Contractors should scrutinize contracts carefully amid Covid-19 crisis

Codes and Standards

Contractors should scrutinize contracts carefully amid Covid-19 crisis

Compliance with time-sensitive notice requirements and careful documentation required.


By Peter Fabris, Contributing Editor | March 23, 2020

Courtesy Pixabay

During the Covid-19 virus crisis, it is important for contractors to protect themselves from possible legal action by adhering to the provisions of current contracts, lawyers advise.

“The virus and its economic impact will almost alter pre-existing plans for owners, developers, general contractors, subcontractors, and everyone else down the chain,” according to Balch & Bingham LLP. “While many are understanding of these circumstances, there are ways to ensure you are protected going forward.” They advise:

· Review on-going contracts and locate their delay, force majeure, change order, termination, suspension and other relevant provisions.

· Comply with time-sensitive notice requirements. This includes supply agreements and insurance policies. When there is uncertainty over whether to invoke a provision in a document, consider putting the other party on notice to protect your rights.

· Scrupulously document developments. “Proving delays, labor shortages, supply interruption, and other project impacts tomorrow will depend on the evidence being created (or not being created) today.” Simple email or daily notes are acceptable to record the impacts from COVID-19.

· Check your insurance coverage. Business interruption insurance typically includes complex provisions and exclusions.

· Anticipate operational problems. “Administrative tasks might be easily completed from home while supply chains may be severely limited by a reduced and quarantined workforce thousands of miles away.” Anticipate likely problems and try to plan for them.

Related Stories

| Feb 22, 2012

ACI BIM manual for cast-in-place concrete in development

The improved communication, coordination, and collaboration afforded by BIM implementation have already been shown to save time and money in projects.

| Feb 20, 2012

Comment period for update to USGBC's LEED Green Building Program now open

This third draft of LEED has been refined to address technical stringency and rigor, measurement and performance tools, and an enhanced user experience.

| Feb 20, 2012

GAF introduces web portal for architects and specifiers

The new portal offers a clean look with minimal clutter to make it easier to find the technical information and product data that architects need.

| Feb 17, 2012

AGC advocates for federal procurement reform

Ensure that small business goals take into consideration actual small business capacity in relevant specialty markets.

| Feb 17, 2012

Codes not to blame for Anchorage roof collapses following heavy snows

Design or construction problems likely contributed to the collapses, according to city officials.

| Feb 17, 2012

Comment period opens March 1 for LEED 2012 update

USGBC says that LEED's strength comes from its continuous evolution.

| Feb 17, 2012

OSHA training videos on proper respirator use available online

17 short videos to help workers learn about the proper use of respirators on the job.

| Feb 17, 2012

Union/employer collaboration on the rise aimed at exceeding OSHA safety standards

Unions have learned to help employers win contracts with bids made competitive through good safety practices.

| Feb 16, 2012

Gain greater agility and profitability with ArchiCAD BIM software

White paper was written with the sole purpose of providing accurate, reliable information about critical issues related to BIM and what ArchiCAD with advanced technology such as the GRAPHISOFT BIM Server provide as an answer to address these issues.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021