Benefits of building enclosure commissioning include reduced costs

Codes and Standards

Benefits of building enclosure commissioning include reduced costs

Savings achieved in less rework and fewer and shorter punch lists.


By Peter Fabris, Contributing Editor | September 24, 2020

Courtesy Pixabay

Building enclosure commissioning, a quality-assurance process intended to ensure a building meets the owner’s requirements, offers benefits including cost savings. The process fosters the ability to catch and eliminate problems early and inexpensively, resulting in reduced project costs and fewer change orders.

ASHRAE Guideline 0-2013 and NIBS Guideline 3 both address building enclosure commissioning. The process begins in the predesign phase with the formation of a commissioning team.

The key document established by the commissioning team in the predesign phase is the owner’s project requirements, which means the owner’s representatives are an invaluable part of the commissioning team for making the owner’s needs known and understood.

After design and construction, the commissioning process should address ongoing operation, maintenance and modification of the project throughout its life. Commissioning guidelines also cover responsibilities for the team and commissioning authority, expectations for the schedule, and documentation. Other practices found within the guidelines include documenting training requirements, verifying training, and the creation of a systems manual for understanding how to operate and maintain all the systems and assemblies within a project.

Related Stories

| Jun 21, 2012

California adds window film to building code

California is the first state to add window film into its building code. Window film, a polymer material, offers cost-effective energy savings.

| Jun 21, 2012

New ISO standard to improve environmental management of concrete

A new ISO standard will help the construction industry better manage the environmental impacts of concrete.

| Jun 21, 2012

On net-zero projects, Building Teams will be held accountable for energy-efficiency performance

The building team will be held accountable for how net-zero energy buildings perform two, five, and maybe ten years after completion.

| Jun 14, 2012

USGBC co-founder launches rating system for building product manufacturers

U.S. Green Building Council co-founder David Gottfried’s new venture, Regenerative Ventures, has established a rating system for building product manufacturers.

| Jun 14, 2012

Green standard set for single-ply roofing membrane

A sustainability standard has been established for single-ply roofing membranes used on commercial buildings.

| Jun 14, 2012

Minnesota Vikings stadium plan gets legislative go-ahead

Legislation that approved the construction of a new billion dollar stadium for the Minnesota Vikings passed the Minnesota legislature.

| Jun 14, 2012

Report alleges New York’s prevailing construction wages are miscalculated, costing billions

A miscalculation in how prevailing wages are calculated in New York reportedly costs the state $3 billion a year in public-infrastructure projects.

| Jun 14, 2012

AGC, other business groups oppose hiring rules for disabled

Business groups have asked the U.S. Department of Labor to reconsider a proposed hiring quota aimed at federal contractors pertaining to people with disabilities.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021