Balance bunker and Phase III projects breaks ground at Mitsubishi Plant in Georgia

Balance bunker and Phase III projects breaks ground at Mitsubishi Plant in Georgia


By By BD+C Staff | October 3, 2011
Mitsubishi Power Systems Americas (MPSA) Savannah Machinery Works.

 

The joint venture of H. J. High Construction/Batson-Cook Company recently broke ground on the construction of a Balance Bunker at Mitsubishi Power Systems Americas (MPSA) Savannah Machinery Works project.

The structure is the fourth project on the campus to be built by the team.

The stand-alone Balance Bunker will bring the latest in product testing technology to the Savannah Machinery Works.

The facility, a modification of similar facilities used by Mitsubishi Heavy Industries, Inc. (MHI) in Japan, was designed by a joint design team of engineers and architects from The Austin Company of Cleveland, Ohio, MPSA and MHI.

The chamber will be contained within a single-story precast and insulated metal panel building, conventionally framed with steel columns, beams and joists. The chamber is constructed of seven feet of reinforced concrete walls lined with inner and outer steel that will be capable of withstanding nearly zero atmosphere under vacuum. The structure will be connected with the main manufacturing facility by a rail line, also built by High / Batson-Cook.

The project, which broke ground in August, is scheduled to be completed in November 2012.

Also announced, the third phase of the MPSA Savannah Machinery Works construction project was awarded to the joint venture of H.J. High Construction/Batson-Cook.

The team, which built the initial two phases of the facility, will erect a $16 million, 74,000-sf manufacturing bay for the new facility in Pooler, Ga.

The new project, Bay 4, will be home to the gas turbine and steam turbine assembly activities. H.J. High and Batson-Cook will install a crane system to aid in the compilation of its product.

In addition, 400 feet of railroad track will be constructed inside the facility.  The track will connect to a new spur, built in Phase II of the project, linking the Savannah Machinery Works to the Port of Savannah. This phase is expected to complete in March of 2012. BD+C

Related Stories

Digital Twin | Aug 27, 2020

The Weekly show: Digital twin technology and social equity in the AEC market

The August 27 episode of BD+C's "The Weekly" is available for viewing on demand. 

Architects | Aug 26, 2020

We the People: Four steps for the architecture profession to build unity through design

Architect offers a 4-point manifesto to the design community to work for racial and social justice in the U.S. following the death of George Floyd.

Coronavirus | Aug 25, 2020

Video: 5 building sectors to watch amid COVID-19

RCLCO's Brad Hunter reveals the winners and non-winners of the U.S. real estate market during the coronavirus pandemic.

Architects | Aug 19, 2020

Japan’s Tokyo Toilet project looks to improve the perception of public restrooms

17 toilets throughout Shibuya will be redesigned as part of the project.

Architects | Aug 5, 2020

Final report: BD+C's 2020 Color Trends Report

This special research report from the editors of BD+C explores the leading trends and drivers related to the use of color on commercial, institutional, and multifamily building projects. 

University Buildings | Aug 2, 2020

R&D hubs, modular-built hotels, and an award-winning student center on the August 6 “The Weekly”

R&D hubs, modular-built hotels, and an award-winning student center on the August 6 “The Weekly”

University Buildings | Jul 24, 2020

A hybrid learning approach could redefine higher education

Universities reassess current assets to determine growth strategies.

Coronavirus | Jun 19, 2020

Experts address COVID-19's impact on nursing homes and schools on The Weekly

The June 18 episode of BD+C's "The Weekly" is available for viewing on demand. 

Coronavirus | Jun 12, 2020

BD+C launches 'The Weekly,' a streaming program for the design and construction industry

The first episode, now available on demand, features experts from Robins & Morton, Gensler, and FMI on the current state of the AEC market.

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021