Construction is under way on the Greenland Tower Chengdu, a 468-meter-high crystalline skyscraper in Chengdu, China, designed by Adrian Smith + Gordon Gill Architecture.
When built, it will be the tallest building in southwestern China, surpassing Chengdu's current tallest buildings by more than 200 meters.
The multi-faceted glass tower was inspired by “the unique ice mountain topography around Chengdu,” the firm said. Plans indicate that inset LED lighting on the edges of the faceted glass will give viewers the impression of a shimmering glacier. The tower will thereby act as a light sculpture for the city of Chengdu.
The project is set for completion in 2018. It is part of a larger complex comprised of the main tower, two smaller towers, and a six-story podium. Office, retail, and residential space will all be included in these buildings, according to Next Big Future.
"The architecture and structure marry perfectly," the firm said in a statement. "The design fully considers the structural requirements of supertall buildings in a high seismic zone, using a geometrical plan, a tapered form, and a high-performance damper bracing system to ensure the structure’s stability and efficiency."
Related Stories
| Mar 19, 2012
Smith Carter joins forces with Genivar
Smith Carter has a workforce of some 190 employees and designs complex buildings in challenging environments.
| Mar 19, 2012
HKS Selected for Baylor Medical Center at Waxahachie
Baylor Medical Center at Waxahachiewill incorporate advanced technology including telemedicine, digital imaging, remote patient monitoring, electronic medical records and computer patient records.
| Mar 19, 2012
Mixed-use project redefines Midtown District in Plantation, Fla.
Stiles Construction is building the residential complex, which is one of Broward County’s first multifamily rental communities designed to achieve LEED certification from the USGBC.
| Mar 16, 2012
Temporary fix to CityCenter's Harmon would cost $2 million, contractor says
By contrast, CityCenter half-owner and developer MGM Resorts International determined last year that the Harmon would collapse in a strong quake and can't be fixed in an economical way. It favors implosion at a cost of $30 million.
| Mar 16, 2012
Work on Oxnard, Calif. shopping center resumes after a three-year hiatus
Stalled since 2009, developers of the Collection at RiverPark decided to restart construction on the outdoor mall.
| Mar 16, 2012
Stego embarks on HPD Pilot Program
Vapor barrier manufacturer strives to provide better green choices to designers and builders.
| Mar 16, 2012
Marvin Windows and Doors accepting entries for fourth-annual myMarvin Architect’s Challenge
Architects in U.S. and abroad offered the chance to showcase their very best work.
| Mar 14, 2012
Hearing to decide fate of unfinished Harmon in Las Vegas under way
The testimony began with CityCenter consulting engineer Chukwuma Ekwueme methodically showing photo after photo of parts of the Harmon, where he and his team had chipped away the concrete pillars and beams to examine the steel reinforcing bars inside.
| Mar 14, 2012
Firestone names 2012 Master Contractor Award Winners
Annual award acknowledges industry’s top roofing professionals.