flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

7 Do's and Don'ts for PV roof rack installation

7 Do's and Don'ts for PV roof rack installation

As PVs grow in popularity, nearly half of all installations require roof rack systems. Our expert tells how to do the job right and protect your client’s roof.


By By Tim Gregorski, Senior Editor | September 7, 2012
This article first appeared in the September 2012 issue of BD+C.

Solar photovoltaic applications in the U.S. continue to grow at an astounding pace, even though the domestic market has tapped only a small portion of the potential PV development.

So far, 2012 has been a strong year for the PV industry, with approximately 2,800 MW of installations projected, according to the Solar Energy Industries Association. The future looks even brighter, with forecasts for PV installations expected to rise at a compound annual growth rate of 30% through 2012.

To compare, the U.S. solar energy industry installed 1,855 MW of photovoltaic solar systems in 2011, representing a 109% increase over 2010. That’s enough to power 370,000 homes. The SEIA reported the fourth quarter of 2011 alone recorded 776 MW of PV systems installed in the U.S., making it the largest installation of photovoltaics for any quarter in PV market history.

Nearly half the installed and planned PV projects in the U.S. are expected to be roof-mounted installations. That’s a scary prospect for roofing product manufacturers and contractors, because an improperly installed PV rack can tear a roof to pieces in no time.

BD+C asked James R. Kirby, Vice President of Sustainability for the Center for Environmental Innovation in Roofing, Washington, D.C., for advice about what Building Teams and building owners should know about roof rack PV systems.

1. DO use the proper flashing techniques for steep-slope roofs.

Because water flows downhill, for steep-slope roofs (which, according to ASTM standard E 1918-97, are roofs in which the uppermost part is installed at a slope of 2:12 or more), proper overlaps during installation are critically important. Commonly used materials for this type of installation are metal flashings with compression gaskets or counterflashing at roof penetrations (or both).

Flashing works because it is located above the level where water drains.

For vertical penetrations, the flashing is the primary weatherproofing element. Counterflashings are secondary and placed above the flashing piece.

7 do’s and don’ts of PV roof rack installation


1. DO use the proper flashing techniques for steep-slope roofs.
2. DO avoid improper flashing techniques for low-slope roofs.
3. DON’T allow for hunt-and-peck pilot holes on steep-slope roofs.
4. DO maintain the roof and PV system after installation.
5. DON’T consider initial payback alone: Factor in life cycle costs.
6. DON’T equate a non-penetrating rack system with zero roof penetrations.
7. DO ask about ballasted rack systems on low-slope roofs and the impact of movement, abrasion, drainage, and wind.

In steep-slope situations where flashing is not feasible or necessary, the counterflashing should extend at least to the nail line of the shingle above. Both methods are acceptable for long-term PV roof rack installation.

“Not all low-slope penetrations use counterflashings, but they all need flashings,” says Kirby. “For steep-slope roofs, it’s a bit different. Shingles basically flash the shingle below by covering up the nails. So if a vertical presentation is attached to a roof, then it needs to be flashed.”

However, in steep-slope roofs, a counterflashing can be inserted under a shingle and over a fastener that’s securing the PV rack.

2. DO avoid improper flashing techniques for low-slope roofs.

For low-slope roofs with little slope to drain, rainwater can pond in low spots or where drainage is interrupted. Drainage can be interrupted by large or wide penetrations or by ballasted PV racks.

It is critical to use flashing that matches the roof’s membrane system. “For low-slope roofs, the flashing material is interfaced with the membrane material, and the materials are not interchangeable,” says Kirby.

Building Teams should support their clients by making sure that the PV contractor incorporates the proper flashing technique for penetrating PV racks.

3. DON’T permit hunt-and-peck pilot holes on steep-slope roofs.

Pilot holes are the number one reason for callbacks for complications after installation. PV installers often use a thin drill bit to locate a rafter in order to position the attachments. Unfortunately, they don’t always repair their “investigation” holes. There are ways to repair these pilot holes, but it’s best not to “hunt-and-peck” in the first place.

“Rafters should be located by observing the eave and ridge,” says Kirby. “Locate nails in the fascia board, which is commonly nailed into the ends of the roof rafters.”

Caution: Vertical stanchions generally require one or two fasteners to be installed into the rafter, not the roof deck, in order to achieve proper pull-out resistance to wind uplift.

4. DO maintain the roof and PV system after installation.

A roof’s chief priority is to keep water and weather out of the building. Therefore, the ability to perform maintenance is critical to the long-term success of a low-slope roof. Certain styles of ballasted PV racks can make it difficult to perform roof maintenance. Some styles must be removed or relocated in order to get to the roof surface for maintenance.

Fortunately, a number of newer rack styles and types that recognize the need for roof maintenance have been developed. “Those styles and types of PV systems will be the long-term success stories in the rooftop PV industry,” says Kirby. “Roof-friendly racking systems are a relatively new trend, and it’s up to the roofing industry to push for more roof-friendly racking systems.”

5. DON’T consider initial payback alone: Factor in life cycle costs.

It’s not easy getting most building owners to think long-term, but Building Teams should counsel clients about the PV investment in the cost per year over the 25- to 30-year life of the roof and the PV system.

According to Kirby, a building owner may expect a relatively short-term payback from the PV system in a certain number of years, but the owner also needs to recognize that the inverter will likely have to be replaced at year 12 or 15.

And what about the cost of a roof replacement if it’s not done at the time of installation? The age of the roof must be considered at the time of PV installation because it’s critical to the long-term success of both the roof and the PV installation.

“A roof that is too old could mean that the PV system may have to be removed along with the old roof,” says Kirby. “If the owner didn’t prepare for the cost, the PV system may not be installed again.”

6. DON’T equate a non-penetrating rack system with zero roof penetrations.

A building owner may be buying a non-penetrating PV rack system, but how do the PV system’s electrical lines get into the building? According to Kirby, the answer is often “through the roof.”

A junction box may be supported by non-penetrating supports; however, this does not eliminate the penetration caused by electrical lines. The entry point for the DC conduit must be properly flashed. Therefore, most if not all PV systems will have at least one penetration.

The same premise is true for both types of non-penetrating systems––adhered and ballasted. It is also important to note that if the PV installation is to occur on a low-slope roof that is under warranty, a contractor recommended by the roofing membrane manufacturer is required in order to keep the warranty from being voided.

7. DO ask about ballasted rack systems on low-slope roofs and impact of movement, abrasion, drainage, and wind.

There are critical questions you should ask the PV contractor prior to installation:

  • How does a ballasted PV system rest upon the roof assembly?
  • What will happen over time on the rooftop where the ballasted system meets the roof surface?
  • Will it collect water and eventually cause weakness?
  • Will there be dust or debris between the roof surface and the bottom of the rack?
  • Will dust or debris abrade the roof surface over time?
  • What measures can be taken to protect the integrity of the roof at the point of contact?

According to Kirby, asking these questions prior to installation is important because any problems that occur may reduce the return on investment to the property owner, while proper installation will keep maintenance costs in check over the life of the rooftop PV system. +

Related Stories

High-rise Construction | Aug 11, 2015

Calatrava's Turning Torso wins CTBUH's 10 Year Award

The 623-foot, 57-story tower was the world's first twisting skyscraper. Completed in 2005, the building, designed by Santiago Calatrava, rotates 90 degrees along its height. 

Architects | Aug 11, 2015

Architecture firm compensation trending upwards

Latest AIA compensation survey finds average compensation for staff positions up 3.5 percent from early 2013

Architects | Aug 11, 2015

12 architecture schools join NCARB's 'speedy path to licensure' program

For architecture students, a license to practice may soon be available as early as graduation day

Architects | Aug 10, 2015

HDR expands its Canadian presence through merger with CEI Architecture

Public-private partnerships are expected to be one of the combined entity’s strengths.  

Retail Centers | Aug 10, 2015

Walgreens’ flagship in Hawaii harkens back to the island’s fishing culture

A house where canoes were made served as the model for this drug superstore’s design. 

Giants 400 | Aug 7, 2015

GOVERNMENT SECTOR GIANTS: Public sector spending even more cautiously on buildings

AEC firms that do government work say their public-sector clients have been going smaller to save money on construction projects, according to BD+C's 2015 Giants 300 report.

Giants 400 | Aug 7, 2015

K-12 SCHOOL SECTOR GIANTS: To succeed, school design must replicate real-world environments

Whether new or reconstructed, schools must meet new demands that emanate from the real world and rapidly adapt to different instructional and learning modes, according to BD+C's 2015 Giants 300 report.

Giants 400 | Aug 7, 2015

MULTIFAMILY AEC GIANTS: Slowdown prompts developers to ask: Will the luxury rentals boom hold?

For the last three years, rental apartments have occupied the hot corner in residential construction, as younger people gravitated toward renting to be closer to urban centers and jobs. But at around 360,000 annual starts, multifamily might be peaking, according to BD+C's 2015 Giants 300 report.

Giants 400 | Aug 7, 2015

UNIVERSITY SECTOR GIANTS: Collaboration, creativity, technology—hallmarks of today’s campus facilities

At a time when competition for the cream of the student/faculty crop is intensifying, colleges and universities must recognize that students and parents are coming to expect an education environment that foments collaboration, according to BD+C's 2015 Giants 300 report.

Giants 400 | Aug 7, 2015

RECONSTRUCTION AEC GIANTS: Restorations breathe new life into valuable older buildings

AEC Giants discuss opportunities and complications associated with renovation, restoration, and adaptive reuse construction work.

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021