BIM-driven prototype turns data centers into a kit of parts

BIM-driven prototype turns data centers into a kit of parts

Architects with Sheehan Partners, Ltd. (SPARCH) create a modular data center scheme for solutions provider Digital Realty.


By Ryan Schultz & Timothy Connor, SPARCH | May 22, 2014
Considering their predominantly functional and technical nature, data centers are becoming as much a product as they are a building.  As a data center “product,” there are opportunities for mass customization of assemblies that can lead to higher levels of efficiencies than those that can be attained by an outmoded stick-built/one-off approach to building design.
 
However, as data center “buildings”—which exist within a real site with a real context and real constraints—the need exists to think of the building as a system of assemblies that can be sensitively arranged to match the unique requirements of a particular location and program.
 
A promise that building information modeling (BIM) holds is to create a dynamic model of components which can evolve and improve over time.
 
To take advantage of this promise, Digital Realty commissioned SPARCH to design and model a prototypical, modular data center shell in BIM that was responsive to a range of data center infrastructure solutions that Digital Realty had developed.
 
As noted by our client, Steve Kundich, AIA, Vice President, Design & Construction with Digital Realty, “BIM was essential for our PBB+ Prototype development, allowing for rapid site master planning and building design. It eliminates most of the conceptual design and design development steps and allows the team to focus on localizing the design to the site and/or customer requirements.”
 
 

Rendering depicts a two-story, four-pod prototype assembly with an attached common building
 
 
 
Designed for assembly, this PBB+ (Powered Base Building+) prototype blends the best of prefabrication, modular, and site-built construction. This branded prototype is designed for supply chain optimization while allowing for a range of solutions based on particular site or program requirements. 
 
In terms of supply chain optimization of the major architectural components, this prototype campaign will provide Digital Realty the ability to negotiate a considerable cost savings through long-term, bulk purchasing agreements while allowing for reduced lead times for key components. The major architectural components of the prototype would include roofing, exterior precast panels, sunshades and storefront, entry canopies, and even prefabricated stair modules. In addition, the building’s structural elements have been selected and designed to be simplified, repeatable, and readily available, avoiding long delays for specialty steel sizes and detailing. 
 
From our client’s perspective, these will add up to major savings on the overall project budget and schedule, which equates to a quicker time to market. “The opportunities that BIM affords for off-site fabrication allow for reduced project schedule time and cost savings,” says Kundich. “We are now prefabricating major M&E portions of the project with our suppliers.” 
 

Exploded components diagram of a one-story data hall pod module
 
 
 
Of course, every site is unique, with its own particular opportunities and requirements. The PBB+ prototype is modular in nature, allowing for both single-story and two-story solutions. An office or “common” building module is coupled with a varying number of data hall pod modules, each with the associated electrical and mechanical data center infrastructure that Digital has developed. This planning flexibility allows the prototype to conform to sites of various shapes and sizes throughout our client’s markets, while being flexible enough to accommodate their customers’ unique needs.
 
Since the PBB+ prototype is documented with BIM, all of Digital Realty’s AE design consultants can use this content to greatly accelerate the documentation of their site-specific projects, reducing the SD and DD phases of the project to just several weeks and allowing the teams to focus on localizing the design to site specific and customer requirements. Ultimately, the CD phases of the project will be reduced as well, as more construction details are developed and refined over time and added to the prototype model.
 
Portions of this prototype have already been incorporated into several Digital projects currently under way. The savings in cost and time in these case studies are just now being quantified. The goal is to provide a system that can be presented in conjunction with the data center infrastructure solutions that Digital has developed, as either a turn-key solution or as the basis of design for a build-to-suit data center project. Either way, the prototype approach should provide a more rapid and predictable project schedule, both in terms of design and construction, and yield a more cost effective and predictable project budget.
 

Individual components of one-story and two-story pod configurations
 
 
As for next steps, we can imagine setting up and working within a BIM infrastructure where the client's extended ecosystem of consultants/suppliers can continuously and incrementally improve this prototypical model, and do it in a way where the updates become a natural by-product of any given project's workflow.
 
Specifically, we can envision the development of a Revit Plugin that will, in concert with Revit’s WAN-based Server technology, continuously sync, in real-time, this evolving library of components between all of Digital Realty’s AEC consultant projects.
 
Similar to the product design analogy referenced above, this hybrid data center “product-building” can continue to evolve with each new “release,” with all of the information contained within this ever-evolving building model, which exists within the BIM infrastructure. 
 
This approach, and the wide network of Digital’s design and vendor partners, should allow for a continual evolution of the design, with greater opportunity for innovation over a one-firm/one-client/one building approach.
 
We recognize that this represents a dramatic and potentially disruptive departure from the traditional design process. We as architects are ideally suited to participate in and even lead this departure and take advantage of the new opportunities, partnerships, and relationships it promises.

Related Stories

Building Team | Jun 22, 2018

What owners should know before choosing the design-build project delivery method

Outside of drawing up a well-written contract, owners often overlook a key attribute that can significantly impact the success of a design-build project, writes Skanska’s Julie Hyson.

Architects | Jun 14, 2018

Chicago Architecture Center sets Aug. 31 as opening date

The Center is located at 111 E. Wacker Drive.

Multifamily Housing | Jun 13, 2018

Multifamily visionaries: KTGY’s extraordinary expectations

KTGY Architecture + Planning keeps pushing the boundaries of multifamily housing design in the U.S., Asia, and the Middle East.

| Jun 11, 2018

Accelerate Live! talk: Regenerative design — When sustainability is not enough

In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), HMC’s Eric Carbonnier poses the question: What if buildings could actually rejuvenate ecosystems?

| Jun 11, 2018

Accelerate Live! talk: The smart jobsite — Predictive visual data analytics for proactive project controls

In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), a trio of experts in predictive visual data analytics presents how design-build giant Clayco has leveraged this technology to achieve production efficiency on several construction sites.

| Jun 11, 2018

Accelerate Live! talk: Design innovation at Adrian Smith + Gordon Gill Architecture

In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), AS+GG’s Anthony Viola takes us behind the magic curtain to illuminate the firm’s methods for nurturing design innovation.

| Jun 11, 2018

Accelerate Live! talk: ‘AEC can has Blockchains?’

In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), HOK’s Greg Schleusner explores how the AEC industry could adapt the best ideas from other industries (banking, manufacturing, tech) to modernize inefficient design and construction processes.

| Jun 11, 2018

Accelerate Live! talk: How advanced digital fabrication techniques are driving design innovation

In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), SOM’s Lucas Tryggestad and Kyle Vansice present the firm’s 3D-printed building project and explore how digital fabrication is pushing design innovation.

| Jun 11, 2018

Accelerate Live! talk: AEC + Data + AI — Poison for some, elixir for others

In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), predictive analytics expert David Morgareidge offers steps that AE firms can take today if they want to survive AECO digital transformation.

Education Facilities | Jun 8, 2018

Data is driving design for education

In gathering this constant flow of data and recognizing the shifting trends, how can educational institutions make informed choices and smart design decisions that lead to higher efficiency and improved control over capital budgets?

boombox1
boombox2
native1

More In Category



Urban Planning

The magic of L.A.’s Melrose Mile

Great streets are generally not initially curated or willed into being. Rather, they emerge organically from unintentional synergies of commercial, business, cultural and economic drivers. L.A.’s Melrose Avenue is a prime example. 


Curtain Wall

7 steps to investigating curtain wall leaks

It is common for significant curtain wall leakage to involve multiple variables. Therefore, a comprehensive multi-faceted investigation is required to determine the origin of leakage, according to building enclosure consultants Richard Aeck and John A. Rudisill with Rimkus. 

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021