Answered prayers

Answered prayers

A bold renovation enables a small church to expand its mission on a grand scale.


By By Laurie Petersen, Contributing Editor | January 3, 2013
To maximize daylight and views for the children, alternating windows of the firs
To maximize daylight and views for the children, alternating windows of the first-floor classrooms were changed into glazed door
This article first appeared in the January 2013 issue of BD+C.

Empty churches and shuttered parochial schools are scattered throughout neighborhoods in many older U.S. cities, and Chicago is no exception. Meanwhile, many daycare providers, community organizations, and charter schools are desperate for program space. Could this be evidence of divine providence at work?

The story of Concordia Place illuminates both the difficulties and rewards of trying to match empty buildings with social programs. Concordia Lutheran Church, founded by Swedish Lutherans in 1898 and today a member congregation of the Evangelical Lutheran Church in America, was seeking to expand its highly successful early childhood program, Concordia Place. That program was started in the early 1980s, when three single mothers pleaded with the small, 60-member congregation to provide low-cost childcare.

Located in Chicago’s North Center neighborhood, about six miles northwest of the Loop, Concordia Place had a long waiting list and no space in which to grow. When a shuttered Catholic church, St. Veronica’s, about a mile southwest of Concordia, came on the market, Concordia’s leaders sprung at the opportunity.

Project summary


CONCORDIA PLACE
Chicago, Ill.

Building Team


Owner: Concordia Lutheran Church
Owner’s representative: Cotter Consulting
Project planning and development: LL Consulting
Architect, interior design, SE: Holabird & Root
MEP engineer: EME (now KJWW)
Civil engineer: Terra Engineering
Historic preservation consultant: Harboe Architects
Landscape architect: McKay Landscape Architects
Contractor: Bulley & Andrews

General Information


Project size: 28,000 sf
Construction cost: $5.6 million
Delivery method: Design-bid-build

There was talk about razing the structures in order to build condominiums, but the local community would hear nothing of that: They wanted the buildings preserved and repurposed to serve mounting social demands. Concordia members undertook a multi-year fundraising campaign, doubling their regular contributions, mortgaging existing church facilities, and soliciting donations from businesses, foundations, and government sources

Unravelling a hodgepodge of building uses

The property featured an unusual set of structures. St. Veronica Parish was founded in 1904 and a year later dedicated a combination church-school building. What looked like a three-story brick-and-limestone school actually contained a sanctuary on the ground floor, classrooms on the floor above, and a large community hall on the third. Gone was an old convent in a wood-frame penthouse above it all; it was destroyed by fire years ago.

In contrast to the modest church-school structure, the rectory, built a decade later, was an imposing red brick Tudor design by noted ecclesiastical architect Henry Schlacks. The archdiocese closed both church and school and sold the property to the city of Chicago in 1989. For a time, it was used as overflow space for a nearby public school, but within a few years it was vacant and subject to repeated vandalism.

Such combination church-school buildings may be the most readily adaptable of church properties, as they usually have no bell towers, large rose windows, or tall, voluminous naves. The lack of the typical church basement meant that the main level was just up from the sidewalk, making ADA compliance easier to achieve.           

When Concordia Lutheran eventually purchased the property, the first two floors of the church-school building prooved perfect for their early childhood and preschool program. But according to the church’s pastor, Reverend Nicholas J. Zook, the leaders  wondered what to do with the cavernous third floor. They surveyed the community and found that, due to heightened gang activity in the neighborhood, teen programs would be welcomed. There was also a large population of seniors and non-English-speaking adults with unmet needs.

Thus, it was envisioned that the so-called “bonus space” of the third floor could house a community center that would offer after-school and summer camp programs for ages six to 12, leadership development for teens, English classes for adults, and wellness programs for seniors.

Keeping program needs and preservation in mind

Local architects Holabird & Root were charged with meeting the varied programmatic needs of these diverse user groups while preserving the historic exteriors. Careful site planning made use of virtually every square inch of the property. “We wanted to get as much space as possible for the kids to play in, but we also wanted to make a welcoming gesture to the public,” says Maria Segal, RA, then Holabird & Root’s early childhood design specialist. (She is now with Blender Architecture, Chicago.)

General contractor Bulley & Andrews demolished a decrepit 1950s addition and replaced it with a single-story annex. Its colors and materials—soft red and light sage green composite cement panels—mediate between the red brick rectory and the yellow brick church-school building. Siting the annex at the back of the lot created a courtyard that is now used for both school and community events, including a farmers’ market run by the after-school teens.

The high-ceilinged annex is used for children’s large-motor activities as well as banquets, community meetings, and worship services. Extensive glazing provides a visual connection to the outdoors and makes it glow during evening events. A playground for the preschool children is just south of the annex, and a fenced play area for toddlers is tucked into the north part of the site, offering direct access from those classrooms.

Because the church complex was rated orange on the Chicago Historic Resources Survey, the project was able to obtain state funds. That triggered the involvement of the Illinois Historic Preservation Agency, which directed Concordia to preserve all existing window openings. This was at odds with Concordia’s desire to change some of the windows into glass-paned doors for the first floor classrooms.

The IHPA and Concordia reached a compromise: alternating windows were changed into doors, and small square windows were punched into the walls below the sills of the remaining windows. The original wood windows were restored and double-glazed.

Except for a stairway in the southeast corner, the interior of the church-school was gutted. Folding wooden doors that divided a large room on the third floor were reused for the same purpose.

The archdiocese had removed about half of the stained glass windows before selling the property. Those that remained were removed from the first-floor sanctuary and placed in backlit frames in the historic stairwell and in the third-floor teen room, which can also serve as a chapel. The IHPA did not require the stained glass to be preserved, but Reverend Zook insisted that it be done anyway, as a gesture “to show continuity with this place as an anchor in the community.”

The interior materials palette is in neutral, soothing colors with natural materials, such as birch plywood, used wherever possible. “That way the child brings the life and color to the spaces,” Segal says.

Reverend Zook praises the 28,000-sf, $5.6 million project, for its maximization of natural light and for providing and an abundance of storage areas from otherwise useless space, which helps maximize the flexibility of the rooms.

Keeping the scale right

A child-appropriate scale was also achieved despite the high ceilings by breaking down the scale of the classrooms with alcoves, cubbies, and lofts. Activity areas are defined by changes in ceiling and floor treatments. Low, square windows provide views into adjacent classrooms as well as to the outdoors. During construction, a number of cast-iron columns were discovered; these columns had to be reinforced with a secondary set of steel supports.

The third floor has an array of spaces whose flexibility has contributed significantly to the building’s success as a community center. Reverend Zook dreamed of a grand lobby on the first floor, but that space was needed for classrooms. Instead, the project team created a great lobby upstairs, where a pitched-roof skylight structure provides abundant north light, and a café serves as a multipurpose space used throughout the day by seniors, adults, and teens. New doors can close off the corridor to separate the licensed preschool spaces from the community areas

This kind of mixed-use facility is a model for the pooling of community resources that is now often necessitated by tight budgets, especially for nonprofit entities like Concordia.

Two campuses, one mission        

Renovating the buildings and constructing the annex resulted in a dramatic expansion of Concordia’s mission and program. Concordia Place’s two campuses now serve a multi-age population from babies to senior citizens, providing more than 300 children (95% of whom are not Lutheran) with childcare and after-school programs. Seventy percent of the children in the new program come from minority families, nearly half of which are headed by single parents.

Reverend Zook feels that the marginal added costs of preservation were a demonstration of Concordia’s “good-faith relationship to the community.” Instead of being lost to the wrecking ball, this former church serves a new organization’s mission as a place where, in the minister’s words, “The church’s witness of outreach is grounded in her service to the larger community of neighbors in which she lives.” +
--
Laurie Petersen is a regular contributor to Chicago Architect, the official publication of AIA Chicago, from which this article was adapted.

Related Stories

University Buildings | Dec 8, 2023

Yale University breaks ground on nation's largest Living Building student housing complex

A groundbreaking on Oct. 11 kicked off a project aiming to construct the largest Living Building Challenge-certified residence on a university campus. The Living Village, a 45,000 sf home for Yale University Divinity School graduate students, “will make an ecological statement about the need to build in harmony with the natural world while training students to become ‘apostles of the environment’,” according to Bruner/Cott, which is leading the design team that includes Höweler + Yoon Architecture and Andropogon Associates.

University Buildings | Dec 5, 2023

The University of Cincinnati builds its largest classroom building to serve its largest college

The University of Cincinnati’s recently completed Clifton Court Hall unifies the school’s social science programs into a multidisciplinary research and education facility. The 185,400-sf structure is the university’s largest classroom building, serving its largest college, the College of Arts and Sciences.

MFPRO+ News | Dec 5, 2023

DOE's Zero Energy Ready Home Multifamily Version 2 released

The U.S. Department of Energy has released Zero Energy Ready Home Multifamily Version 2. The latest version of the certification program increases energy efficiency and performance levels, adds electric readiness, and makes compliance pathways and the certification process more consistent with the ENERGY STAR Multifamily New Construction (ESMFNC) program.

Architects | Dec 5, 2023

Populous celebrates its 40th anniversary with a photo exhibit of its works

The firm partnered with Getty Images to assemble more than 60 images, many capturing fan ardor.

Office Buildings | Dec 1, 2023

Amazon office building doubles as emergency housing for Seattle families

The unusual location for services of this kind serves over 300 people per day. Mary's Place spreads across eight of the office's floors—all designed by Graphite—testing the status quo for its experimental approach to homelessness support.

Mixed-Use | Nov 29, 2023

Mixed-use community benefits from city amenities and ‘micro units’

Salt Lake City, Utah, is home to a new mixed-use residential community that benefits from transit-oriented zoning and cleverly designed multifamily units.

Giants 400 | Nov 28, 2023

Top 100 Laboratory Design Firms for 2023

HDR, Flad Architects, DGA, Elkus Manfredi Architects, and Gensler top BD+C's ranking of the nation's largest laboratory architecture and architecture/engineering (AE) firms for 2023, as reported in Building Design+Construction's 2023 Giants 400 Report.

Engineers | Nov 27, 2023

Kimley-Horn eliminates the guesswork of electric vehicle charger site selection

Private businesses and governments can now choose their new electric vehicle (EV) charger locations with data-driven precision. Kimley-Horn, the national engineering, planning, and design consulting firm, today launched TREDLite EV, a cloud-based tool that helps organizations develop and optimize their EV charger deployment strategies based on the organization’s unique priorities.

Market Data | Nov 27, 2023

Number of employees returning to the office varies significantly by city

While the return-to-the-office trend is felt across the country, the percentage of employees moving back to their offices varies significantly according to geography, according to Eptura’s Q3 Workplace Index.

Resiliency | Nov 27, 2023

All levels of government need to act to cope with climate-driven flooding and sea level rise

The latest National Climate Assessment highlights the need for local, state, and federal governments to adopt policies to mitigate the effects of climate-driven flooding and sea level rise, according to a policy expert with the National Resources Defense Council.

boombox1
boombox2
native1

More In Category


Retail Centers

Thinking outside the big box (store)

For over a decade now, the talk of the mall industry has been largely focused on what developers can do to fill the voids left by a steady number of big box store closures. But what do you do when big box tenants stay put?


Government Buildings

OSHA’s proposed heat standard published in Federal Register

The Occupational Safety and Health Administration (OSHA) has published a proposed standard addressing heat illness in outdoor and indoor settings in the Federal Register. The proposed rule would require employers to evaluate workplaces and implement controls to mitigate exposure to heat through engineering and administrative controls, training, effective communication, and other measures.


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021