The largest 3D-printed building in Europe will have a much lower carbon footprint.


By John Caulfield, Senior Editor | May 4, 2023
The walls of a data center in Germany are being 3D printed. image credit: COBOD
3D printers will take about 140 hours to complete the walls of a 6,600-sf building in Heidelberg, Germany. Image: COBOD

Europe’s largest 3D-printed building is scheduled for completion in July in Heidelberg, Germany.

Spearheaded by Kraus Group, a local real estate developer, investor, and manager, this 6,600-sf project is being constructed for Heidelberg IT Management GmbH and Company KG, a cloud and data center provider. The building will contain an IT server hotel.

PERI 3D Construction is using a BOD2 3D construction printer to print the building’s walls, which PERI estimates will take only 140 hours to complete, or the equivalent of printing four square meters of building per hour.

The printer robots are provided by COBOD, which produced Europe’s first 3D-printed building in 2017 and has sold more than 65 3D printers worldwide. Denmark-based COBOD’s key shareholders include General Electric, CEMEX, Holcim Group, and PERI, the latter of which first used a BOD2 machine in 2020.

Looking to print taller buildings

 

An aerial view of the construction site. Image; Peri Construction
An aerial view of the construction site for what will be Europe's largest 3D-printed building. Image: PERI Construction
 

The Heidelberg project is 162 ft long by 121 ft wide by 30 ft high. Its construction started on March 31. Hans-Jörg Kraus, managing partner of Kraus Group, said in a prepared statement that this project represents his firm’s commitment to innovative and sustainable construction methods.

Henrik Lund-Nielsen, COBOD’s founder and GM, added that the two key benefits of 3D printing for construction are speed of execution and design freedom, noting that other projects his company’s printers have been used for include residential housing in Africa and offices in Germany.

The Heidelberg data center’s architects are SSV Architekten and Mense Korte. Heidelberg Materials is supplying an estimated 450 tons of its i.tech 3D printing mortar for this project, which is 100 percent recyclable and contains a binder with a carbon footprint that’s 55 percent lower than Portland cement.

 

The building's walls are being printed in layers.
A special mortar is being used to print the building's walls, whose carbon footprint will be considerably less than if Portland cement had been applied. Image: Heidelberg Materials
 

Construction Europe magazine’s website reports that without 3D printing, the unusual design of the building’s walls would have required customized form work. COBOD’s 3D printing system is currently limited to around 9 meters in height, and the company is reportedly working on new technology that will allow its robots to print at taller heights. (The world’s tallest 3D-printed building to date is the three-story, 9.9-meter-high Dar Arkan villa in Saudi Arabia.)

The cost of the Heidelberg project was not disclosed.

Related Stories

Building Technology | Nov 10, 2016

New system from MIT may help buildings monitor stress and damage over time

The computational model is being tested on MIT’s Green Building.

Building Technology | Nov 10, 2016

Multifamily development in Miami will feature healthy indoor environments

The 100-unit tower will incorporate healthy living enhancements from The Wellness Habitat Company.

Building Technology | Oct 7, 2016

How much is that LEED point worth? A new tool provides answers

Autocase analyzes the financial, social, and environmental benefits of certification.

Building Technology | Oct 5, 2016

Autodesk’s new BUILD Space is focused on the future of making things in the built environment

The 34,000-sf facility will host teams from academia, industry, and practice doing work in fields including digital fabrication, design robotics, and industrialized construction.

Contractors | Aug 10, 2016

Dodge launches new app to simplify pros' search for suitable projects to bid and work on

The product, called PlanRoom, could be particularly useful in sharing data and communications among AEC teams.

Virtual Reality | Jul 30, 2016

Stantec to open VR showrooms in two offices

The firm moves into its second stage of testing this technology as a real-time design tool.  

Building Tech | Jul 14, 2016

Delegates attending political conventions shouldn’t need to ask ‘Can you hear me now?’

Each venue is equipped with DAS technology that extends the building’s wireless coverage.

Sponsored | Building Technology | Jul 11, 2016

3D scanning technology solves University of Iowa Children’s Hospital’s curved wall curveball

Gilbane Building Company utilized advanced 3D scanning technology as part of a virtual design and construction (VDC) solution to ensure quality control throughout the lifespan of the project

Building Technology | May 24, 2016

Tech is the new office perk, says a new survey of American workers

But most employees still see their companies falling on the dull side of the cutting edge. 

Green | May 16, 2016

Development team picked for largest Passive House project in North America

The 24-story curved building would be 70% more efficient than comparable housing in New York City.

boombox1
boombox2
native1

More In Category




Contractors

Contractors expect to spend more time on prefabrication, according to FMI study

Get ready for a surge in prefabrication activity by contractors. FMI, the consulting and investment banking firm, recently polled contractors about how much time they were spending, in craft labor hours, on prefabrication for construction projects. More than 250 contractors participated in the survey, and the average response to that question was 18%. More revealing, however, was the participants’ anticipation that craft hours dedicated to prefab would essentially double, to 34%, within the next five years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021