ABC: Construction activity increases as backlog edges higher

Contractors

ABC: Construction activity increases as backlog edges higher

The backlog indicator is up 1% to 8.5 months during the second quarter of 2015.


By Associated Builders and Contractors | September 9, 2015

Photo: cegoh/Pixabay

Associated Builders and Contractors' (ABC) Construction Backlog Indicator (CBI) expanded by 1% to 8.5 months during the 2nd quarter of 2015. Backlog declined 3% during the 1st quarter, which was punctuated by harsh winter weather and the lingering effects of the West Coast ports slowdown. CBI stands roughly where it did a year ago, indicative of an ongoing recovery in the nation's nonresidential construction industry.

"The nation's nonresidential construction industry is now one of America's leading engines of growth," said ABC Chief Economist Anirban Basu. "The broader U.S. economic recovery is now in its 74th month, but remains under-diversified, led primarily by a combination of consumer spending growth as well as residential and nonresidential construction recovery. Were the overall economy in better shape, the performance of nonresidential construction would not be as closely watched. The economic recovery remains fragile despite a solid GDP growth figure for the second quarter, and must at some point negotiate an interest-rate tightening cycle. Recent stock market volatility has served to remind all stakeholders how delicate the economic recovery continues to be."

 

 

Regional Highlights

  • The West experienced a significant expansion in backlog, rising 1.2 months following the resolution of the West Coast port slowdown, however backlog in the region remains nearly 2.5 months below its year-ago levels, the largest drop of any region. 
  • Backlog in the South has essentially returned to where it was two years ago, in part because of a slowdown in energy-related investment. The implication is that the average contractor remains busy, but boom-like conditions no longer prevail in energy-intensive communities.
  • Despite this, backlog in the South continue to hold the longest average construction backlog.
  • Backlog slipped for a second consecutive quarter in the Northeast, but remains above levels registered during the second half of 2013.
  • See charts and graphs here.
  •  

Industry Highlights

  • Backlog in the heavy industrial segment has never been higher during the length of the series, penetrating the seven-month mark for the first time. This represents an increase of more than two months in average backlog over the past two years. Average backlog was below five months during 2013's second half.
  • Industrial backlog has continued to rise despite the strength of the U.S. dollar, which has contributed to limited export growth.
  • Commercial/institutional backlog has remained above eight months on average for twelve consecutive quarters, a reflection of America's steady rate of employment expansion.
  • Backlog for all industry segments is higher on a year-over-year basis with exception of the commercial/institutional segment. Commercial/institution construction segments have been among the most active from a construction spending perspective in recent years. Therefore, the small adjustment in average backlog is not particularly worrisome.
  • See charts and graphs here.
  •  

 

Highlights by Company Size

  • On a quarterly basis, backlog rose or remained flat across all firm sizes.
  • Average construction backlog is higher or roughly the same as year-ago levels for firms of all size categories with the exception of a half-month drop in backlog among firms generating $100 million or more in annual revenues.
  • The largest firms, however, continue to have the lengthiest average backlog at 10.7 months.
  • See charts and graphs here.

Related Stories

| Apr 10, 2013

6 funding sources for charter school construction

Competition for grants, loans, and bond financing among charter schools is heating up, so make your clients aware of these potential sources.

| Apr 9, 2013

FMI predicts 8% rise in construction put in place for 2013

FMI, the largest provider of management consulting and investment banking services to the engineering and construction industry released today its Q1-2013 Construction Outlook. The forecast for total construction-put-in-place for 2013 continues to show an increase of 8% over 2012 levels. 

| Apr 8, 2013

Most daylight harvesting schemes fall short of performance goals, says study

Analysis of daylighting control systems in 20 office and public spaces shows that while the automatic daylighting harvesting schemes are helping to reduce lighting energy, most are not achieving optimal performance, according to a new study by the Energy Center of Wisconsin.

| Apr 6, 2013

First look: GlaxoSmithKline's double LEED Platinum office

GlaxoSmithKline and Liberty Property Trust/Synterra Partners transform the work environment with the opening of Five Crescent Drive

| Apr 5, 2013

‘Retainage Laws in the 50 States’ manual from ASA available for subcontractors

A reference manual published by the American Subcontractors Association, Retainage Law in the 50 States, is available for construction subcontractors to understand retainage laws across the U.S.

| Apr 5, 2013

Bangkok gets a leaning tower, that may topple

A seven-story apartment tower under construction in Bangkok has started to tilt and is on the verge of toppling.

| Apr 5, 2013

Snøhetta design creates groundbreaking high-tech library for NCSU

The new Hunt Library at North Carolina State University, Raleigh, incorporates advanced building features, including a five-story robotic bookBot automatic retrieval system that holds 2 million volumes in reduced space.

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021