Cass Gilbert's landmark St. Louis Central Library gets a reboot

Cass Gilbert's landmark St. Louis Central Library gets a reboot

A $70 million project returns large sections of the building to their original Beaux Arts beauty, while modernizing the spaces to make them more inviting and useful for today’s patrons.


By Julie Higginbotham, Senior Editor | October 15, 2013
On the north side of St. Louiss Central Library, the Building Team created a fo
On the north side of St. Louiss Central Library, the Building Team created a four-story atrium in a wing once designed to hold

In the century since Cass Gilbert designed the flagship Central Library for the St. Louis Public Library, information science and building technology have been radically transformed. A $70 million project led by Cannon Design returned large sections of the building to their original Beaux Arts beauty, while modernizing other zones to make the library more inviting and useful for today’s patrons.

Important historic spaces, such as the central Grand Hall, have been revived, including millwork, ornamental plaster, polychrome decoration, bronze work, and marble and cork flooring. Ceiling paintings were restored, and period light fixtures were refurbished or replicated.

The Building Team replaced the outdated MEP and fire protection systems, exploiting original chases concealed within thick masonry walls. Floors in multiple areas were adapted for modern electrical and data infrastructure. The monumental front steps—565 pieces of granite in the form of slabs, balusters, railings, and wall facings—were labeled, removed, catalogued, stored, reassembled, and restored.

ST. LOUIS PUBLIC LIBRARY, CENTRAL LIBRARY
St. Louis, Mo.

 
Building Team 
Submitting firm: Cannon Design (architect) 
Owner: St. Louis Public Library 
Owner’s representative: CLR Consultants 
SE/CE, exterior restoration: David mason & Associates 
MEP/FP engineer: William Tao & Associates 
Historic preservation: Frens & Frens Environmental 
Graphics/signage: Kuhlmann Leavitt 
Construction manager: BSI Constructors
 
General Information 
Size: 185,000 sf 
Construction cost: $70 million 
Construction time: January 2010 to November 2012 
Delivery method: Design-build

The North Wing, once a repository for closed stacks, witnessed a dramatic change.

The original steel skeleton was replaced by a four-story atrium and a series of “floating” platforms. Visible through interior glazing, these levels hold compact-density shelving. A new entry canopy invites patrons to this side of the building, turning a welcoming (and less formal) face to the urban neighborhood.

Several administrative areas on the main floor were repurposed to serve children and teens, with colorful, contemporary de?cor and generous IT infrastructure. A 250-seat auditorium, built in a sub-basement once used for coal storage, creates space for performances and lectures.

The re-imagined Central Library reflects the civic ideals that inspired its founders—a place of uplift, but not a shrine. At last December’s grand opening, Director Waller McGuire emphasized the future. “Central Library isn’t finished yet,” he said. “It’ll never be finished. There will always be new possibilities and new ideas.”

 

The original Olive Street lobby, a counterpoint to the modern entry on the north side, has been meticulously restored, including the elaborate polychrome ceiling painting. The central Great Hall is accessible through the doors at the rear. Photos: Timothy Hursley

 

Reading rooms throughout the building were updated with new lighting and furniture, but historic millwork was preserved. The Building Team used both contemporary and period interior design, depending on each space’s function.

 

Related Stories

Transit Facilities | Feb 4, 2015

London mayor approves plan for a bicycle highway

The plan will guarantee bike riders a designated stretch of street to ride from east to west through the city.

Sports and Recreational Facilities | Feb 4, 2015

Arup unveils plans for the new A.C. Milan stadium

The venue will include a modern stage for the home matches together with a hotel, sports college, restaurants, children’s playground, green areas, and spaces open to the city and dedicated to public use.

Higher Education | Feb 3, 2015

Integrated Learning Neighborhoods: A solution for linking student housing with the typical student experience

Just as urban housing fits into the city as a whole, student housing can be integrated into the campus network as a series of living/learning neighborhoods, write Gensler's Brian Watson and Mark McMinn.

Office Buildings | Feb 3, 2015

5 trends transforming workplace design

RTKL's workplace design expert Jodi Williams foresees healthier and more technologically enabled offices that allow productive worker interaction, wherever they happen to be.

Office Buildings | Feb 3, 2015

Bjarke Ingels' BIG proposes canopied, vertical village for Middle East media company

The tensile canopy shades a relaxation plaza from the desert sun.

Fire-Rated Products | Feb 3, 2015

AIA course: Fire and life safety in large buildings

Earn 1.0 AIA/CES learning units by studying this article and successfully completing the online exam.

Multifamily Housing | Feb 2, 2015

D.C. developer sees apartment project as catalyst for modeling neighborhood after N.Y.'s popular High Line district

It’s no accident that the word “Highline” is in this project’s name. The goal is for the building to be a kind of gateway into the larger redevelopment of the surrounding neighborhood to resemble New York’s City’s trendy downtown Meatpacking District, through which runs a portion the High Line elevated park.

Sponsored | Products and Materials | Feb 2, 2015

What should you consider when reviewing paint warranties?

Warranties can appear to be the same, but as a starting point, you should find out what paint technology your warranty is based on—polyester, silicon-modified polyester or PVDF. Once you’ve established an “apples to apples” comparison with the technologies, you must consider the color palette and its impact on warranty longevity. Review this with your builder, manufacturer or paint company representative. 

Healthcare Facilities | Feb 1, 2015

7 new factors shaping hospital emergency departments

A new generation of highly efficient emergency care facilities is upping the ante on patient care and convenience while helping to reposition hospital systems within their local markets.

Multifamily Housing | Jan 31, 2015

5 intriguing trends to track in the multifamily housing game

Demand for rental apartments and condos hasn’t been this strong in years, and our experts think the multifamily sector still has legs. But you have to know what developers, tenants, and buyers are looking for to have any hope of succeeding in this fast-changing market sector.

boombox1
boombox2
native1

More In Category


Warehouses

California bill would limit where distribution centers can be built

A bill that passed the California legislature would limit where distribution centers can be located and impose other rules aimed at reducing air pollution and traffic. Assembly Bill 98 would tighten building standards for new warehouses and ban heavy diesel truck traffic next to sensitive sites including homes, schools, parks and nursing homes.



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021