Amid supply chain woes, building teams employ extreme procurement measures

Contractors

Amid supply chain woes, building teams employ extreme procurement measures

Project teams are looking to eliminate much of the guesswork around product availability and price inflation by employing early bulk-purchasing measures for entire building projects.


By David Barista, Editorial Director | March 28, 2022
Amid supply chain woes, building teams employ extreme procurement measures
Photo Pixabay

Fifty-two weeks. An entire year. That’s how long project teams are having to wait for certain building materials, systems, and equipment in the post-Covid environment. These include critical core-and-shell materials like steel, steel deck, steel joists, and roofing components such as ISO foam board insulation and fasteners. Even readily available “off-the-shelf” products like drywall, metal framing, and paint have lead times. Not to mention near-historic price inflation levels and shipping costs across almost every product category.

Faced with these immense supply chain issues—on top of the ongoing skilled labor shortage—building teams are forced to employ aggressive product procurement tactics to pull off new construction and major reconstruction programs on schedule—and anywhere close to budget. Common strategies include real-time price tracking, product availability analysis during the design and bidding phases, more-optimal project planning (duh!), and sourcing locally, when possible. 

Some project teams are looking to eliminate much of the guesswork around product availability and price inflation by employing early bulk-purchasing measures for entire building projects, even multi-build developments. This “buy-and-store” approach to product procurement has worked for several recent healthcare projects led by design and construction giant Haskell, says Denise Muth, Project Director with the firm’s Infrastructure and Transportation group. 

ALSO SEE: How building owners and developers can get ahead of the next supply chain disaster

“For one hospital project, it was determined to buy the whole project out from the start and utilize local storage leased by the hospital,” says Muth. “On another project, we accelerated roofing, MEP equipment, elevators, and steel to help jumpstart the lead time process while the balance of design is completed. Depending on the stage of design, our owners are encouraged to purchase the entire project as quickly as possible.”

AEC industry consultant Ryan Bosworth, Principal with Rider Levett Bucknall, urges project teams to take advantage of the glut in vacant or derelict retail stores, especially big boxes, to purchase building products in bulk and warehouse them locally. “Landlords are begging for revenue while they reposition properties,” he says, adding that these spaces are relatively inexpensive to rent and require little build-out.

This bulk-purchasing approach, while effective, does have its obstacles, says Muth, including added front-loaded costs for owners/developers, insurance considerations related to storage facilities, and the risk of changes to specifications or design after materials have been ordered and stored.

Related Stories

Contractors | Nov 5, 2015

Budget bill provision raises OSHA fines for first time in 25 years

Inflation-adjusted penalty hikes could go up as much as 80%.

Contractors | Nov 3, 2015

ABC, AIA & NAHB: Residential, nonresidential construction growth expected in 2016

Economists from the three trade associations discussed several indicators for sector performance in a joint web conference.

Contractors | Nov 2, 2015

ABC: September's nonresidential spending slip no cause for concern

Despite the monthly drop, September's year-over-year increase is largest in seven years. Seven of 16 nonresidential construction sectors saw spending increases.

Contractors | Oct 30, 2015

ABC: Economic growth stronger than headline GDP figure suggests

GDP expanded 1.5% during the third quarter while nonresidential fixed investment expanded by 2.1% during that period.

BIM and Information Technology | Oct 29, 2015

MIT develops ‘river of 3D pixels’ to assemble objects

The Kinetic Blocks can manipulate objects into shapes without human interference.

Contractors | Oct 28, 2015

Office construction costs highest in New York City, San Francisco, says CBRE

A CBRE report found that New York’s construction costs are more than $500 per sf. San Francisco isn’t too far behind.

Contractors | Oct 16, 2015

ABC report: Confidence rises during the first half of the year

In the first half, sales expectations and profit margin expectations rose while staffing level intentions dipped slightly.

Contractors | Oct 7, 2015

Construction equipment continues to be vulnerable to theft

Poor security and lax inventory control make jobsites sitting ducks for robbers, according to crime-data analysis by LoJack. 

Office Buildings | Oct 5, 2015

Renderings revealed for Apple's second 'spaceship': a curvy, lush office complex in Sunnyvale

The project has been dubbed as another “spaceship,” referencing the nickname for the loop-shaped Apple Campus under construction in Cupertino. 

Contractors | Oct 2, 2015

OSHA’s top 10 workplace safety violations for 2015

Fall protection, hazard communication lead the list.

boombox1
boombox2
native1

More In Category




Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021