Amazon will heat its new Seattle campus with waste heat from next-door data centers

Energy Efficiency

Amazon will heat its new Seattle campus with waste heat from next-door data centers

Up to 4 million kilowatt-hours of energy will be saved each year.  


By John Caulfield, Senior Editor | November 16, 2015

Amazon's Denny Triangle campus in Seattle. Rendering courtesy NBBJ

Next month, Amazon.com is scheduled to open the first phase of its massive Denny Triangle campus in Seattle. Through a unique partnership, the spheres and towers that comprise Amazon’s four-block, 4-million-sf campus will be heated by waste heat recovered from the 34-story Westin Building Exchange across the street.

The Seattle Times reports that 70% of the Westin Building Exchange’s 400,000 sf is dedicated to data centers that are throwing off tremendous amounts of excess heat.

The building produces heat equivalent to 11 megawatts per day. Through an agreement with Pacific Northwest, which routes nearly all of its Internet traffic through the data centers in Westin, the building will transfer up to five megawatts to Amazon, which is purchasing the energy at a discounted rate. Recapturing this waste heat is expected to save about 4 million kilowatt-hours of energy per year.

Here’s how this system will work, according to the Times and the Seattle Post-Intelligencer:  When the Amazon buildings need heat, that will signal two heat pumps that collect heat from the data centers in the Westin Building Exchange, and use it to heat water traveling via pipes from the roof of the Westin building and through its floors to a refrigerator-sized steel-plated heat exchanger in Westin’s basement.

 

Image courtesy Amazon.com and McKinstry.

 

By the time that water reaches the exchanger, its temperature exceeds 70 degrees Fahrenheit. The exchanger transfers that heat through pipes running under the street to Amazon’s campus, which returns cooler water via the exchanger to the data centers.

When this system is fully functional, it will be circulating up to 3,000 gallons of water per minute.

Several entities collaborated on this project, which has been in the works for three years. They include McKinstry, which designed the heat-exchange system; and Clise Development, which co-owns the Westin Building Exchange with Digital Realty Trust, and sold Amazon the four blocks for its campus. Clise and McKinstry formed a partnership called Eco District for this project.

The agreement also involved several city agencies including its office of sustainability and environment. The Post-Intelligencer reports that one of Amazon’s building is already using this so-called district heating system that will ultimately provide heat for more than 3 million sf of office space.

Richard Stevenson, Clise Properties’ president, estimates the cost of this system in “the low millions” that would pay for itself in energy savings.

While heat exchange isn’t a new concept, it usually involves only one building, and rarely on the scale of this project. The Times quotes Susan Wickwire, executive director of the Seattle 2030 District—which aims to significantly reduce energy and water use in buildings in Seattle by 2030—who believes the arrangement between Amazon and Pacific Northwest could provide “a smooth path” for similar agreements where building occupants work together to save energy and make their operations more efficient.

“We’re showing people it can be done,” John Schoettler, Amazon’s director of global real estate, told the Times. “If other developments can model this, that’s a win-win.”

Amazon’s Denny Triangle campus, designed by NBBJ, will include three intersecting glass spheres that form a five-story office building, a 38-story tower, and 18,000 sf of retail. Amazon expects to be fully moved into these buildings in a couple of years.

Related Stories

| Feb 16, 2012

4.8-megawatt solar power system completed at Jersey Gardens Mall

Solar array among the largest rooftop systems in North America.

| Feb 14, 2012

Angelo State University opens doors to new recreation center expansion

  Designed by SmithGroup, the JJR_Center for Human Performance offers enhanced fitness options, dynamic gathering space.

| Feb 14, 2012

SAIC selected for architectural and engineering design services at Lajes Field, Azores

SAIC’s services will include a broad variety of new construction projects and maintenance and repair projects

| Feb 14, 2012

Thornton Tomasetti names Al Hashimi vice president for its Middle East Operations

Al Hashimi is joining the company to help expand Thornton Tomasetti’s business in the region and support clients locally.

| Feb 13, 2012

WHR Architects renovation of Morristown Memorial Hospital Simon Level 5 awarded LEED Gold

Located in the Simon Building, which serves as the main entrance leading into the Morristown Memorial Hospital campus, the project comprises three patient room wings connected by a centralized nursing station and elevator lobby.

| Feb 10, 2012

Task force addresses questions regarding visually graded Southern Pine lumber

Answers address transition issues, how to obtain similar load-carrying capabilities, and why only some grades and sizes are affected at this time. 

| Feb 8, 2012

World’s tallest solar PV-installation

The solar array is at the elevation of 737 feet, making the building the tallest in the world with a solar PV-installation on its roof.

| Feb 6, 2012

Kirchhoff-Consigli begins Phase 2 renovations at FDR Presidential Library and Museum

EYP Architecture & Engineering is architect for the $35 million National Archives Administration project.

| Feb 6, 2012

Siemens gifts Worcester Polytechnic Institute $100,000 for fire protection lab renovation

Siemens support is earmarked for the school’s Fire Protection Engineering Lab, a facility that has been forwarding engineering and other advanced degrees, graduating fire protection engineers since 1979.

| Feb 2, 2012

Call for Entries: 2012 Building Team Awards. Deadline March 2, 2012

Winning projects will be featured in the May issue of BD+C. 

boombox1
boombox2
native1

More In Category

Sustainable Design and Construction

Northglenn, a Denver suburb, opens a net zero, all-electric city hall with a mass timber structure

Northglenn, Colo., a Denver suburb, has opened the new Northglenn City Hall—a net zero, fully electric building with a mass timber structure. The 32,600-sf, $33.7 million building houses 60 city staffers. Designed by Anderson Mason Dale Architects, Northglenn City Hall is set to become the first municipal building in Colorado, and one of the first in the country, to achieve the Core certification: a green building rating system overseen by the International Living Future Institute.




Glass and Glazing

The next generation of thermal glazing: How improving U-value can yield energy savings and reduce carbon emissions

The standards for energy-efficient construction and design have been raised. Due to the development of advanced low-e coatings for the interior surface and vacuum insulating technologies, architects now have more choices to improve U-values wherever enhanced thermal performance is needed to create eco-friendly spaces. These options can double or even triple thermal performance, resulting in annual energy savings and a positive return on carbon.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021