Building 13 Naval Station, Great Lakes, Ill.

Building 13 Naval Station, Great Lakes, Ill.


By BY Robert Cassidy, Editorial Director | October 12, 2010

Designed by Chicago architect Jarvis Hunt and constructed in 1903, Building 13 is one of 39 structures within the Great Lakes Historic District at Naval Station Great Lakes, Ill. The original boathouse, considered a “contributing structure with major significance,” reflects the Beaux Arts vocabulary and classical forms that Hunt applied to his work (1902-1911) at the Naval Station campus.

After more than a century of use, however, the building envelope, brick, terra cotta, windows, and roof were in sore need of repair, even as the Navy was seeking to expand the function of the nearly 27,000-sf boathouse to support year-round marine activity of the Great Lakes harbor with the addition of shops, classrooms, offices, toilets, and showers. However, any renovation had to be done within the strict guidelines of the Secretary of the Interior Standards for Rehabilitation, the National Historic Preservation Act, and the Base Exterior Architecture Plan (BEAP).

The design-build team, led by Chicago firm Johnson Lasky Architects, took on the structural problems more or less from top to bottom. Visual and physical inspections, materials testing (including brick and mortar analyses), and soundings on each individual terra cotta unit were conducted.

The roof was replaced with shingles over three-inch polyiso ventilated nail base insulation panels. Forty-year asphalt shingles rated for 110 mph wind loads were used to meet the BEAP’s historic requirements. New copper gutters, flashings, and terminations were installed.

At the turn of the 20th century, terra cotta was used as a mass-produced alternative to carved stone, and Hunt made extensive use of it in Building 13. Damaged terra cotta was replaced with new matching material from California manufacturer Gladding McBean. Brick was salvaged from Navy supplies of matching historic brick. Mortar was replicated based on an analysis of existing original material. New exterior doors replicated the original wood panel design. The glass transom above the main entrance door was fitted with laminated glass.

Windows were completely restored off site; missing glass was replaced with glazing that matched the original in texture, thickness, and type (“wavy”) to meet state historical preservation standards.

 With the building now providing year-round use, it was necessary to upgrade the mechanical system to forced air, with an air handler, ductwork, controls, and other equipment. The Building Team solved this problem by housing a new mechanical room between two existing mezzanines on opposite sides of the building within the warehouse.

In granting the project a Gold Award, the jury praised the Building Team’s attention to detail. “They had to tackle a lot of different components: brick, terra cotta, the windows, etc.,” said K. Nam Shiu, PE, SE, VP at Walker Restoration Consultants, Elgin, Ill. “This was a labor of love. It doesn’t look like any corners were cut,” said Tom Brooks, VP, Restoration Division, Berglund Construction, Chicago. “Instead of remove and throw away, they chose to remove and restore,” said George Tuhowski III, LEED AP, Director of Sustainability and General Superintendent, Leopardo Construction, Hoffman Estates, Ill.

Judge Darlene Ebel, Director, Facility Information Management, University of Illinois at Chicago, called it “a good restoration, with good sustainability. The building still fits in with the whole area.” BD+C

* Note: Walker Johnson, FAIA, recused himself from the proceedings during the judging of this entry.

PROJECT SUMMARY

Building Team

Submitting firm: Johnson Lasky Architects (architect)

Owner: Naval Station Great Lakes

Environmental design: EDI, Inc.

Structural engineer: AHG Structural Engineering

MEP/fire protection engineer: KJWW Engineering

GC: Boaz Friedler Joint Venture

General Information

Area: 26,900 gsf

Construction cost: $5 million

Construction time: May 2007 to August 2009

Delivery method: Design-build

Related Stories

Multifamily Housing | Jul 23, 2019

Is prefab in your future?

The most important benefit of offsite construction, when done right, is reliability.

Healthcare Facilities | Jul 15, 2019

Can a kids’ healthcare space teach, entertain, and heal?

Standard building requirements don’t have to be boring. Here’s how you can inject whimsical touches into everyday design features.

Architects | Jul 10, 2019

9 picks from NeoCon 2019

Interior architect Mary Bartlett selects her favorite products and systems from the 2019 NeoCon show, Chicago, June 10-12, 2019. 

BD+C University Course | Jul 8, 2019

Shadow box design: To vent or not to vent [AIA course]

A curtain wall shadow box is a spandrel assembly consisting of vision glass at the building exterior and an opaque infill at the interior side of the curtain wall system. This course is worth 1.0 AIA LU/HSW. 

Architects | Jul 8, 2019

Unity Temple, Robie House among eight Frank Lloyd Wright projects to receive World Heritage status

The UNESCO designation includes signature works designed by Wright during the first half of the 20th century.

Architects | Jul 1, 2019

Perkins Eastman Co-founder Mary-Jean Eastman to keynote Women in Design+Construction Conference

Two of Perkins Eastman’s firm leaders—Mary-Jean Eastman, FAIA, Vice Chair and Managing Principal of its New York City studio, and Barbara Mullenex, AIA, Managing Principal of the Washington, D.C., studio—will share anecdotes about their personal journeys to the top of a global architecture, design, and planning firm, at Building Design+Construction's fourth annual Women in Design+Construction Conference. The event will take place November 11-13, 2019, at the Fairmont Scottsdale Princess resort in Scottsdale, Ariz. 

Sports and Recreational Facilities | Jun 27, 2019

Foster + Partners unveils design of wooden boathouse for Row New York

The project will sit on the banks of the Harlem River in Sherman Creek Park.

Building Tech | Jun 26, 2019

Modular construction can deliver projects 50% faster

Modular construction can deliver projects 20% to 50% faster than traditional methods and drastically reshape how buildings are delivered, according to a new report from McKinsey & Co.

Architects | Jun 24, 2019

Clayco combines architecture and design assets into one business unit

Lamar Johnson Collaborative adds BatesForum.

Architects | Jun 14, 2019

Making public facilities more public

Municipal facilities must strike a delicate balance between openness and security.

boombox1
boombox2
native1

More In Category



Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021