flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Amid supply chain woes, building teams employ extreme procurement measures

Contractors

Amid supply chain woes, building teams employ extreme procurement measures

Project teams are looking to eliminate much of the guesswork around product availability and price inflation by employing early bulk-purchasing measures for entire building projects.


By David Barista, Editorial Director | March 28, 2022
Amid supply chain woes, building teams employ extreme procurement measures
Photo Pixabay

Fifty-two weeks. An entire year. That’s how long project teams are having to wait for certain building materials, systems, and equipment in the post-Covid environment. These include critical core-and-shell materials like steel, steel deck, steel joists, and roofing components such as ISO foam board insulation and fasteners. Even readily available “off-the-shelf” products like drywall, metal framing, and paint have lead times. Not to mention near-historic price inflation levels and shipping costs across almost every product category.

Faced with these immense supply chain issues—on top of the ongoing skilled labor shortage—building teams are forced to employ aggressive product procurement tactics to pull off new construction and major reconstruction programs on schedule—and anywhere close to budget. Common strategies include real-time price tracking, product availability analysis during the design and bidding phases, more-optimal project planning (duh!), and sourcing locally, when possible. 

Some project teams are looking to eliminate much of the guesswork around product availability and price inflation by employing early bulk-purchasing measures for entire building projects, even multi-build developments. This “buy-and-store” approach to product procurement has worked for several recent healthcare projects led by design and construction giant Haskell, says Denise Muth, Project Director with the firm’s Infrastructure and Transportation group. 

ALSO SEE: How building owners and developers can get ahead of the next supply chain disaster

“For one hospital project, it was determined to buy the whole project out from the start and utilize local storage leased by the hospital,” says Muth. “On another project, we accelerated roofing, MEP equipment, elevators, and steel to help jumpstart the lead time process while the balance of design is completed. Depending on the stage of design, our owners are encouraged to purchase the entire project as quickly as possible.”

AEC industry consultant Ryan Bosworth, Principal with Rider Levett Bucknall, urges project teams to take advantage of the glut in vacant or derelict retail stores, especially big boxes, to purchase building products in bulk and warehouse them locally. “Landlords are begging for revenue while they reposition properties,” he says, adding that these spaces are relatively inexpensive to rent and require little build-out.

This bulk-purchasing approach, while effective, does have its obstacles, says Muth, including added front-loaded costs for owners/developers, insurance considerations related to storage facilities, and the risk of changes to specifications or design after materials have been ordered and stored.

Related Stories

Office Buildings | Mar 3, 2015

Former DuPont lab to be converted into business incubator near UPenn campus

The new Pennovation Center will provide collaborative and research spaces for educators, scientists, students, and the private sector.

Sponsored | BIM and Information Technology | Mar 3, 2015

The great debate: Is 3D PDF really BIM?

You can pull apart buildings, cut through floors, and view simulated animation for assembly instructions all within a PDF.

Codes and Standards | Mar 2, 2015

Proposed energy standard for data centers, telecom buildings open for public comment

The intent of ASHRAE Standard 90.4P is to create a performance-based approach that would be more flexible and accommodating of innovative change.

Contractors | Mar 2, 2015

Nonresidential construction spending dips in January, still outpaced 2014

Nonresidential construction spending fell 2% in January, which is the largest setback to spending since January 2014, according to the March 2 release from the U.S. Census Bureau.

K-12 Schools | Mar 1, 2015

Are energy management systems too complex for school facility staffs?

When school districts demand the latest and greatest, they need to think about how those choices will impact the district’s facilities employees.

Industrial Facilities | Feb 27, 2015

Massive windmill will double as mixed-use entertainment tower in Rotterdam

The 571-foot structure will house apartments, a hotel, restaurants, even a roller coaster.

Office Buildings | Feb 26, 2015

Using active design techniques to strengthen the corporate workplace and enhance employee wellness

The new Lentz Public Health Center in Nashville, Tenn., serves as a model of how those progressive and healthy changes can be made.

K-12 Schools | Feb 26, 2015

Should your next school project include a safe room?

Many school districts continue to resist mandating the inclusion of safe rooms or storm shelters in new and existing buildings. But that may be changing.

K-12 Schools | Feb 26, 2015

Construction funding still scarce for many school districts

Many districts are struggling to have new construction and renovation keep pace with student population growth.

K-12 Schools | Feb 26, 2015

D.C.'s Dunbar High School is world's highest-scoring LEED school, earns 91% of base credits

The 280,000-sf school achieved 91 points, out of 100 base points possible for LEED, making it the highest-scoring school in the world certified under USGBC’s LEED for Schools-New Construction system.

boombox1
boombox2
native1

More In Category




Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021