; the Owner’s Perspective panel discussion; and the Blue Ocean Strategy presentation.

| Dec 27, 2011

Suffolk Construction celebrates raising of Boston Tea Party Ships & Museum cupola

Topping off ceremony held on 238th Anniversary of Boston Tea Party.

| Dec 27, 2011

State of the data center 2011

Advances in technology, an increased reliance on the Internet and social media as well as an increased focus on energy management initiatives have had a significant impact on the data center world.

| Dec 27, 2011

USGBC’s Center for Green Schools releases Best of Green Schools 2011

Recipient schools and regions from across the nation - from K-12 to higher education - were recognized for a variety of sustainable, cost-cutting measures, including energy conservation, record numbers of LEED certified buildings and collaborative platforms and policies to green U.S. school infrastructure.

boombox1
boombox2
native1

More In Category


Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021