flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

At Boston University’s dental school, ‘under construction’ won’t mean ‘closed for business’

Contractors

At Boston University’s dental school, ‘under construction’ won’t mean ‘closed for business’

A major renovation and addition are scheduled to minimize operational disruption.


By John Caulfield, Senior Editor | April 26, 2018

Boston University's Goldman School of Dental Medicine will increase its clinical space by 60% through a renovation and addition that are being conducted while the school stays open and continues to offer its services to students and the community. Image: SmithGroupjjr

On April 5, Shawmut Design and Construction broke ground on a 41,900-sf expansion and 53,100-sf renovation of Boston University’s Goldman School of Dental Medicine.

The building team that includes Smith Group JJR (design architect, SE, MEP), Compass Project Management (project manager), and Haley Aldrich (geotech engineer), expects to be onsite for 32 months, during which the school—an active building with over 200 students, plus faculty, staff, and thousands of patients per year—will remain open.

This is a common challenge for rehab projects, complicated in this case by a tight urban site and a building with only a 13,000-sf floor plate—“a postage stamp,” says Shawmut’s Vice President Kevin Sullivan—the building team has to work within.

To keep the school open during work, Sullivan says his firm started by “overcommunicating” with shareholders who included the school’s dean, and its directors of facilities and operations.

The Building Team came up with a multi-phase schedule that will work on the basement, first floor, and part of the second floor first; the two additions next; and then renovate the upper floors. Sullivan explains that this schedule allows for floors and utilities to be isolated, which will sometimes require installing temporary systems to avoid operational disruptions. It will also minimize the need to move students and patients around.

A link to download a virtual reality walkthrough video of this project, posted by Shawmut, can be accessed here.

A rendering of an operatory inside Boston University's renovated and expanded dental school. Image: SmithGroupjjr

 

The isolations will also allow the team to minimize vibration on occupants caused by drilling into concrete to install new façade that lets in more light into the building and blends in with the facades of other buildings in the neighborhood. Because of the tight site space, the Building Team had to close two traffic lanes and move a bus stop.

The expansion will include office, instructional, clinical, and student collaborative spaces on seven existing levels, plus support spaces and a new 140-seat auditorium on the first floor.

The renovation will reconfigure the layout of the patient and student/faculty entry, as well as its clinical, classroom, and student spaces.

All told, the project will increase clinical space by more than 60%, make treatment areas more comfortable and flexible, and provide a student and resident lounge, a café, and collaborative study area on the first floor. With the addition, the school’s floor plate will increase to 18,000 sf.  

The project’s completion data is slated for December 2020.

Related Stories

| May 30, 2018

Accelerate Live! talk: Why the AEC industry must adapt to the Internet of Things boom

In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), building systems expert Jeff Carpenter explores established and emerging IoT applications for commercial and institutional buildings, and offers a technology roadmap for navigating the IoT landscape.

| May 30, 2018

Accelerate Live! talk: T3 mass timber office buildings

In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), architect and mass timber design expert Steve Cavanaugh tells the story behind the nation’s newest—and largest—mass timber building: T3 in Minneapolis.

| May 30, 2018

Accelerate Live! talk: An AEC giant’s roadmap for integrating design, manufacturing, and construction

In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), Skender CEO Mark Skender and Chief Design Officer Tim Swanson present the construction giant’s vision for creating a manufacturing-minded, vertically-integrated design-manufacturing-build business model.

| May 30, 2018

Accelerate Live! talk: From micro schools to tiny houses: What’s driving the downsizing economy?

In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), micro-buildings design expert Aeron Hodges, AIA, explores the key drivers of the micro-buildings movement, and how the trend is spreading into a wide variety of building typologies.

Market Data | May 29, 2018

America’s fastest-growing cities: San Antonio, Phoenix lead population growth

San Antonio added 24,208 people between July 2016 and July 2017, according to U.S. Census Bureau data.

Contractors | May 27, 2018

Swinerton rebrands to call attention to its broader portfolio

Renewable energy is the kind of higher-margin business sector into which this GC has been expanding.

| May 24, 2018

Accelerate Live! talk: The rise of multi-user virtual reality

In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), two of CannonDesign's tech leaders present their early findings from pilot testing multi-user VR technology for AEC project coordination.

| May 24, 2018

Accelerate Live! talk: The next frontier of post-occupancy evaluations

In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), ZGF Architects’ Chris Chatto outlines methods for conducting meaningful, holistic evaluations from design to occupancy.

| May 24, 2018

Accelerate Live! talk: Security and the built environment: Insights from an embassy designer

In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), embassy designer Tom Jacobs explores ways that provide the needed protection while keeping intact the representational and inspirational qualities of a design.

Contractors | May 5, 2018

Manual data entry still hampers jobsite construction

A new survey also finds managers and executives collecting and managing their work information on multiple platforms.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021