Construction problems at prison spur support to quash non-traditional project delivery in Iowa

Codes and Standards

Construction problems at prison spur support to quash non-traditional project delivery in Iowa

Legislators may remove exceptions to design-bid-build.


By Peter Fabris, Contributing Editor | March 5, 2015
Construction problems at prison spur support to quash non-traditional project delivery in Iowa

The state university system would be one of the entities most impacted by changes to state law on project delivery. Photo: via Pixabay

Iowa lawmakers are investigating construction problems at the Fort Madison prison project and are scrutinizing rules regarding project delivery on state projects, according to a Des Moines Register report.

The prison will require $25 million to fix geothermal heating and ventilation systems. Legislators are pointing fault at the construction management arrangement that had private construction managers overseeing the project. 

In 2011, Iowa’s Department of Administrative Services eliminated the requirement for traditional design-bid-build and laid off state staff who had overseen construction projects. In the wake of sharp public scrutiny of the prison project, there is growing bi-partisan support to return project delivery rules to design-bid-build. Bills have been introduced in the state House and Senate to do just that.

The state university system would be one of the entities most impacted by changes to state law on project delivery.

Related Stories

| Mar 8, 2012

Engineering innovation provides new option for meeting seismic codes in skyscrapers

Two University of Toronto engineers have developed “viscoelastic-energy-dissipating dampers” to replace many of the heavy concrete beams used in tall structures.

| Mar 8, 2012

CSI webinar on building code compliance March 22

A March 22 webinar will provide an overview of a 28-step process during the design of a building to ensure compliance with building codes.

| Mar 8, 2012

Federal silica dust rule caught in bureaucratic limbo

A federal rule meant to protect the lungs of workers has been caught in bureaucratic purgatory for more than a year.

| Mar 8, 2012

New LEED-EBOM rating has requirements for specific project types

Several key changes are proposed for the LEED-EBOM Rating System in 2012.

| Mar 8, 2012

Green buildings more resilient than conventionally built structures

A new study by the U.S. Green Building Council (USGBC) and the University of Michigan’s Taubman College of Architecture and Urban Planning suggests that structures built to green standards can advance building resiliency.

| Mar 1, 2012

LEED Platinum standard likely to mean net-zero energy by 2018

As LEED standards continue to rise, the top level, LEED Platinum, will likely mean net-zero energy construction by 2018.

| Mar 1, 2012

EPA beefs up stormwater discharge rule from construction projects

The U.S. Environmental Protection Agency (EPA) has now finalized its 2012 construction general permit (CGP) that authorizes stormwater discharges from construction projects that disturb one or more acres of land in the areas where EPA is the permitting authority.

| Mar 1, 2012

Regulators investigate structural failures during construction of two Ohio casinos

Regulators with the Occupational Safety & Health Administration and the city of Cincinnati are investigatingthe collapse of the second floor of Cincinnati's Horseshoe Casino as workers were pouring concrete.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021