Shrinking IT budgets and rising operational costs have led data center operators and corporate clients to scrutinize project budgets.


By David Barista, Editor-in-Chief | August 20, 2013
Many AEC firms that specialize in data centers report growth in the retrofit mar
Many AEC firms that specialize in data centers report growth in the retrofit market. An example is the 450,000-sf EMC Cloud Data Center in Durham, N.C., which was built in a former IBM warehouse. The buildings original exterior was kept in place, and its loading docks were repurposed as air-side economizers. Symmes Maini and McKee Associates led the design team. DPR Construction was the construction manager. PHOTO: ROBERT BENSON PHOTOGRAPHY

While the once white-hot data center construction market has cooled off in recent years, the outlook for this sector remains quite rosy. Each year, businesses and institutions spend billions on data center construction and retrofit projects to keep up with the nation’s insatiable demand for data storage and processing. 

The data center sector is conservatively estimated at $13-15 billion annually—larger than the hospitality, amusement/recreation, and water supply sectors, according to U.S. Census Bureau data. And the emergence of cloud computing and storage, combined with the “never delete anything” mindset of consumers and businesses, will only drive demand for data storage and processing.  

“The data center market should generally follow the growth of Internet traffic, and Internet traffic continues to grow strongly,” says Craig Deering, AIA, LEED AP, National Practice Leader – Critical Facilities with HDR Architecture.

According to a May 2013 report from Cisco Systems, IP traffic volume in North America is expected to grow to 40 exabytes a month by 2017, a 23% cumulative annual growth rate. Cisco predicts global IP traffic will increase threefold over the next five years. Driving this steep growth are the explosion of networked devices, especially wireless gadgets, and the emergence of video as a dominant content type. Cisco predicts that traffic from wireless and mobile devices will exceed wired devices by 2016, and video will reach 69% of global consumer Internet traffic by 2017.

TOP DATA CENTER ARCHITECTURE FIRMS

 
2012 Data Center Revenue ($)
1 Corgan $27,534,191
2 Gensler $23,330,000
3 HDR Architecture $16,295,000
4 Integrated Design Group $14,598,910
5 PageSoutherlandPage $14,450,000
6 Reynolds, Smith and Hills $4,360,000
7 Callison $3,973,699
8 Little $3,655,590
9 RTKL Associates $3,634,000
10 EwingCole $3,000,000

TOP DATA CENTER ENGINEERING FIRMS

 
2012 Data Center Revenue ($)
1 Fluor $235,678,900
2 Syska Hennessy Group $36,735,434
3 Jacobs Engineering Group $36,700,000
4 H&A Architects & Engineers $35,427,599
5 URS Corp. $26,229,049
6 Environmental Systems Design $10,575,892
7 Parsons Brinckerhoff $10,300,000
8 H.F. Lenz $7,357,000
9 Science Applications International Corp. $6,760,598
10 AKF Group $6,602,000

TOP DATA CENTER CONSTRUCTION FIRMS

 
2012 Data Center Revenue ($)
1 DPR Construction $895,882,459
2 Balfour Beatty $753,194,214
3 Holder Construction $710,000,000
4 Turner Corporation, The $501,750,000
5 Whiting-Turner Contracting Co., The $490,093,045
6 Mortenson Construction $307,360,000
7 Structure Tone $285,725,000
8 Skanska USA $236,396,858
9 Gilbane $130,362,000
10 Carlson Design Construct $128,000,000

Giants 300 coverage of Data Centers brought to you by System Sensor www.systemsensor.com

What does this mean in terms of construction spending growth? If the Data Center Dynamics annual census of the industry is any indication, the data center construction market will remain one of the fastest-growing sectors in the country. According to DCD Intelligence’s most recent survey of nearly 3,800 data center owner/operators and 1,600 vendors, data center facility investment was up 23% on the Coasts and 50% in the central U.S. in 2011-12.

“Calculating the size of the data center market is challenging,” says Deering, “but no matter how you look at it, there’s no doubt that the data center market stands on its own as a distinct and meaningful sector.”

Achieving a lower cost of computing

Shrinking IT budgets and rising operational costs have led data center operators and corporate clients to scrutinize project budgets. As a result, AEC firms are being tasked with finding solutions for lowering the overall cost of computing and operating and maintaining the facilities. 

This, in turn, is driving innovation in data center design, including the use of advanced cooling schemes, energy-efficient IT equipment, and higher-density environments. Advanced technologies like KyotoCooling, which utilizes heat wheels to reduce the cooling load on the building’s HVAC system, are becoming more common in U.S. data center projects. In addition, a growing number of data center operators are choosing to build new facilities in northern climates to take advantage of the cooler outdoor air temperatures.  

Advancements in server technology, combined with a recent change to ASHRAE’s TC 9.9 Datacom guidelines, means that Building Teams can deliver facilities that operate at higher internal temperatures, greatly reducing cooling costs.   

“The top end of the allowable range now is 80.6°F, up from 76°F previously,” says Ronald Vokoun, DBIA, LEED AP BD+C, Mission Critical Market Leader – Western Region with JE Dunn Construction. “Generally speaking, for every 1.8°F that you raise the temperature in your data center, you save 2-4% of your total energy bill. That’s a pretty high and immediate ROI.”

Rising costs are forcing many companies to outsource their data hosting through co-location and cloud services. This trend is leading to the construction of more mega-data center facilities, like CyrusOne’s new Chandler, Ariz., complex, which will eventually house more than 

1 million sf of data center space. By 2015, just 2% of the world’s data centers will contain 60% of the floor space, up from 52% in 2010, according to a report from Gartner Inc. 

“We will continue to see the concentration of data center floor space into a small community of dominant global players,” says HDR’s Deering.

Retrofits: A growth market

An emerging market for AEC firms is data center retrofits. The first wave of data centers—built during the dot-com boom of the late 1990s—are woefully outdated and are prime for retrofitting. Even the facilities built years later are behind the technology curve, and operators will be looking to upgrade their servers and infrastructure to meet the computing demands of today’s market.      

“Many companies are looking at the ‘capex’ versus ‘opex’ dollars and realizing that they can strike a meaningful balance between the two by simply updating, retrofitting, or renovating their existing facilities,” says Jerry Sumrell, PE, Vice President, Mission Critical with RS&H. “This presents new challenges to the design industry, as we will be devoting more time to working in live data center environments with all of the associated risks that come with it. It’s akin to performing open-heart surgery—you have to keep the facility running 24/7 while adding new equipment, decommissioning existing equipment, and transferring power/cooling from one piece of equipment to another.”

Read BD+C's full Giants 300 Report

Related Stories

High-rise Construction | Apr 23, 2015

Size matters in NYC, where several projects vie for the city’s tallest building honor

The latest renderings of 217 West 57th Street show a tower that would rise higher than the World Trade Center’s pinnacle, when elevations are included.

Green | Apr 22, 2015

AIA Committee on the Environment recognizes Top 10 Green Projects

Seattle's Bullitt Center and the University Center at The New School are among AIA's top 10 green buildings for 2015.

Office Buildings | Apr 21, 2015

Stop the endless debate over open vs. closed work environments

Rather than be confused by the constant stream of opinions, leadership teams contemplating workplace investments should start with powerful employee engagement strategies that drive results.

BIM and Information Technology | Apr 21, 2015

Software tools shouldn't dictate the AEC process

With over 200 solutions on the market, construction software is one of the most complex and fragmented markets, writes Gensler's Mark Thole.

Cultural Facilities | Apr 20, 2015

Jean Nouvel loses court battle against Philharmonie de Paris over alleged design ‘sabotage’

Nouvel boycotted the January opening of the facility and asked for his name to be removed from all references to the work. 

Sponsored | Coatings | Apr 20, 2015

Removing graffiti without a trace

The issue of graffiti removal inspired Valspar scientists to develop a graffiti resistance system, which has been tested and approved

Contractors | Apr 20, 2015

Too many construction projects don’t meet owners’ expectations: KPMG report

Causes for delays, overruns, and underperformance include project management talent shortages, distrust between owners and contractors, and the lack of fully integrated project management systems.     

High-rise Construction | Apr 17, 2015

Construction begins on Goettsch Partners-designed Nanning China Resources Center Tower

The tower's design is derived from its multiple uses, which include 170,000 sm of Class A office space, 5,000 sm of boutique retail, and a 45,000-sm luxury Shangri-La hotel.

High-rise Construction | Apr 16, 2015

Construction begins on Seattle's Tibet-inspired Potala Tower

Construction on the 41-story Potala Tower in Seattle finally kicked off following a ground-breaking ceremony seven months ago.

Building Team Awards | Apr 10, 2015

14 projects that push AEC teaming to the limits

From Lean construction to tri-party IPD to advanced BIM/VDC coordination, these 14 Building Teams demonstrate the power of collaboration in delivering award-winning buildings. These are the 2015 Building Team Award winners.

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021