Calculating the ROI of building enclosure commissioning

Calculating the ROI of building enclosure commissioning

A researcher at Lawrence Berkeley National Laboratory calls building enclosure commissioning “the single-most cost-effective strategy for reducing energy, costs, and greenhouse gas emissions in buildings today.”


By C.C. Sullivan | June 28, 2013
According to Evan Mills, PhD, a researcher at Lawrence Berkeley National Laboratory, building enclosure commissioning, or BECx, should be viewed as “the single-most cost-effective strategy for reducing energy, costs, and greenhouse gas emissions in buildings today.”
 
(This article excerpted from BD+C's June 2013 AIA/CES course on cladding and exterior insulation. Take this free course at BD+C University.)
 
Mills studied the benefits of BECx, noting that commissioning only costs about $1.16/sf for new construction and $0.30/sf for existing buildings on average, with a payback period of as little as 14 months. Savings associated with using BECx from both maintenance and energy savings average about 16% for existing buildings and 13% for new construction. The main benefit is that whole-building energy savings are guaranteed, thanks to the pivotal role of the enclosure in determining efficiency performance.
 
“Further enhancing the value of commissioning, its non-energy benefits surpass those of most other energy-management practices,” including major first-cost savings through right-sizing of HVAC equipment, Mills has testified. “When accounting for these benefits, the net median commissioning project cost was reduced by 49% on average, while in many cases they exceeded the direct value of the energy savings.”
 
The National Institute of Building Sciences published its NIBS Guideline 3-2012 on enclosure commissioning last year. The U.S. Green Building Council has allowed the application of BECx to earn an innovation credit in the LEED rating system, and BECx was even considered as a prerequisite, but that proposal lost momentum, says Rob Kistler, AIA, NCARB, Committee Chair for NIBS Guideline 3 and Principal, The Facade Group.
 
It appears that LEED v4 will not explicitly encourage the detail review, onsite testing, and observation that some enclosure experts say is what makes BECx effective, notes Tristan Roberts, with BuildingGreen’s LEEDUser service. Instead, the new LEED draft language directly quotes NIBS Guideline 3, which describes the following techniques as part of proper BECx for enhanced building commissioning:
•  Devise a plan early in the project cycle that describes testing requirements, acceptance criteria, and documentation.
•  Review details in the construction documentation to check for overall performance, continuity of weather barriers and insulation, and constructability.
•  Conduct observations on the job site as required for critical milestones in enclosure installation, from field mockups to trades startup to field testing.
•  Use mockups to benchmark workmanship requirements and ensure compliance with specifications and manufacturer’s installation requirements.
 
The NIBS committee for BECx, which Altenhofen serves on, recommends including a consulting enclosure expert for the building project, especially in the construction administration phase. The expert will help ensure proposed cladding materials and systems are integrated properly into the design process, followed by visual observations of a statistical sampling of installation of work. Toward the end of the CA phase and before acceptance, a blower-door test will check whether the air infiltration levels are equal to or better than standard.
 
As noted in the summary of NIBS Guideline 3, BECx helps reduce the chances that inadequate cladding work will be discovered during the punch list phase: “The performance of the enclosure cannot be verified until the entire building is completely enclosed. At this time it is not possible to tune or dial in the performance. To access a nonperforming subsystem or assembly might be very expensive.”
 
(This article excerpted from BD+C's June 2013 AIA/CES course on cladding and exterior insulation. Take this free course at BD+C University.)

Related Stories

| Jan 3, 2012

AIA Course: New Developments in Concrete Construction

Earn 1.0 AIA/CES learning units by studying this article and successfully completing the online exam.

| Jan 3, 2012

The Value of Historic Paint Investigations

An expert conservator provides a three-step approach to determining a historic building’s “period of significance”—and how to restore its painted surfaces to the correct patterns and colors. 

| Jan 3, 2012

28th Annual Reconstruction Awards: Bringing Hope to Cancer Patients

A gothic-style structure is reconstructed into comfortable, modern patient residence facility for the American Cancer Society.

| Jan 3, 2012

Art Gensler: Still Making a Difference for Clients Every Day

After running what is today the largest architecture firm in the world for more than four decades, M. Arthur Gensler, Jr., FAIA, FIIDA, RIBA, is content to be just another employee at the firm that bears his name. 

| Jan 3, 2012

Gensler: 'The One Firm Firm'

The giant architecture firm succeeds by giving each of its more than 3,000 employees the opportunity for career growth and professional leadership. 

| Jan 3, 2012

Rental Renaissance, The Rebirth of the Apartment Market

Across much of the U.S., apartment rents are rising, vacancy rates are falling. In just about every major urban area, new multifamily rental projects and major renovations are coming online. It may be too soon to pronounce the rental market fully recovered, but the trend is promising.

| Dec 29, 2011

OSHA enforcing new fall hazard standards

OSHA is enforcing its new fall protection standards, as evidenced by a recent crackdown in New York.

| Dec 29, 2011

Decision not to fireproof the new World Trade Center Transportation Hub criticized

Some criticized the decision, reasoning that the structure could be a terrorist target.

| Dec 29, 2011

Seismic safety in question at thousands of California public schools

California regulators responsible for enforcing earthquake safety laws have failed to certify more than 16,000 construction projects in California public schools, increasing the risk that some projects may be unsafe, according to a state audit report.

| Dec 29, 2011

GreenWizard offers cloud-based LEED credit management, assessment

The company recently began offering companies the ability to run assessments for design credits, in addition to traditional product-specific LEED credits.

boombox1
boombox2
native1

More In Category



Urban Planning

The magic of L.A.’s Melrose Mile

Great streets are generally not initially curated or willed into being. Rather, they emerge organically from unintentional synergies of commercial, business, cultural and economic drivers. L.A.’s Melrose Avenue is a prime example. 


Curtain Wall

7 steps to investigating curtain wall leaks

It is common for significant curtain wall leakage to involve multiple variables. Therefore, a comprehensive multi-faceted investigation is required to determine the origin of leakage, according to building enclosure consultants Richard Aeck and John A. Rudisill with Rimkus. 

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021