flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Bernards and Colombo leverage Bluebeam Revu to speed up project document management

Sponsored Content

Bernards and Colombo leverage Bluebeam Revu to speed up project document management

Bernards and Colombo team up with Revu to streamline project documentation for the Tehachapi Valley Healthcare District Replacement Hospital


By Bluebeam | November 5, 2013
Tehachapi project rendering courtesy of SWA Architects
Tehachapi project rendering courtesy of SWA Architects

Bernards, a well-respected, nationally ranked construction firm and Colombo Construction Company, a southern California firm known for its quality healthcare projects, have teamed for the first time to provide construction management services for the $57 Million Tehachapi Valley Healthcare District Replacement Hospital in Tehachapi, California. This new 25-bed, 79,000 square foot facility will replace the existing hospital which no longer meets current California safety standards, and is located in a rural part of Kern County. As the only hospital in a 50-mile radius, the project is a vital addition to the community, so it’s important that the team completes the job as quickly and efficiently as possible.

Challenge
The project broke ground in early 2013, and the first challenge the team faced was how to manage the enormous number of drawings necessary for the construction of a hospital. Since Tehachapi is a California hospital, it requires approval from the Office of Statewide Health Planning and Development (OSHPD*). Because of time constraints during the bidding process, two sets of drawings had to be correlated: a “permit set” of 500 documents for OSHPD approval, and another “bid set” of 520 documents for the prime contractors.

Not only was the bid set larger, but it also contained updated information that was not reflected in the older permit set. The team needed a reliable solution to quickly and accurately compare the differences between the two versions. Printing hard copies of each set and comparing them against each other was not an option — the process would be time-consuming and risk a significant margin for error. Moreover, because of the project’s remote location, printing costs are extremely high. It was becoming clear that digital was the only way to go.

A Digital Solution
The team at first considered looking for a third-party service to help with the seemingly overwhelming task of comparing the two sets of drawings. Fortunately, Bernards Project Engineer William Lopez had a better idea. Having used Bluebeam Revu on other projects with great success, he was confident that leveraging Revu was the best course of action. The technology was already in-house, and this solution saved time and the cost of looking for a third party qualified enough to complete the work.

The Tehachapi team contacted the project architect, requesting PDF copies of both the permit and bid sets. They then began the process of creating an electronic plan room by installing two 55” screens and using Revu’s Compare Documents feature to display — side-by-side — the automatic comparison of the two sets. This feature enables users to select two drawings, and automatically highlights all disparities with clouds, so they are easy-to-find.

Upon completion, the team reviewed and organized all the markups using the “Markups list.” This feature tracks markups as they are added to the document in a convenient list that can be filtered, searched, imported and exported.

Results
Using Revu, the team compared an initial test set of 100 sheets, and everyone was happy and surprised when it took only 3 hours to back-check the results. In fact, William and the team were amazed by the speed and success of the test. “We were able to complete the final job of comparing the permit set against the bid set in just 15 hours — pretty amazing, considering we had expected this process to take over a week!” 

A quality assurance/quality control review revealed that Revu was finding the myriad of important details, including revision symbols and date stamps, that manual scanning could have missed. Even minute details in the scanned permit drawings were picked up. Best of all, the team was able to spend their valuable weekends at home, not in the office reviewing drawings.

Mike Funderberg, Bernards’ Project Manager for the Tehachapi project, commented “The utilization of Bluebeam for this document comparison effort saved nearly 400 hours of the Bernards/Colombo staff’s time to devote to other pressing issues. Being able to not only utilize software, but rely on it, made our processes so much more efficient.” 

Continuing to Leverage Revu
OSPHD is still in the process of updating the permit set to reflect the advancements of the bid set drawings, and is sending approvals just about every day. As the Bernards/Colombo team receives those changes, they slip-sheet them into the master set using Revu’s Replace Pages feature, updating the sets 10 times faster than it would take to update a paper set. 

The Tehachapi team is also using Revu for BIM coordination. For example, when they discovered the ceilings needed to be dropped to accommodate additional ducts and piping, they created 3-D PDFs of the sectioned BIM, to send to the architect with their markups. This is a much faster and easier way to share redlines, and the team loves how easy it is to manipulate 3-D PDFs. They also plan on using Revu for takeoffs, color coding, and other day-to-day construction tasks, and have already set up Wi-Fi in the trailer, enabling plan review in the field.

To learn more about Revu or download a free 30-day trial, please visit us here.

Bluebeam contact information:
• 866.496.2140
• sales@bluebeam.com
• www. bluebeam.com

*OSHPD is an agency created in 1978 to provide the state with enhanced understanding of the structure and function of its healthcare delivery systems. 

Related Stories

| Nov 7, 2022

Mixed-use tower in China features world’s highest outdoor pool

Guangxi China Resources Tower, a new 403-meter-tall (1,322 feet) skyscraper in Nanning, China features the world’s highest outdoor pool—at 323 meters (1,060 feet) above grade.

Building Team | Nov 3, 2022

More than half of U.S. contractors say finding skilled workers is big barrier to their growth

More than half of U.S. contractors (55%) say finding enough skilled workers is one of the biggest barriers to growing their business, according to a DEWALT Powering the Future Survey.

Building Materials | Nov 2, 2022

Design for Freedom: Ending slavery and child labor in the global building materials sector

Sharon Prince, Founder and CEO of Grace Farms and Design for Freedom, discusses DFF's report on slavery and enforced child labor in building products and materials.

Codes and Standards | Nov 2, 2022

New York City construction official wants to boost design-build

The new associate commissioner of alternative delivery in New York City’s Department of Design and Construction aims to encourage more design-build project delivery in the city.

University Buildings | Nov 2, 2022

New Univ. of Calif. Riverside business school building will support hybrid learning

  A design-build partnership of Moore Ruble Yudell and McCarthy Building Companies will collaborate on a new business school building at the University of California at Riverside.

Building Team | Nov 1, 2022

Nonresidential construction spending increases slightly in September, says ABC

National nonresidential construction spending was up by 0.5% in September, according to an Associated Builders and Contractors analysis of data published today by the U.S. Census Bureau.

K-12 Schools | Nov 1, 2022

Safety is the abiding design priority for K-12 schools

With some exceptions, architecture, engineering, and construction firms say renovations and adaptive reuse make up the bulk of their work in the K-12 schools sector.

| Nov 1, 2022

Updated Florida building codes helped newer homes withstand Hurricane Ian

Newer homes seemed to fare much better than older structures during Hurricane Ian, suggesting that updated Florida building codes made a difference.

Wood | Nov 1, 2022

A European manufacturer says its engineered wood products can store carbon for decades

  Metsä Wood, a Finland-based manufacturer of engineered wood products, says its sustainable, material-efficient products can store carbon for decades, helping to combat climate change. 

Hotel Facilities | Oct 31, 2022

These three hoteliers make up two-thirds of all new hotel development in the U.S.

With a combined 3,523 projects and 400,490 rooms in the pipeline, Marriott, Hilton, and InterContinental dominate the U.S. hotel construction sector.

boombox1
boombox2
native1

More In Category


Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021