Calculating the ROI of building enclosure commissioning

Calculating the ROI of building enclosure commissioning

A researcher at Lawrence Berkeley National Laboratory calls building enclosure commissioning “the single-most cost-effective strategy for reducing energy, costs, and greenhouse gas emissions in buildings today.”


By C.C. Sullivan | June 28, 2013
According to Evan Mills, PhD, a researcher at Lawrence Berkeley National Laboratory, building enclosure commissioning, or BECx, should be viewed as “the single-most cost-effective strategy for reducing energy, costs, and greenhouse gas emissions in buildings today.”
 
(This article excerpted from BD+C's June 2013 AIA/CES course on cladding and exterior insulation. Take this free course at BD+C University.)
 
Mills studied the benefits of BECx, noting that commissioning only costs about $1.16/sf for new construction and $0.30/sf for existing buildings on average, with a payback period of as little as 14 months. Savings associated with using BECx from both maintenance and energy savings average about 16% for existing buildings and 13% for new construction. The main benefit is that whole-building energy savings are guaranteed, thanks to the pivotal role of the enclosure in determining efficiency performance.
 
“Further enhancing the value of commissioning, its non-energy benefits surpass those of most other energy-management practices,” including major first-cost savings through right-sizing of HVAC equipment, Mills has testified. “When accounting for these benefits, the net median commissioning project cost was reduced by 49% on average, while in many cases they exceeded the direct value of the energy savings.”
 
The National Institute of Building Sciences published its NIBS Guideline 3-2012 on enclosure commissioning last year. The U.S. Green Building Council has allowed the application of BECx to earn an innovation credit in the LEED rating system, and BECx was even considered as a prerequisite, but that proposal lost momentum, says Rob Kistler, AIA, NCARB, Committee Chair for NIBS Guideline 3 and Principal, The Facade Group.
 
It appears that LEED v4 will not explicitly encourage the detail review, onsite testing, and observation that some enclosure experts say is what makes BECx effective, notes Tristan Roberts, with BuildingGreen’s LEEDUser service. Instead, the new LEED draft language directly quotes NIBS Guideline 3, which describes the following techniques as part of proper BECx for enhanced building commissioning:
•  Devise a plan early in the project cycle that describes testing requirements, acceptance criteria, and documentation.
•  Review details in the construction documentation to check for overall performance, continuity of weather barriers and insulation, and constructability.
•  Conduct observations on the job site as required for critical milestones in enclosure installation, from field mockups to trades startup to field testing.
•  Use mockups to benchmark workmanship requirements and ensure compliance with specifications and manufacturer’s installation requirements.
 
The NIBS committee for BECx, which Altenhofen serves on, recommends including a consulting enclosure expert for the building project, especially in the construction administration phase. The expert will help ensure proposed cladding materials and systems are integrated properly into the design process, followed by visual observations of a statistical sampling of installation of work. Toward the end of the CA phase and before acceptance, a blower-door test will check whether the air infiltration levels are equal to or better than standard.
 
As noted in the summary of NIBS Guideline 3, BECx helps reduce the chances that inadequate cladding work will be discovered during the punch list phase: “The performance of the enclosure cannot be verified until the entire building is completely enclosed. At this time it is not possible to tune or dial in the performance. To access a nonperforming subsystem or assembly might be very expensive.”
 
(This article excerpted from BD+C's June 2013 AIA/CES course on cladding and exterior insulation. Take this free course at BD+C University.)

Related Stories

| Aug 11, 2010

Wisconsin becomes the first state to require BIM on public projects

As of July 1, the Wisconsin Division of State Facilities will require all state projects with a total budget of $5 million or more and all new construction with a budget of $2.5 million or more to have their designs begin with a Building Information Model. The new guidelines and standards require A/E services in a design-bid-build project delivery format to use BIM and 3D software from initial ...

| Aug 11, 2010

Opening night close for Kent State performing arts center

The curtain opens on the Tuscarawas Performing Arts Center at Kent State University in early 2010, giving the New Philadelphia, Ohio, school a 1,100-seat multipurpose theater. The team of Legat & Kingscott of Columbus, Ohio, and Schorr Architects of Dublin, Ohio, designed the 50,000-sf facility with a curving metal and glass façade to create a sense of movement and activity.

| Aug 11, 2010

Residence hall designed specifically for freshman

Hardin Construction Company's Austin, Texas, office is serving as GC for the $50 million freshman housing complex at the University of Houston. Designed by HADP Architecture, Austin, the seven-story, 300,000-sf facility will be located on the university's central campus and have 1,172 beds, residential advisor offices, a social lounge, a computer lab, multipurpose rooms, a fitness center, and a...

| Aug 11, 2010

News Briefs: GBCI begins testing for new LEED professional credentials... Architects rank durability over 'green' in product attributes... ABI falls slightly in April, but shows market improvement

News Briefs: GBCI begins testing for new LEED professional credentials... Architects rank durability over 'green' in product attributes... ABI falls slightly in April, but shows market improvement

| Aug 11, 2010

Luxury Hotel required faceted design

Goettsch Partners, Chicago, designed a new five-star, 214-room hotel for the King Abdullah Financial District (KAFD) in Riyadh, Saudi Arabia. The design-build project, with Saudi Oger Ltd. as contractor and Rayadah Investment Co. as developer, has a three-story podium supporting a 17-story glass tower with a nine-story opening that allows light to penetrate the mass of the building.

| Aug 11, 2010

Three Schools checking into L.A.'s Ambassador Hotel site

Pasadena-based Gonzalez Goodale Architects is designing three new schools for Los Angeles Unified School District's Central Wilshire District. The $400 million campus, located on the site of the former Ambassador Hotel, will house a K-5 elementary school, a middle school, a high school, a shared recreation facility (including soccer field, 25-meter swimming pool, two gymnasiums), and a new publ...

| Aug 11, 2010

New Jersey's high-tech landscaping facility

Designed to enhance the use of science and technology in Bergen County Special Services' landscaping programs, the new single-story facility at the technical school's Paramus campus will have 7,950 sf of classroom space, a 1,000-sf greenhouse (able to replicate different environments, such as rainforest, desert, forest, and tundra), and 5,000 sf of outside landscaping and gardening space.

| Aug 11, 2010

U.S. firm designing massive Taiwan project

MulvannyG2 Architecture is designing one of Taipei, Taiwan's largest urban redevelopment projects. The Bellevue, Wash., firm is working with developer The Global Team Group to create Aquapearl, a mixed-use complex that's part of the Taipei government's "Good Looking Taipei 2010" initiative to spur redevelopment of the city's Songjian District.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021