ASHRAE/IES publish first standard focused on commissioning process

ASHRAE/IES publish first standard focused on commissioning process

Standard 202, an industry consensus document, includes specific tasks to be conducted to verify that a project meets the owner's requirements.


By ASHRAE | September 27, 2013

ATLANTA – A newly published standard focused on the commissioning process will help ensure a fully functional, fine-tuned facility.

ANSI/ASHRAE/IES Standard 202, Commissioning Process for Buildings and Systems, identifies the minimum acceptable commissioning process for buildings and systems as described in ASHRAE’s Guideline 0-2005, The Commissioning Process. Standard 202 is ASHRAE’s first standard focused on the commissioning process. The commissioning process as detailed in Standard 202 applies to all construction projects and systems and is an industry consensus document.

“Given the integration and interdependency of facility systems, a performance deficiency in one system can result in less than optimal performance by other systems,” Gerald Kettler, P.E., chair of the committee that wrote the standard, said. “Implementing the Commissioning Process is intended to reduce the project capital cost through the warranty period and also reduce the life-cycle cost of the facility. Using this integrated process results in a fully functional, fine-tuned facility, with complete documentation of its systems and assemblies and trained operations and maintenance personnel.”

The commissioning process assumes that owners, programmers, designers, contractors and operations and maintenance entities are fully accountable for the quality of their work. The process begins at project inception and continues for the life of a facility.

The process includes specific tasks to be conducted to verify that design, construction, verification, testing, documentation and training meet the owner’s project requirements, according to Kettler.

The standard defines the commissioning process through 13 functional steps, each of which contains deliverables. The commissioning activities and deliverable are as follows:

  • Initiate the Commissioning Process, including defining roles and responsibilities

  • Define the project requirements, which results in the  Owner’s Project Requirements (OPR) document

  • Develop commissioning plan – produces a written Commissioning Process Plan

  •  Plan design approach to Owners Project Requirements – defines the basis of design

  • Set contractor commissioning requirement, which are included in the commissioning specifications

  •  Design review by the commissioning authority provides feedback and a design review report

  • Submittals review verifies compliance with the OPR in a submittal review report

  • Observation  & Testing verifies system performance with results documented in construction checklists and reports

  • Issues resolution coordination is done with an issues and resolution log

  • Systems manual assembly results in a systems manual for building operation

  • Conduct training for building operations with training plans and records

  • Post occupancy operation commissioning provides an end of warranty commissioning report

  • Assembly of a commissioning report captures all the project commissioning documentation

Other commissioning guidance from ASHRAE includes Guideline 0-2005, The Commissioning Process;Guideline 1.1-2007, HVAC&R Technical Requirements for the Commissioning Process; and Guideline 1.5-2012, The Commissioning Process for Smoke Control Systems.

ASHRAE also is working on several other guidelines related to commissioning:  Guideline 0.2P, The Commissioning Process for Existing Systems and Assemblies; Guideline 1.2P, The Commissioning Process for Existing HVAC&R Systems; Guideline 1.3P, Building Operation and Maintenance Training for the HVAC&R Commissioning Process; and Guideline 1.4P, Procedures for Preparing Facility Systems Manuals.

The cost of ANSI/ASHRAE/IES Standard 202-2013, Commissioning Process for Buildings and Systems, is $72 ($61, ASHRAE members). To order, contact ASHRAE Customer Contact Center at 1-800-527-4723 (United States and Canada) or 404-636-8400 (worldwide), fax 678-539-2129, or visitwww.ashrae.org/bookstore.

ASHRAE, founded in 1894, is a building technology society with more than 50,000 members worldwide. The Society and its members focus on building systems, energy efficiency, indoor air quality, refrigeration and sustainability. Through research, standards writing, publishing, certification and continuing education, ASHRAE shapes tomorrow’s built environment today. More information can be found atwww.ashrae.org/news.

Related Stories

| Apr 17, 2012

Freese and Nichols awarded Malcolm Baldridge National Quality Award

Freese and Nichols is the only engineering and architecture firm to ever receive this recognition.

| Apr 17, 2012

Miramar College police substation in San Diego receives LEED Platinum

The police substation is the first higher education facility in San Diego County to achieve LEED Platinum Certification, the highest rating possible.

| Apr 17, 2012

Alberici receives 2012 ASA General Contractor of the Year award

Alberici has been honored by the ASA eight times in the award’s nineteen-year history--more than any other general contractor in its class.

| Apr 16, 2012

Freeland promoted to vice president at Heery International

Recently named to Building Design+Construction’s 40 Under 40 Class of 2012.

| Apr 16, 2012

University of Michigan study seeks to create efficient building design

The result, the researchers say, could be technologies capable of cutting the carbon footprint created by the huge power demands buildings place on the nation’s electrical grid.

| Apr 16, 2012

UNT lab designed to study green energy technologies completed

Lab to test energy technologies and systems in order to achieve a net-zero consumption of energy.

| Apr 16, 2012

Shawmut awarded Tag Heuer builds in Florida and Pennsylvania

Both projects are scheduled to be completed this spring.

| Apr 16, 2012

Batson-Cook breaks ground on senior living center in Brunswick, Ga.

Marks the third Benton House project constructed by Batson-Cook.

| Apr 16, 2012

Altoon + Porter Architects renamed Altoon Partners

The global practice, with offices in Los Angeles, Amsterdam, and Shanghai, specializes in retail, residential and mixed-use developments.

| Apr 16, 2012

Drake joins EYP as science and technology project executive

Drake’s more than 30 years of diversified design and project delivery experience spans a broad range of complex building types.

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021