Cass Gilbert's landmark St. Louis Central Library gets a reboot

Cass Gilbert's landmark St. Louis Central Library gets a reboot

A $70 million project returns large sections of the building to their original Beaux Arts beauty, while modernizing the spaces to make them more inviting and useful for today’s patrons.


By Julie Higginbotham, Senior Editor | October 15, 2013
On the north side of St. Louiss Central Library, the Building Team created a fo
On the north side of St. Louiss Central Library, the Building Team created a four-story atrium in a wing once designed to hold

In the century since Cass Gilbert designed the flagship Central Library for the St. Louis Public Library, information science and building technology have been radically transformed. A $70 million project led by Cannon Design returned large sections of the building to their original Beaux Arts beauty, while modernizing other zones to make the library more inviting and useful for today’s patrons.

Important historic spaces, such as the central Grand Hall, have been revived, including millwork, ornamental plaster, polychrome decoration, bronze work, and marble and cork flooring. Ceiling paintings were restored, and period light fixtures were refurbished or replicated.

The Building Team replaced the outdated MEP and fire protection systems, exploiting original chases concealed within thick masonry walls. Floors in multiple areas were adapted for modern electrical and data infrastructure. The monumental front steps—565 pieces of granite in the form of slabs, balusters, railings, and wall facings—were labeled, removed, catalogued, stored, reassembled, and restored.

ST. LOUIS PUBLIC LIBRARY, CENTRAL LIBRARY
St. Louis, Mo.

 
Building Team 
Submitting firm: Cannon Design (architect) 
Owner: St. Louis Public Library 
Owner’s representative: CLR Consultants 
SE/CE, exterior restoration: David mason & Associates 
MEP/FP engineer: William Tao & Associates 
Historic preservation: Frens & Frens Environmental 
Graphics/signage: Kuhlmann Leavitt 
Construction manager: BSI Constructors
 
General Information 
Size: 185,000 sf 
Construction cost: $70 million 
Construction time: January 2010 to November 2012 
Delivery method: Design-build

The North Wing, once a repository for closed stacks, witnessed a dramatic change.

The original steel skeleton was replaced by a four-story atrium and a series of “floating” platforms. Visible through interior glazing, these levels hold compact-density shelving. A new entry canopy invites patrons to this side of the building, turning a welcoming (and less formal) face to the urban neighborhood.

Several administrative areas on the main floor were repurposed to serve children and teens, with colorful, contemporary de?cor and generous IT infrastructure. A 250-seat auditorium, built in a sub-basement once used for coal storage, creates space for performances and lectures.

The re-imagined Central Library reflects the civic ideals that inspired its founders—a place of uplift, but not a shrine. At last December’s grand opening, Director Waller McGuire emphasized the future. “Central Library isn’t finished yet,” he said. “It’ll never be finished. There will always be new possibilities and new ideas.”

 

The original Olive Street lobby, a counterpoint to the modern entry on the north side, has been meticulously restored, including the elaborate polychrome ceiling painting. The central Great Hall is accessible through the doors at the rear. Photos: Timothy Hursley

 

Reading rooms throughout the building were updated with new lighting and furniture, but historic millwork was preserved. The Building Team used both contemporary and period interior design, depending on each space’s function.

 

Related Stories

| Nov 15, 2011

Miller joins Perkins Eastman as regional manager, Middle East and Northern Africa

Miller joins Perkins Eastman with more than 48 years of experience in architecture, design management, and construction administration for planning and infrastructure.

| Nov 14, 2011

Summit Design+Build selected at GC for new Office Concepts headquarters

The new headquarters will include 17,000 sf of office space and 15,000 sf of warehouse and feature 24 ft ceilings, an open floor plan, two conference rooms and one training room and will feature sustainable finishes throughout. 

| Nov 14, 2011

Griffin Electric completes electrical work at Cary Arts Center

  The Griffin Electric team was responsible for replacing the previous electrical service on-site with a 1000A, 480/277V service and providing electrical feeds for a new fire pump chiller, six air-handlers and two elevators.

| Nov 14, 2011

303 East 33rd Street building achieves LEED-NC

  The 165,000 sf 12-story residential building is the first green development to be LEED certified in the Murray Hill neighborhood of Manhattan.

| Nov 14, 2011

VanSumeren appointed to Traco general manager

VanSumeren will draw on his more than 20 years of experience in manufacturing management and engineering to deliver operational and service excellence and drive profitable growth for Traco. 

| Nov 11, 2011

By the Numbers

What do ‘46.9,’ ‘886.2,’ and ‘171,271’ mean to you? Check here for the answer.

| Nov 11, 2011

Streamline Design-build with BIM

How construction manager Barton Malow utilized BIM and design-build to deliver a quick turnaround for Georgia Tech’s new practice facility.

| Nov 11, 2011

AIA: Engineered Brick + Masonry for Commercial Buildings

Earn 1.0 AIA/CES learning units by studying this article and successfully completing the online exam. 

| Nov 11, 2011

How Your Firm Can Win Federal + Military Projects

The civilian and military branches of the federal government are looking for innovative, smart-thinking AEC firms to design and construct their capital projects. Our sources give you the inside story.

boombox1
boombox2
native1

More In Category


Retail Centers

Thinking outside the big box (store)

For over a decade now, the talk of the mall industry has been largely focused on what developers can do to fill the voids left by a steady number of big box store closures. But what do you do when big box tenants stay put?


Government Buildings

OSHA’s proposed heat standard published in Federal Register

The Occupational Safety and Health Administration (OSHA) has published a proposed standard addressing heat illness in outdoor and indoor settings in the Federal Register. The proposed rule would require employers to evaluate workplaces and implement controls to mitigate exposure to heat through engineering and administrative controls, training, effective communication, and other measures.


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021