BIM-driven prototype turns data centers into a kit of parts

BIM-driven prototype turns data centers into a kit of parts

Architects with Sheehan Partners, Ltd. (SPARCH) create a modular data center scheme for solutions provider Digital Realty.


By Ryan Schultz & Timothy Connor, SPARCH | May 22, 2014
Considering their predominantly functional and technical nature, data centers are becoming as much a product as they are a building.  As a data center “product,” there are opportunities for mass customization of assemblies that can lead to higher levels of efficiencies than those that can be attained by an outmoded stick-built/one-off approach to building design.
 
However, as data center “buildings”—which exist within a real site with a real context and real constraints—the need exists to think of the building as a system of assemblies that can be sensitively arranged to match the unique requirements of a particular location and program.
 
A promise that building information modeling (BIM) holds is to create a dynamic model of components which can evolve and improve over time.
 
To take advantage of this promise, Digital Realty commissioned SPARCH to design and model a prototypical, modular data center shell in BIM that was responsive to a range of data center infrastructure solutions that Digital Realty had developed.
 
As noted by our client, Steve Kundich, AIA, Vice President, Design & Construction with Digital Realty, “BIM was essential for our PBB+ Prototype development, allowing for rapid site master planning and building design. It eliminates most of the conceptual design and design development steps and allows the team to focus on localizing the design to the site and/or customer requirements.”
 
 

Rendering depicts a two-story, four-pod prototype assembly with an attached common building
 
 
 
Designed for assembly, this PBB+ (Powered Base Building+) prototype blends the best of prefabrication, modular, and site-built construction. This branded prototype is designed for supply chain optimization while allowing for a range of solutions based on particular site or program requirements. 
 
In terms of supply chain optimization of the major architectural components, this prototype campaign will provide Digital Realty the ability to negotiate a considerable cost savings through long-term, bulk purchasing agreements while allowing for reduced lead times for key components. The major architectural components of the prototype would include roofing, exterior precast panels, sunshades and storefront, entry canopies, and even prefabricated stair modules. In addition, the building’s structural elements have been selected and designed to be simplified, repeatable, and readily available, avoiding long delays for specialty steel sizes and detailing. 
 
From our client’s perspective, these will add up to major savings on the overall project budget and schedule, which equates to a quicker time to market. “The opportunities that BIM affords for off-site fabrication allow for reduced project schedule time and cost savings,” says Kundich. “We are now prefabricating major M&E portions of the project with our suppliers.” 
 

Exploded components diagram of a one-story data hall pod module
 
 
 
Of course, every site is unique, with its own particular opportunities and requirements. The PBB+ prototype is modular in nature, allowing for both single-story and two-story solutions. An office or “common” building module is coupled with a varying number of data hall pod modules, each with the associated electrical and mechanical data center infrastructure that Digital has developed. This planning flexibility allows the prototype to conform to sites of various shapes and sizes throughout our client’s markets, while being flexible enough to accommodate their customers’ unique needs.
 
Since the PBB+ prototype is documented with BIM, all of Digital Realty’s AE design consultants can use this content to greatly accelerate the documentation of their site-specific projects, reducing the SD and DD phases of the project to just several weeks and allowing the teams to focus on localizing the design to site specific and customer requirements. Ultimately, the CD phases of the project will be reduced as well, as more construction details are developed and refined over time and added to the prototype model.
 
Portions of this prototype have already been incorporated into several Digital projects currently under way. The savings in cost and time in these case studies are just now being quantified. The goal is to provide a system that can be presented in conjunction with the data center infrastructure solutions that Digital has developed, as either a turn-key solution or as the basis of design for a build-to-suit data center project. Either way, the prototype approach should provide a more rapid and predictable project schedule, both in terms of design and construction, and yield a more cost effective and predictable project budget.
 

Individual components of one-story and two-story pod configurations
 
 
As for next steps, we can imagine setting up and working within a BIM infrastructure where the client's extended ecosystem of consultants/suppliers can continuously and incrementally improve this prototypical model, and do it in a way where the updates become a natural by-product of any given project's workflow.
 
Specifically, we can envision the development of a Revit Plugin that will, in concert with Revit’s WAN-based Server technology, continuously sync, in real-time, this evolving library of components between all of Digital Realty’s AEC consultant projects.
 
Similar to the product design analogy referenced above, this hybrid data center “product-building” can continue to evolve with each new “release,” with all of the information contained within this ever-evolving building model, which exists within the BIM infrastructure. 
 
This approach, and the wide network of Digital’s design and vendor partners, should allow for a continual evolution of the design, with greater opportunity for innovation over a one-firm/one-client/one building approach.
 
We recognize that this represents a dramatic and potentially disruptive departure from the traditional design process. We as architects are ideally suited to participate in and even lead this departure and take advantage of the new opportunities, partnerships, and relationships it promises.

Related Stories

| Apr 5, 2011

Top 10 Buildings: Women in Architecture

Making selections of top buildings this week led to a surprising discovery about the representation of women in architecture, writes Tom Mallory, COO and co-founder, OpenBuildings.com. He discovered that finding female-created architecture, when excluding husband/wife teams, is extremely difficult and often the only work he came across was akin to interior design.

| Apr 5, 2011

What do Chengdu, Lagos, and Chicago have in common?

They’re all “world middleweight cities” that are likely to become regional megacities (10 million people) by 2025—along with Dongguan, Guangzhou, Hangzhou, Shenzhen, Tianjin, and Wuhan (China); Kinshasa (Democratic Republic of the Congo); Jakarta (Indonesia); Lahore (Pakistan); and Chennai (India), according to a new report from McKinsey Global Institute: “Urban World: Mapping the economic power of cities”.

| Mar 30, 2011

China's low-carbon future city

In 2005, the Chinese government announced its target to reduce energy consumption per GDP unit by 20% by the year 2010. After a multi-billion investment, that target has been reached. The Chinese Climate Protection Program’s goal to increase energy efficiency, develop renewable energies, and promote energy savings while reducing pollutant emissions and strengthening environmental protection is reflected in the “Future City” by SBA Design.

| Mar 30, 2011

Is the AEC industry at risk of losing its next generation leaders without better mentoring?

After two or three horrifying years for the AEC industry, we are finally seeing the makings of a turnaround. However, data developed by Kermit Baker as part of the AIA Work-on-the-Boards survey program indicates that between 17% and 22% of design firms are eliminating positions for interns and staff with less than six years of experience. This data suggests the industry is at risk of losing a large segment of its next generation of leaders if something isn't done to improve mentoring across the profession.

| Mar 29, 2011

City's design, transit system can ease gas costs

Some cities in the U.S. are better positioned to deal with rising gas prices than others because of their design and transit systems, according to CEOs for Cities, a Chicago-based nonprofit that works to build stronger cities. The key factor: whether residents have to drive everywhere, or have other options.

| Mar 29, 2011

Chicago’s Willis Tower to become a vertical solar farm

Chicago’s iconic Willis Tower (formerly the Sears Tower) is set to become a massive solar electric plant with the installation of a pilot solar electric glass project.

boombox1
boombox2
native1

More In Category


Urban Planning

The magic of L.A.’s Melrose Mile

Great streets are generally not initially curated or willed into being. Rather, they emerge organically from unintentional synergies of commercial, business, cultural and economic drivers. L.A.’s Melrose Avenue is a prime example. 


Curtain Wall

7 steps to investigating curtain wall leaks

It is common for significant curtain wall leakage to involve multiple variables. Therefore, a comprehensive multi-faceted investigation is required to determine the origin of leakage, according to building enclosure consultants Richard Aeck and John A. Rudisill with Rimkus. 


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021