BIM-driven prototype turns data centers into a kit of parts

BIM-driven prototype turns data centers into a kit of parts

Architects with Sheehan Partners, Ltd. (SPARCH) create a modular data center scheme for solutions provider Digital Realty.


By Ryan Schultz & Timothy Connor, SPARCH | May 22, 2014
Considering their predominantly functional and technical nature, data centers are becoming as much a product as they are a building.  As a data center “product,” there are opportunities for mass customization of assemblies that can lead to higher levels of efficiencies than those that can be attained by an outmoded stick-built/one-off approach to building design.
 
However, as data center “buildings”—which exist within a real site with a real context and real constraints—the need exists to think of the building as a system of assemblies that can be sensitively arranged to match the unique requirements of a particular location and program.
 
A promise that building information modeling (BIM) holds is to create a dynamic model of components which can evolve and improve over time.
 
To take advantage of this promise, Digital Realty commissioned SPARCH to design and model a prototypical, modular data center shell in BIM that was responsive to a range of data center infrastructure solutions that Digital Realty had developed.
 
As noted by our client, Steve Kundich, AIA, Vice President, Design & Construction with Digital Realty, “BIM was essential for our PBB+ Prototype development, allowing for rapid site master planning and building design. It eliminates most of the conceptual design and design development steps and allows the team to focus on localizing the design to the site and/or customer requirements.”
 
 

Rendering depicts a two-story, four-pod prototype assembly with an attached common building
 
 
 
Designed for assembly, this PBB+ (Powered Base Building+) prototype blends the best of prefabrication, modular, and site-built construction. This branded prototype is designed for supply chain optimization while allowing for a range of solutions based on particular site or program requirements. 
 
In terms of supply chain optimization of the major architectural components, this prototype campaign will provide Digital Realty the ability to negotiate a considerable cost savings through long-term, bulk purchasing agreements while allowing for reduced lead times for key components. The major architectural components of the prototype would include roofing, exterior precast panels, sunshades and storefront, entry canopies, and even prefabricated stair modules. In addition, the building’s structural elements have been selected and designed to be simplified, repeatable, and readily available, avoiding long delays for specialty steel sizes and detailing. 
 
From our client’s perspective, these will add up to major savings on the overall project budget and schedule, which equates to a quicker time to market. “The opportunities that BIM affords for off-site fabrication allow for reduced project schedule time and cost savings,” says Kundich. “We are now prefabricating major M&E portions of the project with our suppliers.” 
 

Exploded components diagram of a one-story data hall pod module
 
 
 
Of course, every site is unique, with its own particular opportunities and requirements. The PBB+ prototype is modular in nature, allowing for both single-story and two-story solutions. An office or “common” building module is coupled with a varying number of data hall pod modules, each with the associated electrical and mechanical data center infrastructure that Digital has developed. This planning flexibility allows the prototype to conform to sites of various shapes and sizes throughout our client’s markets, while being flexible enough to accommodate their customers’ unique needs.
 
Since the PBB+ prototype is documented with BIM, all of Digital Realty’s AE design consultants can use this content to greatly accelerate the documentation of their site-specific projects, reducing the SD and DD phases of the project to just several weeks and allowing the teams to focus on localizing the design to site specific and customer requirements. Ultimately, the CD phases of the project will be reduced as well, as more construction details are developed and refined over time and added to the prototype model.
 
Portions of this prototype have already been incorporated into several Digital projects currently under way. The savings in cost and time in these case studies are just now being quantified. The goal is to provide a system that can be presented in conjunction with the data center infrastructure solutions that Digital has developed, as either a turn-key solution or as the basis of design for a build-to-suit data center project. Either way, the prototype approach should provide a more rapid and predictable project schedule, both in terms of design and construction, and yield a more cost effective and predictable project budget.
 

Individual components of one-story and two-story pod configurations
 
 
As for next steps, we can imagine setting up and working within a BIM infrastructure where the client's extended ecosystem of consultants/suppliers can continuously and incrementally improve this prototypical model, and do it in a way where the updates become a natural by-product of any given project's workflow.
 
Specifically, we can envision the development of a Revit Plugin that will, in concert with Revit’s WAN-based Server technology, continuously sync, in real-time, this evolving library of components between all of Digital Realty’s AEC consultant projects.
 
Similar to the product design analogy referenced above, this hybrid data center “product-building” can continue to evolve with each new “release,” with all of the information contained within this ever-evolving building model, which exists within the BIM infrastructure. 
 
This approach, and the wide network of Digital’s design and vendor partners, should allow for a continual evolution of the design, with greater opportunity for innovation over a one-firm/one-client/one building approach.
 
We recognize that this represents a dramatic and potentially disruptive departure from the traditional design process. We as architects are ideally suited to participate in and even lead this departure and take advantage of the new opportunities, partnerships, and relationships it promises.

Related Stories

| Feb 10, 2014

Ball State to host Geothermal Conference on design, drilling and equipment - April 10, 2014

To best serve the industry, Ball State University has organized a single day conference in which participants will be able to exchange technical notes, develop understandings and share experiences with design, drilling, and equipment issues related to geothermal ground source heat pump technology.

| Feb 7, 2014

DOE, Autodesk team to overhaul the EnergyPlus simulation program

The update will allow a larger ecosystem of developers to contribute updates to the code in order to improve performance and decrease the time required to run energy model simulations.

| Feb 7, 2014

Meet the new Fellows: AIA elevates 143 to College of Fellows

The AIA College of Fellows is an honor awarded to members who have made significant contributions to the architectural profession.

| Feb 7, 2014

Bernards announces executive leadership realignment

Changes reflect long-term growth plans as builder enters its fifth decade.    

| Feb 7, 2014

Zaha Hadid's 'white crystal' petroleum research center taking shape in the desert [slideshow]

Like a crystalline form still in the state of expansion, the King Abdullah Petroleum Studies and Research Center will rise from the desert in dramatic fashion, with a network of bright-white, six-sided cells combining to form an angular, shell-like façade.

| Feb 6, 2014

First look: Gensler ups the ante on airport design with new SFO boarding area

The new terminal features a yoga room, award-winning arts program, and an interactive play area for kids.

| Feb 6, 2014

End of the open workplace?

If you’ve been following news about workplace design in the popular media, you might believe that the open workplace has run its course. While there’s no shortage of bad open-plan workplaces, there are two big flaws with the now common claim that openness is bad.

| Feb 6, 2014

New Hampshire metal building awes visitors

Visitors to the Keene Family YMCA in New Hampshire are often surprised by what they encounter. Liz Coppola calls it the “wow factor.” “Literally, there’s jaw dropping,” says Coppola, director of financial and program development for the Keene Family YMCA.

| Feb 5, 2014

M&A activity down in 2013 among architecture, engineering firms: Report

In 2013, consultant Morrissey Goodale observed 168 sales of U.S.-based architecture and engineering (“A/E”) firms – down nearly 7% from the record 180 sales of U.S.-based A/E firms in 2012.

| Feb 5, 2014

BIA Opens Entries for 25th Annual Brick in Architecture Awards

Entries open on February 10 for the Brick Industry Association's (BIA) Brick in Architecture Awards. Celebrating its silver anniversary, BIA's annual honors spotlight outstanding, innovative and sustainable architecture that incorporates clay brick products as the predominant exterior building or paving material. 

boombox1
boombox2
native1

More In Category


Museums

The Tampa Museum of Art will soon undergo a $110 million expansion

In Tampa, Fla., the Tampa Museum of Art will soon undergo a 77,904-sf Centennial Expansion project. The museum plans to reach its $110 million fundraising goal by late 2024 or early 2025 and then break ground. Designed by Weiss/Manfredi, and with construction manager The Beck Group, the expansion will redefine the museum’s surrounding site.



Reconstruction & Renovation

Movement to protect historic buildings raises sharp criticism

While the movement to preserve historic buildings has widespread support, it also has some sharp critics with well-funded opposition groups springing up in recent years. Some opponents are linked to the Stand Together Foundation, founded and bankrolled by the Koch family’s conservative philanthropic organization, according to a column in Governing magazine.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021