Cass Gilbert's landmark St. Louis Central Library gets a reboot

Cass Gilbert's landmark St. Louis Central Library gets a reboot

A $70 million project returns large sections of the building to their original Beaux Arts beauty, while modernizing the spaces to make them more inviting and useful for today’s patrons.


By Julie Higginbotham, Senior Editor | October 15, 2013
On the north side of St. Louiss Central Library, the Building Team created a fo
On the north side of St. Louiss Central Library, the Building Team created a four-story atrium in a wing once designed to hold

In the century since Cass Gilbert designed the flagship Central Library for the St. Louis Public Library, information science and building technology have been radically transformed. A $70 million project led by Cannon Design returned large sections of the building to their original Beaux Arts beauty, while modernizing other zones to make the library more inviting and useful for today’s patrons.

Important historic spaces, such as the central Grand Hall, have been revived, including millwork, ornamental plaster, polychrome decoration, bronze work, and marble and cork flooring. Ceiling paintings were restored, and period light fixtures were refurbished or replicated.

The Building Team replaced the outdated MEP and fire protection systems, exploiting original chases concealed within thick masonry walls. Floors in multiple areas were adapted for modern electrical and data infrastructure. The monumental front steps—565 pieces of granite in the form of slabs, balusters, railings, and wall facings—were labeled, removed, catalogued, stored, reassembled, and restored.

ST. LOUIS PUBLIC LIBRARY, CENTRAL LIBRARY
St. Louis, Mo.

 
Building Team 
Submitting firm: Cannon Design (architect) 
Owner: St. Louis Public Library 
Owner’s representative: CLR Consultants 
SE/CE, exterior restoration: David mason & Associates 
MEP/FP engineer: William Tao & Associates 
Historic preservation: Frens & Frens Environmental 
Graphics/signage: Kuhlmann Leavitt 
Construction manager: BSI Constructors
 
General Information 
Size: 185,000 sf 
Construction cost: $70 million 
Construction time: January 2010 to November 2012 
Delivery method: Design-build

The North Wing, once a repository for closed stacks, witnessed a dramatic change.

The original steel skeleton was replaced by a four-story atrium and a series of “floating” platforms. Visible through interior glazing, these levels hold compact-density shelving. A new entry canopy invites patrons to this side of the building, turning a welcoming (and less formal) face to the urban neighborhood.

Several administrative areas on the main floor were repurposed to serve children and teens, with colorful, contemporary de?cor and generous IT infrastructure. A 250-seat auditorium, built in a sub-basement once used for coal storage, creates space for performances and lectures.

The re-imagined Central Library reflects the civic ideals that inspired its founders—a place of uplift, but not a shrine. At last December’s grand opening, Director Waller McGuire emphasized the future. “Central Library isn’t finished yet,” he said. “It’ll never be finished. There will always be new possibilities and new ideas.”

 

The original Olive Street lobby, a counterpoint to the modern entry on the north side, has been meticulously restored, including the elaborate polychrome ceiling painting. The central Great Hall is accessible through the doors at the rear. Photos: Timothy Hursley

 

Reading rooms throughout the building were updated with new lighting and furniture, but historic millwork was preserved. The Building Team used both contemporary and period interior design, depending on each space’s function.

 

Related Stories

| Aug 8, 2013

Top Science and Technology Sector Engineering Firms [2013 Giants 300 Report]

Affiliated Engineers, Middough, URS top Building Design+Construction's 2013 ranking of the largest science and technology sector engineering and engineering/architecture firms in the U.S.

| Aug 8, 2013

Top Science and Technology Sector Architecture Firms [2013 Giants 300 Report]

HDR, Perkins+Will, HOK top Building Design+Construction's 2013 ranking of the largest science and technology sector architecture and architecture/engineering firms in the U.S.

| Aug 8, 2013

Top Science and Technology Sector Construction Firms [2013 Giants 300 Report]

Skanska, DPR, Suffolk top Building Design+Construction's 2013 ranking of the largest science and technology sector contractors and construction management firms in the U.S.

| Aug 8, 2013

Level of Development: Will a new standard bring clarity to BIM model detail?

The newly released LOD Specification document allows Building Teams to understand exactly what’s in the BIM model they’re being handed.

| Aug 8, 2013

Blueprint for a boom town: Potential pitfalls for booming development

Accolades for Nashville, Tenn., my hometown and GS&P’s flagship location, just keep piling up. In 2011, Forbes named Nashville No. 3 on their list of “The Next Big Boom Towns in the U.S." All of these accolades are wonderful, but Nashville now must work hard to prove their longevity—to grow and build intelligently.

| Aug 8, 2013

Does billing by the hour still make sense?

What’s an idea really worth? That’s the question posed by The New York Times in a provocative article that explores whether the notion of billing time still makes economic sense. 

| Aug 8, 2013

Vertegy spins off to form independent green consultancy

St. Louis-based Vertegy has announced the formation of Vertegy, LLC, transitioning into an independent company separate from the Alberici Enterprise. The new company was officially unveiled Aug. 1, 2013

| Aug 6, 2013

CoreNet: Office space per worker shrinks to 150 sf

The average amount of space per office worker globally has dropped to 150 square feet or less, from 225 square feet in 2010, according to a recent global survey conducted by CoreNet Global.

| Aug 6, 2013

Australia’s first net zero office building features distinctive pixelated façade

Australia's first carbon neutral office building, featuring a distinctive pixelated façade, recently opened in Melbourne.

| Aug 5, 2013

Top Retail Architecture Firms [2013 Giants 300 Report]

Callison, Stantec, Gensler top Building Design+Construction's 2013 ranking of the largest retail architecture and architecture/engineering firms in the United States.

boombox1
boombox2
native1

More In Category

Warehouses

California bill would limit where distribution centers can be built

A bill that passed the California legislature would limit where distribution centers can be located and impose other rules aimed at reducing air pollution and traffic. Assembly Bill 98 would tighten building standards for new warehouses and ban heavy diesel truck traffic next to sensitive sites including homes, schools, parks and nursing homes.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021