Bernards, a well-respected, nationally ranked construction firm and Colombo Construction Company, a southern California firm known for its quality healthcare projects, have teamed for the first time to provide construction management services for the $57 Million Tehachapi Valley Healthcare District Replacement Hospital in Tehachapi, California. This new 25-bed, 79,000 square foot facility will replace the existing hospital which no longer meets current California safety standards, and is located in a rural part of Kern County. As the only hospital in a 50-mile radius, the project is a vital addition to the community, so it’s important that the team completes the job as quickly and efficiently as possible.
Challenge
The project broke ground in early 2013, and the first challenge the team faced was how to manage the enormous number of drawings necessary for the construction of a hospital. Since Tehachapi is a California hospital, it requires approval from the Office of Statewide Health Planning and Development (OSHPD*). Because of time constraints during the bidding process, two sets of drawings had to be correlated: a “permit set” of 500 documents for OSHPD approval, and another “bid set” of 520 documents for the prime contractors.
Not only was the bid set larger, but it also contained updated information that was not reflected in the older permit set. The team needed a reliable solution to quickly and accurately compare the differences between the two versions. Printing hard copies of each set and comparing them against each other was not an option — the process would be time-consuming and risk a significant margin for error. Moreover, because of the project’s remote location, printing costs are extremely high. It was becoming clear that digital was the only way to go.
A Digital Solution
The team at first considered looking for a third-party service to help with the seemingly overwhelming task of comparing the two sets of drawings. Fortunately, Bernards Project Engineer William Lopez had a better idea. Having used Bluebeam Revu on other projects with great success, he was confident that leveraging Revu was the best course of action. The technology was already in-house, and this solution saved time and the cost of looking for a third party qualified enough to complete the work.
The Tehachapi team contacted the project architect, requesting PDF copies of both the permit and bid sets. They then began the process of creating an electronic plan room by installing two 55” screens and using Revu’s Compare Documents feature to display — side-by-side — the automatic comparison of the two sets. This feature enables users to select two drawings, and automatically highlights all disparities with clouds, so they are easy-to-find.
Upon completion, the team reviewed and organized all the markups using the “Markups list.” This feature tracks markups as they are added to the document in a convenient list that can be filtered, searched, imported and exported.
Results
Using Revu, the team compared an initial test set of 100 sheets, and everyone was happy and surprised when it took only 3 hours to back-check the results. In fact, William and the team were amazed by the speed and success of the test. “We were able to complete the final job of comparing the permit set against the bid set in just 15 hours — pretty amazing, considering we had expected this process to take over a week!”
A quality assurance/quality control review revealed that Revu was finding the myriad of important details, including revision symbols and date stamps, that manual scanning could have missed. Even minute details in the scanned permit drawings were picked up. Best of all, the team was able to spend their valuable weekends at home, not in the office reviewing drawings.
Mike Funderberg, Bernards’ Project Manager for the Tehachapi project, commented “The utilization of Bluebeam for this document comparison effort saved nearly 400 hours of the Bernards/Colombo staff’s time to devote to other pressing issues. Being able to not only utilize software, but rely on it, made our processes so much more efficient.”
Continuing to Leverage Revu
OSPHD is still in the process of updating the permit set to reflect the advancements of the bid set drawings, and is sending approvals just about every day. As the Bernards/Colombo team receives those changes, they slip-sheet them into the master set using Revu’s Replace Pages feature, updating the sets 10 times faster than it would take to update a paper set.
The Tehachapi team is also using Revu for BIM coordination. For example, when they discovered the ceilings needed to be dropped to accommodate additional ducts and piping, they created 3-D PDFs of the sectioned BIM, to send to the architect with their markups. This is a much faster and easier way to share redlines, and the team loves how easy it is to manipulate 3-D PDFs. They also plan on using Revu for takeoffs, color coding, and other day-to-day construction tasks, and have already set up Wi-Fi in the trailer, enabling plan review in the field.
To learn more about Revu or download a free 30-day trial, please visit us here.
*OSHPD is an agency created in 1978 to provide the state with enhanced understanding of the structure and function of its healthcare delivery systems.
Related Stories
| Jun 29, 2012
Guardian launches industry’s first glass visualizer for interior design
Online tool allows designers to explore the possibilities of glass.
| Jun 28, 2012
Federal applications of renewable energy
U.S. Army Fort Knox: Using the Earth for space heating and cooling. The U.S. Department of Energy’s (DOE) Federal Energy Management Program (FEMP) facilitates the Federal Government’s implementation of sound, cost-effective energy management and investment practices to enhance the nation’s energy security and environmental stewardship.
| Jun 27, 2012
HDR opens office in Beijing
The Beijing office is HDR’s second location in China; the firm’s other office is in Shanghai.
| Jun 27, 2012
KBE Building wins honor for Armed Forces Reserve Center
The construction phase was completed in just 16 months.
| Jun 27, 2012
SOM’s Baker receives honorary doctorate in engineering from Heriot-Watt University
Baker recognized for his career and influential contribution in the field of structural engineering.
| Jun 25, 2012
Living green wall planned for InterContinental Chicago
Project, with price tag of $2 million to $3 million, needs council approval.
| Jun 25, 2012
AIA-NJ honors DMR Architects
The academic building, completed in 2009, provides classrooms, computer labs, faculty offices, and meeting spaces for the College, which has a steady 7% annual increase in enrollment.
| Jun 25, 2012
Thornton Tomasetti appoints Hofmeister and Zhu to board of directors
The addition of Hofmeister and Zhu brings the number of directors to 10.
| Jun 22, 2012
Golden Gate Bridge Celebrates 75 Years With the Opening of New Bridge Pavilion
With features such as Nichiha's Illumination series panels, super-insulating glass units, and LED lighting, the new Golden Gate Bridge Pavilion not only boasts the bridge's famous international orange, but green sustainability as well
| Jun 19, 2012
Energy and Commerce Departments Announce New Centers for Building Operations Excellence
Part of Better Buildings Initiative, Centers Will Focus on Energy Efficiency Workforce Development for Building Operations Professionals