Bernards, a well-respected, nationally ranked construction firm and Colombo Construction Company, a southern California firm known for its quality healthcare projects, have teamed for the first time to provide construction management services for the $57 Million Tehachapi Valley Healthcare District Replacement Hospital in Tehachapi, California. This new 25-bed, 79,000 square foot facility will replace the existing hospital which no longer meets current California safety standards, and is located in a rural part of Kern County. As the only hospital in a 50-mile radius, the project is a vital addition to the community, so it’s important that the team completes the job as quickly and efficiently as possible.
Challenge
The project broke ground in early 2013, and the first challenge the team faced was how to manage the enormous number of drawings necessary for the construction of a hospital. Since Tehachapi is a California hospital, it requires approval from the Office of Statewide Health Planning and Development (OSHPD*). Because of time constraints during the bidding process, two sets of drawings had to be correlated: a “permit set” of 500 documents for OSHPD approval, and another “bid set” of 520 documents for the prime contractors.
Not only was the bid set larger, but it also contained updated information that was not reflected in the older permit set. The team needed a reliable solution to quickly and accurately compare the differences between the two versions. Printing hard copies of each set and comparing them against each other was not an option — the process would be time-consuming and risk a significant margin for error. Moreover, because of the project’s remote location, printing costs are extremely high. It was becoming clear that digital was the only way to go.
A Digital Solution
The team at first considered looking for a third-party service to help with the seemingly overwhelming task of comparing the two sets of drawings. Fortunately, Bernards Project Engineer William Lopez had a better idea. Having used Bluebeam Revu on other projects with great success, he was confident that leveraging Revu was the best course of action. The technology was already in-house, and this solution saved time and the cost of looking for a third party qualified enough to complete the work.
The Tehachapi team contacted the project architect, requesting PDF copies of both the permit and bid sets. They then began the process of creating an electronic plan room by installing two 55” screens and using Revu’s Compare Documents feature to display — side-by-side — the automatic comparison of the two sets. This feature enables users to select two drawings, and automatically highlights all disparities with clouds, so they are easy-to-find.
Upon completion, the team reviewed and organized all the markups using the “Markups list.” This feature tracks markups as they are added to the document in a convenient list that can be filtered, searched, imported and exported.
Results
Using Revu, the team compared an initial test set of 100 sheets, and everyone was happy and surprised when it took only 3 hours to back-check the results. In fact, William and the team were amazed by the speed and success of the test. “We were able to complete the final job of comparing the permit set against the bid set in just 15 hours — pretty amazing, considering we had expected this process to take over a week!”
A quality assurance/quality control review revealed that Revu was finding the myriad of important details, including revision symbols and date stamps, that manual scanning could have missed. Even minute details in the scanned permit drawings were picked up. Best of all, the team was able to spend their valuable weekends at home, not in the office reviewing drawings.
Mike Funderberg, Bernards’ Project Manager for the Tehachapi project, commented “The utilization of Bluebeam for this document comparison effort saved nearly 400 hours of the Bernards/Colombo staff’s time to devote to other pressing issues. Being able to not only utilize software, but rely on it, made our processes so much more efficient.”
Continuing to Leverage Revu
OSPHD is still in the process of updating the permit set to reflect the advancements of the bid set drawings, and is sending approvals just about every day. As the Bernards/Colombo team receives those changes, they slip-sheet them into the master set using Revu’s Replace Pages feature, updating the sets 10 times faster than it would take to update a paper set.
The Tehachapi team is also using Revu for BIM coordination. For example, when they discovered the ceilings needed to be dropped to accommodate additional ducts and piping, they created 3-D PDFs of the sectioned BIM, to send to the architect with their markups. This is a much faster and easier way to share redlines, and the team loves how easy it is to manipulate 3-D PDFs. They also plan on using Revu for takeoffs, color coding, and other day-to-day construction tasks, and have already set up Wi-Fi in the trailer, enabling plan review in the field.
To learn more about Revu or download a free 30-day trial, please visit us here.
*OSHPD is an agency created in 1978 to provide the state with enhanced understanding of the structure and function of its healthcare delivery systems.
Related Stories
| Sep 6, 2013
U40 Summit featured speaker: Arthur Gensler on how to build a world-class AEC practice
Gensler, founder of the world’s largest architecture firm, will talk about the role of the architect in society, the impact of great design, and the practicalities of starting and running a practice, and will offer advice for today’s young design and construction professionals.
| Sep 6, 2013
Nonresidential Construction Index holds steady in Q3
FMI's 2013 Third Quarter Nonresidential Construction Index report shows a NRCI score of 60.3, a .2-point improvement over Q2.
| Sep 5, 2013
Do you have the next big breakthrough for the AEC industry?
Next month's Under 40 Leadership Summit in San Francisco is your place to shine. Our third annual networking and leadership event for young AEC professionals will feature an XPrize-type competition, called Vision U40, that will reward attendees who develop the most innovative solutions to today's pressing issues.
| Sep 4, 2013
Identifying your leadership gaps
U.S. businesses spend more than $170 billion annually on leadership-based curriculum, according to the American Society of Training and Development. Is all that training producing better leaders or just more people who hold positions of leadership?
| Sep 4, 2013
Augmented reality: 12 applications for design and construction professionals
Building Design+Construction reached out to AEC professionals who have studied and applied augmented reality and asked them to pinpoint applications that are ripe for the technology. Here’s what they had to offer.
| Sep 4, 2013
Augmented reality goes mainstream: 12 applications for design and construction firms
Thanks to inexpensive mobile devices and increasingly advanced software apps, Building Teams are finally able to bring their BIM models to life on the job site.
| Sep 4, 2013
K-12 school design that pays off for students
More and more educators are being influenced by the Reggio Emilia approach to pedagogy, with its mantra of “environment as the third teacher”—an approach that gives Building Teams a responsibility to pay even closer attention to the special needs of today’s schools.
| Sep 4, 2013
Video: Autodesk Fellow Tom Wujec on why you should join the Vision U40 competition
Tom Wujec, lead facilitator of BD+C's 3rd Annual Under 40 Leadership Summit, October 9-11 in San Francisco, explains the Vision U40 competition, which will launch at the event. U40 Summit participants will collaborate in small teams to develop innovative solutions to today's pressing social, economic, technical and cultural problems related to the built environment. They will complete for $5,000 in prizes.
| Sep 4, 2013
Smart building technology: Talking results at the BUILDINGChicago/ Greening the Heartland show
Recent advancements in technology are allowing owners to connect with facilities as never before, leveraging existing automation systems to achieve cost-effective energy improvements. This BUILDINGChicago presentation will feature Procter & Gamble’s smart building management program.
| Sep 4, 2013
Twenty-nine-acre brick building complex in Watertown, Mass., to be renovated as innovation hub
The owner of a 29-acre cluster of brick buildings in Watertown, Mass., wants to reinvent the site as a 21st-century innovation hub.