Calculating the ROI of building enclosure commissioning

Calculating the ROI of building enclosure commissioning

A researcher at Lawrence Berkeley National Laboratory calls building enclosure commissioning “the single-most cost-effective strategy for reducing energy, costs, and greenhouse gas emissions in buildings today.”


By C.C. Sullivan | June 28, 2013
According to Evan Mills, PhD, a researcher at Lawrence Berkeley National Laboratory, building enclosure commissioning, or BECx, should be viewed as “the single-most cost-effective strategy for reducing energy, costs, and greenhouse gas emissions in buildings today.”
 
(This article excerpted from BD+C's June 2013 AIA/CES course on cladding and exterior insulation. Take this free course at BD+C University.)
 
Mills studied the benefits of BECx, noting that commissioning only costs about $1.16/sf for new construction and $0.30/sf for existing buildings on average, with a payback period of as little as 14 months. Savings associated with using BECx from both maintenance and energy savings average about 16% for existing buildings and 13% for new construction. The main benefit is that whole-building energy savings are guaranteed, thanks to the pivotal role of the enclosure in determining efficiency performance.
 
“Further enhancing the value of commissioning, its non-energy benefits surpass those of most other energy-management practices,” including major first-cost savings through right-sizing of HVAC equipment, Mills has testified. “When accounting for these benefits, the net median commissioning project cost was reduced by 49% on average, while in many cases they exceeded the direct value of the energy savings.”
 
The National Institute of Building Sciences published its NIBS Guideline 3-2012 on enclosure commissioning last year. The U.S. Green Building Council has allowed the application of BECx to earn an innovation credit in the LEED rating system, and BECx was even considered as a prerequisite, but that proposal lost momentum, says Rob Kistler, AIA, NCARB, Committee Chair for NIBS Guideline 3 and Principal, The Facade Group.
 
It appears that LEED v4 will not explicitly encourage the detail review, onsite testing, and observation that some enclosure experts say is what makes BECx effective, notes Tristan Roberts, with BuildingGreen’s LEEDUser service. Instead, the new LEED draft language directly quotes NIBS Guideline 3, which describes the following techniques as part of proper BECx for enhanced building commissioning:
•  Devise a plan early in the project cycle that describes testing requirements, acceptance criteria, and documentation.
•  Review details in the construction documentation to check for overall performance, continuity of weather barriers and insulation, and constructability.
•  Conduct observations on the job site as required for critical milestones in enclosure installation, from field mockups to trades startup to field testing.
•  Use mockups to benchmark workmanship requirements and ensure compliance with specifications and manufacturer’s installation requirements.
 
The NIBS committee for BECx, which Altenhofen serves on, recommends including a consulting enclosure expert for the building project, especially in the construction administration phase. The expert will help ensure proposed cladding materials and systems are integrated properly into the design process, followed by visual observations of a statistical sampling of installation of work. Toward the end of the CA phase and before acceptance, a blower-door test will check whether the air infiltration levels are equal to or better than standard.
 
As noted in the summary of NIBS Guideline 3, BECx helps reduce the chances that inadequate cladding work will be discovered during the punch list phase: “The performance of the enclosure cannot be verified until the entire building is completely enclosed. At this time it is not possible to tune or dial in the performance. To access a nonperforming subsystem or assembly might be very expensive.”
 
(This article excerpted from BD+C's June 2013 AIA/CES course on cladding and exterior insulation. Take this free course at BD+C University.)

Related Stories

Great Solutions | May 5, 2017

No nails necessary: Framing system comes together with steel zip ties and screws

Clemson University’s School of Architecture develops a patent-pending construction method that is gaining attention for its potential use in rapid, low-tech sustainable housing.

Multifamily Housing | May 3, 2017

Silicon Valley’s high-tech oasis

An award-winning rental complex takes its design cues from its historic location in Silicon Valley.

Architects | May 3, 2017

Avoiding trouble in paradise: Tips on building successfully in the Caribbean

The island setting itself is at the root of several of these disruptive assumptions.

Multifamily Housing | May 2, 2017

Multifamily housing: 7 exciting, inspiring innovations [AIA Course]

This AIA CES course features seven novel approaches developers and Building Teams are taking to respond to competitive pressures and build more quickly and with more attractive offerings.

Healthcare Facilities | May 1, 2017

Designing patient rooms for the entire family can improve patient satisfaction and outcomes

Hospital rooms are often not designed to accommodate extended stays for anyone other than the patient, which can have negative effects on patient outcome.

Architects | Apr 27, 2017

Number of U.S. architects holds steady, while professional mobility increases

New data from NCARB reveals that while the number of architects remains consistent, practitioners are looking to get licensed in multiple states.

Multifamily Housing | Apr 26, 2017

Multifamily amenity trends: The latest in package delivery centers

Package delivery centers provide order and security for the mountains of parcels piling up at apartment and condominium communities.

Multifamily Housing | Apr 26, 2017

Huh? A subway car on the roof?

Chicago’s newest multifamily development features an iconic CTA car on its amenity deck. 

High-rise Construction | Apr 26, 2017

Dubai’s newest building is a giant gilded picture frame

Despite currently being under construction, the building is the center of an ongoing lawsuit filed by the architect.

boombox1
boombox2
native1

More In Category

Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021