BIM on Target

BIM on Target

By using BIM for the design of its new San Clemente, Calif., store, big-box retailer Target has been able to model the entire structural steel package, including joists, in 3D, chopping the timeline for shop drawings from as much as 10 weeks down to an ‘unheard of’ three-and-a-half weeks.


By By Jeff Yoders, Contributing Editor | January 7, 2011
This article first appeared in the January 2011 issue of BD+C.

Minneapolis-based Target Corp. has always put the design of its stores high up on its list of corporate priorities. Target was one of the original participants in the U.S Green Building Council’s Pilot Portfolio certification program, which allows prototype designs of multiple similar buildings to be LEED-certified as variations of a single prototype. Five Target stores have been LEED-certified to date.

Over the last year Target fully transitioned its new store design from 2D (using Bentley Microstation) to 3D (utilizing the Autodesk Revit BIM platform). Early in 2010, as Target began planning a new 142,206-sf store for San Clemente, Calif., the retailer decided to take prototype design to an even higher level, using both 3D BIM and integrated project delivery.

“Right now we maintain a general merchandise P [for “prototype”] store,” said Brad Koland, group manager of structural engineering at Target. However, this month the company will be releasing its Revit prototype. “Right now it doesn’t really get to a deeper level of integration,” said Koland. “We’re trying to find out the viability of how deeply embedded we can take this 3D information into our prototype.”

One goal of the San Clemente investigation was to figure out how better to utilize the space around the structural steel joists in its stores, space that typically houses some HVAC and electrical lines. There is a sense among Target’s architects and engineers that this space could be used more effectively if they were to know early enough in the design process exactly where the joist web framing lays out, so that they could plan how pipes, ducts, and electrical lines would go around them. Koland said Target’s Building Teams need to know how all the elements of the steel joists and the joist girders come into play early in the design phase to effectively utilize that space.

“With BIM analysis tools we knew we could reduce conflicts and increase utilization of the space within our box,” said Koland. “We wanted to move beyond that. We wanted to use BIM as a way to figure out what was in there, and then establish that and build in protocols for how we could start to utilize that space to reduce the height of our buildings, or maximize the amount of space we have, or minimize the amount of structure we have to put up.”

To do that, the integrated team on the San Clemente store—including IPD engineer and steel detailer Meyer Borgman Johnson (MBJ), general contractor Whiting-Turner, and the in-house architects and engineers at Target—met at strategic times near the end of the design phase of the Orange County store. Whiting-Turner created a comprehensive virtual design and construction (VDC) execution plan that was sent out as part of the bidding package for all subcontractors. It defined what Whiting-Turner would be providing, what was expected of each subcontractor, and why and how the 3D model would be used. Because the joist design was such an important part of the overall process, bidding was opened in September for the steel joist fabrication package. The pre-qualification process included a requirement to work as an integrated team using a parametric 3D model.

The steel joist fabrication package went to New Millennium Building Systems, largely because of its BIM capabilities. MBJ created a construction BIM model using Target’s Revit model as a starting point, converting to Tekla Structures using the IFC file format. After quality control checking, this model was delivered to New Millennium in lieu of 2D drawings. The structural joist fabricator was able to use the generic joist elements, rather than having to redraw them, to begin the process for exact steel joist design and modeling.

Using New Millennium’s Dynamic Joist design component, a plug-in for Tekla Structures that helps automate this integrated process, the Fort Wayne, Ind., fabricator was able to quickly design the steel joists, insert “real” fabrication-ready joists and bridge in the shared Tekla model, and produce 2D shop drawings. The geometry and profiles of the joists were determined by New Millennium’s design, detailing, and fabrication standards.

“The parametric Dynamic Joist plug-in will model a joist from user-specified points,” said Ricky Gillenwater, IT director at New Millennium and developer of the plug-in. “What users have initially is a generic representation of a joist, consisting of generic material and geometry. The component transforms into an as-built representation as it goes through the joist detailing and design process, which is what we gave MBJ.”

The time period from the award of the steel joist package to the approval of shop drawings sent back to New Millennium for fabrication from the integrated design team, including calculations and integrated 3D geometry, was three-and-half weeks.

“That’s unheard of to have an approved set of calculations and shop drawings back in the joist manufacturer’s hands ready for fabrication,” said Jerod Hoffman, principal and structural engineer at MBJ. Referring to the structural steel package (including miscellaneous metals), Hoffman said this is the first Target store ever bid to steel fabricators off of completed shop drawings.

“Instead of providing just 2D construction documents, we gave Whiting-Turner the model, the bill of materials that listed every nut and bolt, and approved shop drawings, which the fabricator could use to supersede the 2D drawings and specifications,” Hoffman said. “The hope is that because we’re providing them exact quantities, the quality, competitiveness, and value of the bids they receive will be better than using 2D design drawings only.” Hoffman says he expects “zero change orders” with regard to coordination issues in the steel because “they’ve all been worked out.”

Through the integrated design process, MBJ also discovered early on that some of the load-bearing steel joists had to be fabricated and scoped in a way that changed the original plan for the steel embeds in the store’s concrete walls. As a result, the new embeds were correctly put out on the bid documents for the structural steel and concrete packages and will, therefore, be bid on as an already-coordinated first competitive cost.

Grading and site work on the project began in late December, and Whiting-Turner is already working with its subcontractors on 4D scheduling and cost estimation. The contractor plans to use Navisworks to coordinate the Tekla Structures steel model, as well as other models for the mechanical, electrical, and other subcontractors. Although Revit is not the model being used to create shop drawings and other deliverables for the subcontractors, Whiting-Turner will use the Revit design model in conjunction with fabrication models to perform clash detection and check quality control.

 “The type of sub we’re seeing bid on the project is more sophisticated,” said Reema Zuberi, project manager and regional VDC coordinator at Whiting-Turner. “They are able to work with 3D models and are comfortable working together earlier in the process.”

The store is expected to be ready for its grand opening in October. BD+C

Target: Expanding BIM Design Horizons

Target’s in-house property development operation includes more than 60 architects, 80 engineers, and 30 construction managers. The retailer, with 1,743 stores in every state except Vermont, has cut back its new openings due to the weak economy, but still expects to open 30 new stores in 2011, including the San Clemente, Calif., project. Store design is overseen by senior vice president Rich Varda, an architect whose work outside of Target includes the recently opened Musical Instrument Museum in Phoenix.

Utilizing BIM and prototype designs for efficient design and construction is a key part of Target’s expansion strategy. “Twenty-ten was a demarcation from a 2D design deliverable to a fully 3D design for all store designs,” said Brad Koland, group manager of structural engineering at Target. “We definitely saw that the first incremental benefit of using Revit came from clash detection. There was a cost savings associated with moving from a 2D platform to a 3D one.”

Target has, over the years, experimented with many different ways of procuring construction materials. Getting a better idea of how to use the area around steel joists was one area where, Koland said, Target wanted to build a foundation of knowledge for what is possible.

“We have a really robust owner-provided construction material and equipment program,” he said. “We source some general construction materials but not too many. So, this isn’t necessarily a strong drive toward materials sourcing, but we wanted to see what technology would allow us to do. Sourcing is one of the possible outcomes, but really getting better clarity around what’s inside our building is the primary driver for this investigation.”

Related Stories

MFPRO+ News | Dec 11, 2023

U.S. poorly prepared to house growing number of older adults

The U.S. is ill-prepared to provide adequate housing for the growing ranks of older people, according to a report from Harvard University’s Joint Center for Housing Studies. Over the next decade, the U.S. population older than 75 will increase by 45%, growing from 17 million to nearly 25 million, with many expected to struggle financially.

Office Buildings | Dec 11, 2023

Believe it or not, there could be a shortage of office space in the years ahead

With work-from-home firmly established, many real estate analysts predict a dramatic reduction in office space leasing and plummeting property values. But the high-end of the office segment might actually be headed for a shortage, according to real estate intelligence company CoStar Group. 

University Buildings | Dec 8, 2023

Yale University breaks ground on nation's largest Living Building student housing complex

A groundbreaking on Oct. 11 kicked off a project aiming to construct the largest Living Building Challenge-certified residence on a university campus. The Living Village, a 45,000 sf home for Yale University Divinity School graduate students, “will make an ecological statement about the need to build in harmony with the natural world while training students to become ‘apostles of the environment’,” according to Bruner/Cott, which is leading the design team that includes Höweler + Yoon Architecture and Andropogon Associates.

University Buildings | Dec 5, 2023

The University of Cincinnati builds its largest classroom building to serve its largest college

The University of Cincinnati’s recently completed Clifton Court Hall unifies the school’s social science programs into a multidisciplinary research and education facility. The 185,400-sf structure is the university’s largest classroom building, serving its largest college, the College of Arts and Sciences.

MFPRO+ News | Dec 5, 2023

DOE's Zero Energy Ready Home Multifamily Version 2 released

The U.S. Department of Energy has released Zero Energy Ready Home Multifamily Version 2. The latest version of the certification program increases energy efficiency and performance levels, adds electric readiness, and makes compliance pathways and the certification process more consistent with the ENERGY STAR Multifamily New Construction (ESMFNC) program.

Architects | Dec 5, 2023

Populous celebrates its 40th anniversary with a photo exhibit of its works

The firm partnered with Getty Images to assemble more than 60 images, many capturing fan ardor.

Office Buildings | Dec 1, 2023

Amazon office building doubles as emergency housing for Seattle families

The unusual location for services of this kind serves over 300 people per day. Mary's Place spreads across eight of the office's floors—all designed by Graphite—testing the status quo for its experimental approach to homelessness support.

Mixed-Use | Nov 29, 2023

Mixed-use community benefits from city amenities and ‘micro units’

Salt Lake City, Utah, is home to a new mixed-use residential community that benefits from transit-oriented zoning and cleverly designed multifamily units.

Giants 400 | Nov 28, 2023

Top 100 Laboratory Design Firms for 2023

HDR, Flad Architects, DGA, Elkus Manfredi Architects, and Gensler top BD+C's ranking of the nation's largest laboratory architecture and architecture/engineering (AE) firms for 2023, as reported in Building Design+Construction's 2023 Giants 400 Report.

Engineers | Nov 27, 2023

Kimley-Horn eliminates the guesswork of electric vehicle charger site selection

Private businesses and governments can now choose their new electric vehicle (EV) charger locations with data-driven precision. Kimley-Horn, the national engineering, planning, and design consulting firm, today launched TREDLite EV, a cloud-based tool that helps organizations develop and optimize their EV charger deployment strategies based on the organization’s unique priorities.

boombox1
boombox2
native1

More In Category

Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021