flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

The average U.S. contractor has 8.4 months worth of construction work in the pipeline, as of June 2024

Contractors

The average U.S. contractor has 8.4 months worth of construction work in the pipeline, as of June 2024

ABC's Construction Backlog Indicator increased to 8.4 months in June.


By Associated Builders and Contractors | July 9, 2024
Image by Tom from Pixabay

Image by Tom from Pixabay

Associated Builders and Contractors reported today that its Construction Backlog Indicator increased to 8.4 months in June, according to an ABC member survey conducted June 20 to July 3. The reading is down 0.5 months from June 2023.

View ABC’s Construction Backlog Indicator and Construction Confidence Index tables for June. View the full Construction Backlog Indicator and Construction Confidence Index data series.

The entire decline in backlog observed over the past calendar year is attributable to the Middle States and Northeast. Backlog in the South and West regions was unchanged between June 2023 and June 2024.

ABC’s Construction Confidence Index readings for sales and staffing levels fell slightly in June, while the reading for profit margins improved. All three readings remain above the threshold of 50, indicating expectations for growth over the next six months.

The average U.S. contractor has 8.4 months worth of construction work in the pipeline, as of June 2024

“Backlog continues to hold up remarkably well despite high interest rates, inflation and emerging weakness in the broader economy," said ABC Chief Economist Anirban Basu. “While contractor confidence regarding the outlook for sales and staffing levels fell modestly in June, all three Construction Confidence Index components are higher than they were one year ago.

“The combination of slowing inflation and softening growth suggests that the Federal Reserve may begin to lower interest rates as soon as September,” said Basu. “That will buoy backlog as some of the softer construction segments, like office and commercial, benefit from lower borrowing costs and looser lending standards.” 

The average U.S. contractor has 8.4 months worth of construction work in the pipeline, as of June 2024

The average U.S. contractor has 8.4 months worth of construction work in the pipeline, as of June 2024
 

Related Stories

Mixed-Use | Apr 26, 2022

Downtown Phoenix to get hundreds of residential and student housing units

In fast-growing Phoenix, Arizona, a transit-oriented development called Central Station will sit adjacent to Arizona State University’s Downtown Phoenix campus. 

Hotel Facilities | Apr 25, 2022

U.S. hotel construction pipeline up 2%, with 5,090 projects in the works

The total U.S. hotel construction pipeline stands at 5,090 projects and 606,302 rooms at the end of the first quarter of 2022, up 2% by projects, but down 3% by rooms, according to the Q1 2022 Construction Pipeline Trend Report for the United States from Lodging Econometrics (LE). 

Codes and Standards | Apr 25, 2022

Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Cushman & Wakefield’s 2022 Americas Office Fit-Out Cost Guide found supply chain constraints and shifting consumer demands will continue to add pressure to costs, both in materials and labor.

Sports and Recreational Facilities | Apr 25, 2022

Iowa's Field of Dreams to get boutique hotel, new baseball fields

A decade ago, Go the Distance Baseball formed to preserve the Iowa farm site where the 1989 movie Field of Dreams was filmed. 

Building Team | Apr 22, 2022

EarthCam Adds Senior Leadership Roles to Facilitate Rapid Growth

EarthCam today announced several new leadership positions as it scales up to accommodate increasing demand for its webcam technology and services.

Architects | Apr 22, 2022

Top 10 green building projects for 2022

The American Institute of Architects' Committee on the Environment (COTE) has announced its COTE Top Ten Awards for significant achievements in advancing climate action.

Mixed-Use | Apr 22, 2022

San Francisco replaces a waterfront parking lot with a new neighborhood

A parking lot on San Francisco’s waterfront is transforming into Mission Rock—a new neighborhood featuring rental units, offices, parks, open spaces, retail, and parking.

Legislation | Apr 21, 2022

NIMBYism in the Sunbelt stymies new apartment development

Population growth in Sunbelt metro areas is driving demand for new apartment development, but resistance is growing against these projects.

Building Team | Apr 20, 2022

White House works with state, local governments to bolster building performance standards

The former head of the U.S. Green Building Council says the Biden Administration’s formation of the National Building Performance Standards Coalition is a “tremendous” step in the right direction to raise building performance standards in the U.S.

Market Data | Apr 20, 2022

Pace of demand for design services rapidly accelerates

Demand for design services in March expanded sharply from February according to a new report today from The American Institute of Architects (AIA).  

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021