5 tips for running a successful BIM coordination meeting

5 tips for running a successful BIM coordination meeting

Make the most of BIM coordination meetings by following these helpful tips.


By Jared Krieger, AIA, LEED AP, Gensler | May 30, 2013

Building information modeling tools are great, but if you can't run efficient, productive coordination meetings, the Building Team will never realize the benefits of true BIM coordination. Here are some helpful tips for making the most of BIM coordination meetings based on my experience working on BIM/VDC-driven projects:

1. Practice and prepare. Yes, practice for a meeting. The more you do it the more productive your meetings can be. It takes some skill to be able to navigate the model and have the correct models loaded and visibility settings. Spending 15 minutes before loading models and opening views for the areas of focus will save you a lot of waiting and down time during the meeting.

2. Assign a "designated driver.” This person needs to be familiar with the model and savvy with the software platform. Models can be quite cumbersome, and it can slow down the meeting when a group of people have to watch someone poorly navigating the model. That will quickly kill your productivity.

SEE JARED KRIEGER AT THE 2013 AIA NATIONAL CONVENTION
Jared Krieger, Project Architect in Gensler’s Washington, D.C., office, will speak on “Maximizing BIM: How to Successfully Execute a Fully Integrated BIM Project,” at the AIA National Convention in Denver on Friday, June 21, 6:00-7:00 p.m. More information: http://convention.aia.org.

3. Use your team’s time wisely. You don’t always have to have the full team in the room at the same time. Consider splitting the meeting into structured trades. For example, meet with the structural engineer for the first portion of the meeting to review structural specific coordination. Then have some overlap time with MEP and structural for common coordination. Finish the meeting with MEP-specific coordination.

4. Use meeting notes to stay focused. Open action items and homework from the previous meeting should be the basis for discussion in your current meeting. Use this structure to keep yourself on track, and resolve open coordination issues before moving on to new items.

5. Talk about this process early in the project. For most people, using a collaboratively focused process leveraging technology will be a new process. It may sound like a large time commitment, but if done correctly it will save you time in the long run. Educate the team early on and set/manage expectations.

Jared Krieger, AIA, LEED AP, is a Project Architect and BIM/VDC expert based in Gensler's Washington, D.C., office. He can be reached at jared_krieger@gensler.com.

Related Stories

AEC Tech | Oct 28, 2020

Meet Jaibot, Hilti's new construction robot

The semi-autonomous robot is designed to assist MEP contractors with ceiling-drilling applications. 

Hotel Facilities | Oct 27, 2020

Hotel construction pipeline dips 7% in Q3 2020

Hospitality developers continue to closely monitor the impact the coronavirus will have on travel demand, according to Lodging Econometrics.

Data Centers | Oct 26, 2020

Speed to market is biggest obstacle for burgeoning data center construction sector

Hyperscale and edge computing are driving growth in data center and mission critical facilities construction.

Adaptive Reuse | Oct 26, 2020

Mall property redevelopments could result in dramatic property value drops

Retail conversions to fulfillment centers, apartments, schools, or medical offices could cut values 60% to 90%.

Multifamily Housing | Oct 15, 2020

L.A., all the way

KFA Architecture has hitched its wagon to Los Angeles’s star for more than 40 years.

Architects | Oct 14, 2020

The Weekly Show: AI for building facade inspections; designing a world-class architecture firm

The October 15 episode of BD+C's "The Weekly" is available for viewing on demand.

Coronavirus | Oct 8, 2020

The Weekly show: Statue of Liberty Museum, emotional learning in K-12, LA's climate change vulnerability

The October 8 episode of BD+C's "The Weekly" is available for viewing on demand.

Architects | Oct 8, 2020

Gensler’s annual report chronicles the firm’s ‘transformation’

The firm positions itself as a leading voice for how building design plays a central role in meeting society’s evolving demands.

Smart Buildings | Oct 1, 2020

Smart buildings stand on good data

The coming disruption of owning and operating a building and how to stay ahead through BIM.

Architects | Oct 1, 2020

BIG imagines how we could live on the moon

The architecture firm has partnered with ICON on the project.

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021