TSX Broadway is a 550,000-sf 46-story mixed-use tower that’s been under construction in New York City’s Times Square since 2019. This $2.5 billion project—whose development partners include L&L Holding, Maefield Development, Fortress Investment, and The Nederlander Organization—has retained 25 percent of site’s existing structure that included 16 stories of what had been a DoubleTree hotel, and the iconic Palace Theater, which on January 7 began its journey from the ground floor of this site to being lifted and repositioned 30 ft above grade to make way for 75,000 sf of street-level retail.
The lift of the 7,000-plus-ton, 27,000-sf theater with landmark status was expected to take six to eight weeks, at which point the Palace Theater will undergo a $50 million renovation that includes a new entrance on 47th Street with an 80-ft marquee, the addition of 10,000 sf of front-of-house space with a new lobby, a new orchestra pit for the 1,700-seat theater, and more back-of-house space.
Last week, the project’s Building Team poured the 43rd floor of TSX Broadway, which along with the theater is scheduled for completion in the fourth quarter of 2022, according to Robert Israel, Executive Vice President of L&L Holding and the firm’s project manager, with whom BD+C spoke earlier this week.
Also see: An animation of the demolition, excavation, and theater lift
HEAVY LIFTING
![Hydraulic jacks used to raise the theater](/sites/default/files/inline-images/%2ATSX%20Broadway%20Theatre%20Lift%20January%202022%20Day%202-54.jpg)
This project, he said, required a new permanent foundation, a new subcellar level, and a lifting foundation. The lift itself is utilizing a mechanism, devised by Urban Foundation Engineering, that combines 34 structural lifting posts and 136 hydraulic jacks. Israel said that the developers hired the structural engineering consultant Howard Shapiro & Associates to ensure the security and stability of the structure and theater, which was originally built in 1913 and remodeled in 1988.
The 580-ft-tall tower, when completed, will also feature a 669-key hotel (Israel said the developers were close to signing a branding and property management deal, but could not disclose the hotelier).
RISING ABOVE THE NOISE
![Exterior lighting systems for TSX Broadway](/sites/default/files/inline-images/TSX%20Broadway%20Mancini%20Duffy.png)
The building will also have several signage and lighting systems, all designed for marketing purposes: the exterior of floors three through nine will be distinguished by an 18,000-sf LED podium sign into which is integrated an indoor-outdoor stage with a 30x30-ft opening and a 35-ft depth that extends 10 ft outside beyond the LED lights. Israel suggested that this space could be used for New Year’s Eve events, and all manner of performances and broadcasts.
There will also be crown signage at the top of the building, and a full-tower lighting system, dubbed The Beacon, that will be able to project programmed messages and images.
Also see: How TSX Broadway will become the world’s largest billboard
TSX Broadway’s Building Team includes Mancini Duffy (AOR core and shell and hotel), PBDW Architects (AOR theater design and historic preservation), Jablonski Building Conservation (historic preservation consultant), Wise Janney Elsner Engineers & Architects (plaster structural support consultant), Cosentini (MEP), Langan (SOE/foundation engineering consultant), Severud (SE), and Perkins Eastman (lead design of building envelope).
Related Stories
| Oct 15, 2014
First look: Blueprint revealed for proposed High Line project in Queens
Yet another High Line-esque project has been proposed, this time in Queens. A blueprint has been developed for a 3.5-mile stretch of abandoned railroad tracks, which would connect Rego Park to Ozone Park with a walkway and bike path.
| Oct 14, 2014
Proven 6-step approach to treating historic windows
This course provides step-by-step prescriptive advice to architects, engineers, and contractors on when it makes sense to repair or rehabilitate existing windows, and when they should advise their building owner clients to consider replacement.
| Oct 12, 2014
AIA 2030 commitment: Five years on, are we any closer to net-zero?
This year marks the fifth anniversary of the American Institute of Architects’ effort to have architecture firms voluntarily pledge net-zero energy design for all their buildings by 2030.
| Oct 10, 2014
A new memorial by Zaha Hadid in Cambodia departs from the expected
The project sees a departure from Hadid’s well-known use of concrete, fiberglass, and resin. Instead, the primary material will be timber, curved and symmetrical like the Angkor Wat and other Cambodian landmarks.
| Oct 8, 2014
First look: Woods Bagot unveils plans for new Christchurch Convention Center
The locally-inspired building is meant to serve as a symbol of the city's recovery from the earthquake of 2011.
| Oct 6, 2014
Frank Gehry's $100 million Eisenhower Memorial gets preliminary approval
After a rejection earlier in the year, Frank Gehry has gotten some good news: his revised design for the Dwight D. Eisenhower Memorial has received approval from the National Capital Planning Commission.
| Oct 2, 2014
Budget busters: Report details 24 of the world's most obscenely over-budget construction projects
Montreal's Olympic Stadium and the Sydney Opera House are among the landmark projects to bust their budgets, according to a new interactive graph by Podio.
| Oct 1, 2014
10 iconic modern buildings first to receive 'Keeping it Modern' conservation grants from the Getty Foundation
Frank Lloyd Wright's Robie House and Jørn Utzon’s Sydney Opera House are among the buildings to receive grants.
| Sep 29, 2014
Snøhetta releases final plan for terraced central library in Calgary
The competition-winning New Central Library is now in the final design stages, after two years of community engagement on the part of design firms Snøhetta and DIALOG.
| Sep 25, 2014
Jean Nouvel unveils plans for National Art Museum of China
Of the design, Nouvel describes it as inspired by the simplicity of “a single brush stroke.”