Building enclosure commissioning, a quality-assurance process intended to ensure a building meets the owner’s requirements, offers benefits including cost savings. The process fosters the ability to catch and eliminate problems early and inexpensively, resulting in reduced project costs and fewer change orders.
ASHRAE Guideline 0-2013 and NIBS Guideline 3 both address building enclosure commissioning. The process begins in the predesign phase with the formation of a commissioning team.
The key document established by the commissioning team in the predesign phase is the owner’s project requirements, which means the owner’s representatives are an invaluable part of the commissioning team for making the owner’s needs known and understood.
After design and construction, the commissioning process should address ongoing operation, maintenance and modification of the project throughout its life. Commissioning guidelines also cover responsibilities for the team and commissioning authority, expectations for the schedule, and documentation. Other practices found within the guidelines include documenting training requirements, verifying training, and the creation of a systems manual for understanding how to operate and maintain all the systems and assemblies within a project.
Related Stories
Codes and Standards | May 7, 2018
Plan advances in Los Angeles for Climate Emergency Mobilization Department
Would oversee efforts to reduce greenhouse gas emissions across the city.
Codes and Standards | May 3, 2018
Data collection, machine learning boost building efficiency
Sensors, software algorithms squeeze out waste.
Codes and Standards | May 2, 2018
Energy Department releases Updated EnergyPlus and OpenStudio building energy modeling tools
The tools can now accept input in epJSON format.
Codes and Standards | May 1, 2018
ASHRAE publishes new energy simulation-aided design standard
Requires building energy modeling during schematic design.
Codes and Standards | Apr 30, 2018
CALGreen projects pre-approved for streamlined LEED v4 requirements
Reduces need to run additional energy models.
Codes and Standards | Apr 26, 2018
New standard supports community resilience
ASTM International guidance supports cost-effective ways to withstand and recover from disasters.
Codes and Standards | Apr 25, 2018
Lessons learned from decades of Superfund cleanups guide contaminated land reuse
Sites repurposed for residential, commercial use, and solar energy generation.
Codes and Standards | Apr 24, 2018
Vibrant downtown core the key for urban multifamily development
Nighttime activity makes the difference.
Codes and Standards | Apr 19, 2018
ILFI launches new Zero Carbon Certification
Offers greater flexibility around project fuel types and offsetting renewables.
Codes and Standards | Apr 18, 2018
New Green Globe pilot program launched
Precursor to revised Green Globes Assessment Protocol for Commercial Buildings.