‘BIM for all’ platform pays off for contractor

‘BIM for all’ platform pays off for contractor

Construction giant JE Dunn is saving millions in cost avoidances by implementing a custom, cloud-based BIM/VDC collaboration platform.


By David Barista, Editor-in-Chief | December 3, 2013
JE Dunn uses pop-up WiFi stations and weatherproof computer kiosks (pictured) to
JE Dunn uses pop-up WiFi stations and weatherproof computer kiosks (pictured) to bring the Dunn Dashboard to the job site. All p

Designing and building laboratories is complicated enough. Imagine having to answer to 40 owner representatives on a single project, at every step of the design development and preconstruction phases. Oh, by the way, most of those clients have a PhD and know as much, if not more, about building science and energy efficiency than almost anyone on your staff.  

This was the scenario that JE Dunn Construction and SmithGroupJJR faced when they collaborated with a fastidious team of scientists and researchers from the National Renewable Energy Laboratory to create the 182,500-sf Energy System Integration Facility in Golden, Colo. The lab’s advanced computer modeling and simulation capabilities—used to study clean energy technologies on a megawatt scale—are powered by a petaflop-scale computer system and data center that is rated as one of the most energy efficient in the world, with an average power usage effectiveness of 1.05. 

Every inch of the facility, from the high-bay lab spaces to the data center server racks, was the result of close collaboration with the facility’s eventual occupants and O&M team. For both JE Dunn and SmithGroupJJR, who have been using BIM/VDC tools to drive construction projects for nearly a decade, the NREL project raised two primary concerns.

First, how could the Building Team intimately involve so many stakeholders in an iterative design and preconstruction process without getting bogged down by the paperwork and communication? Second, how could project participants (clients as well as subcontractors) who are not fluent in BIM/VDC software engage with a complex parametric model in a meaningful way? 

Dunn Dashboard: Functions and benefits

• Cloud-based collaboration. All information is accessible via mobile devices through a mobile-scaled dashboard interface. Building Team members in different locations can collaborate on design documents, BIM models, and 3D laser scans in real time.
• Electronic submittals and invoicing. Bids can be submitted electronically; invoices and pay functions also are managed in a single location.
• Customizable security options. The Dashboard offers role-based permissions for all project stakeholders, including architects, subcontractors, owners, and construction partners.
• Instant owner’s manual at project conclusion. Entire dashboard of documents is handed over at project close out in Web-based form.
• Real-time updates. Data is updated in real-time, ensuring all construction partners are working with consistent documentation.
• BIM access for all. Mobile job site kiosks provide construction field workers with access to the Dunn Dashboard.

JE Dunn’s solution was to provide each scientist, researcher, and facility team member with a custom, restricted view of the BIM model, based on his or her area of concern. Using any computer device with an Internet connection, the clients could quickly open their assigned views of the model and conduct virtual walkthroughs of the spaces and provide feedback directly in the model. JE Dunn and SmithGroupJJR incorporated the suggested changes in the next round of design drawings and posted updated model views for stakeholders to review. This cloud-based collaboration drastically compressed the overall design schedule, saving weeks of preconstruction planning time.

“Rather than having to pass a set of documents around sequentially, elongating the review process, we let them go directly into the model, which drastically reduced the schedule,” says John Jacobs, LEED AP, JE Dunn’s Chief Information Officer. “They didn’t have to pull the model down from the cloud onto their machine or need BIM knowledge to view it. We created an easy-to-use interface where they could access the views with a click of a button.”

JE Dunn’s solution for the NREL project, which incorporated third-party software tools like Horizontal Glue (now part of Autodesk’s BIM 360 suite) and Microsoft SharePoint, served as the basis for its highly successful Dunn Dashboard cloud-based project collaboration and digital sharing platform. In less than two years since its launch, more than 425 of the firm’s project teams have adopted the platform to share real-time BIM model data—and other project documents, such as bid submittals, RFIs, and warranty information—with the clients and Building Team. More than 20 projects are being added to the platform every month, and the total number of external users just surpassed the 11,000 mark: 8,400 subcontractors, 1,600 architects, and 1,100 owner’s reps.

JE Dunn and other large construction firms, including McCarthy Building Cos. and Mortenson Construction, are investing in custom-built, cloud-based project collaboration and digital sharing platforms that greatly increase the accessibility and usefulness of BIM/VDC models for a large number of stakeholders. On the table are hundreds of thousands of dollars, even millions, in potential cost avoidances by minimizing the number of change orders and compressing the design development and preconstruction schedules. 

“BIM in the cloud is a huge leap forward for the construction industry,” says Jacobs. “We as contractors and architects can look at a 2D document and envision what it’s going to look like; some of our clients can’t. The Dunn Dashboard gives them the ability to visualize their space and make crucial decisions during preconstruction without being BIM specialists. We can avoid all the costly, last-minute changes.”

Scalability, adaptability yield new capabilities

A distinguishing characteristic of the Dunn Dashboard, says Jacobs, is its scalability. “The IT department built it and then got out of the way,” he says. “As a result, our project teams are using it in ways we never thought of.”

On the recently completed CyrusOne data center in Chandler, Ariz., the JE Dunn team and the project’s architect, Corgan Associates, used Dunn Dashboard as a repository for questions and answers from subcontractors bidding on the work. All questions were submitted anonymously, and the team received alerts when questions were submitted. 

“All information was logged and publicly available, so anyone bidding on the job could log in and see the questions and answers in real time,” says Kevin Sears, LEED AP, JE Dunn’s Project Manager on the CyrusOne project. “This process created an equal playing field for the subs and greatly reduced the time and effort that goes into answering the many questions during preconstruction. Corgan only had to answer questions once, and they didn’t have to waste time distributing the answers to the subs.” 

In similar fashion, the team utilized the platform to share high-resolution construction photos and webcam feeds with the project’s client representatives, who were based in different parts of the country.   

Taking the Dashboard right to the field

As projects move into the construction phase, the firm brings the Dunn Dashboard to the job site through pop-up WiFi stations and weatherproof computer kiosks placed strategically throughout the site. Jacobs says the kiosks are especially important since many laborers and tradespeople are not equipped with the mobile devices to access the BIM model and other project documents. 

“If you’re going to put all of this data into a model and the laborer or the carpenter can’t consume it, then it’s useless,” he says. “We regularly see lines forming at these kiosks. People walk up and quickly access what they need, whether it be a cut sheet or a detail view. They can move the model around and view an intersection of materials, like a window jamb or flashing detail, so they are sure to build it right the first time.”

Once the project is complete, the Dunn Dashboard offers instantaneous turnover of the project documents to the owner—there’s no two- or three-month waiting period for training videos, warranty claims, insurance policies, design documents, and the as-built BIM model. With the push of a button, the facilities management team is given access to all finalized project documents. 

“Literally, the day they move in the facilities team has complete access—via smartphone, tablet, or computer—to all the documents and information they need to run the building,” says Jacobs.

Related Stories

| Apr 20, 2012

Shawmut completes Yard House Restaurant in Boston

12,000-sf restaurant marks new addition to Boston’s Fenway neighborhood.

| Apr 20, 2012

Registration open for Solar Power International 2012 in Orlando

President Bill Clinton to deliver keynote address at ?largest solar energy event in the Americas.

| Apr 19, 2012

The 10 mistakes most likely to get you sued

The California Chamber of Commerce has produced a white paper cataloging the top 10 mistakes most likely to get a company sued. While a few of the laws cited apply specifically to California, some of them are federal and may apply in your state.

| Apr 19, 2012

Holcim cement plants recognized at PCA Spring Meeting

The Holly Hill plant received the PCA’s Chairman’s Safety Performance Award in recognition of their exceptional health and safety programs. The Theodore plant received the Environmental Performance Award in recognition of the steps they take beyond those required by laws, regulations and permits to minimize their impact on the environment.

| Apr 19, 2012

KTGY Group’s Arista Uptown Apartments in Broomfield, Colo. completed

First of eight buildings highlights unique amenities.

| Apr 19, 2012

Nauset begins work on $20M Joint Forces HQ at Hanscom AFB

3D imaging key to project timetable and cost containment.

| Apr 19, 2012

HBD Construction names Steven Meeks vice president

Meeks will provide expertise for the company in its many diverse areas of construction projects including health care, senior living, education and retail.

| Apr 18, 2012

Lafarge moving North American headquarters to Illinois

Lafarge CEO John Stull says the factors in their decision were location in the Midwest and area transportation.

| Apr 18, 2012

Positive conditions persist for Architecture Billings Index

The AIA reported the March ABI score was 50.4, following a mark of 51.0 in February; greatest demand is for commercial building projects.

| Apr 18, 2012

Syska Hennessy re-launches Information and Communication Technology practice

The ICT practice will focus a blend of products including Information Technology, Security, Audiovisual, Building Automation, Fire Life Safety, Medical Communications and Intelligent Building Systems.

boombox1
boombox2
native1

More In Category

Geothermal Technology

Rochester, Minn., plans extensive geothermal network

The city of Rochester, Minn., home of the famed Mayo Clinic, is going big on geothermal networks. The city is constructing Thermal Energy Networks (TENs) that consist of ambient pipe loops connecting multiple buildings and delivering thermal heating and cooling energy via water-source heat pumps.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021