flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

2019 Data Center Giants Report: AEC firms stretch to keep up with data center demand

Giants 400

2019 Data Center Giants Report: AEC firms stretch to keep up with data center demand

This and more data center sector trends from Building Design+Construction's 2019 Giants 300 Report. 


By John Caulfield, Senior Editor  | August 28, 2019
2019 Data Center Giants Report DPR - Digital realty Ashburn, Va Photo Ulf Wallin

Last January, Digital Realty opened a 230,000-sf data center in Ashburn, Va., one of this sector’s most robust zones. Built by DPR Construction using concrete tilt-up panels, this was the Digital Realty’s first deployment of its mega-scale prototype, and the time from groundbreaking to IST/Occupancy took only eight months. Phase 1 includes a 6-MW data hall, the first of six halls with equal critical power planned over the data center’s three-year buildout period. Photo: Ulf Wallin

  

In 2018, Holder Construction did $1.38 billion in data center construction. As of May 2019, it had 28 data center projects in the works, and the firm expects construction this year to approach $3 billion. One such project—in Phoenix, for a large REIT—opened in July 2019 with 6 MW of processing capacity, and will reach 48 MW when it’s eventually built out to around 500,000 sf.

To keep pace with this sector’s expansion, Holder is increasing its headcount by 25%. “The AEC industry is very close to being overwhelmed by data center demand, especially for electricians,” says Tony TeVault, Vice President with Holder’s office in Atlanta. “Every market is at full capacity and equipment vendors are super-stretched.”

Data center sector growth is creating opportunities for AEC firms, as owners scramble to build facilities as fast as they can. “Speed to market” is this sector’s abiding objective, in part to accommodate looming 5G technology.

 

ALSO SEE: Top 35 Data Center Architecture Firms
ALSO SEE: Top 50 Data Center Engineering Firms
ALSO SEE: Top 45 Data Center Construction Firms

 

“As soon as a client receives a positive capacity demand signal in a region, the race is on to design and build a data center at rapid pace,” says James Coe, PE, Senior Principal with Syska Hennessy, whom BD+C interviewed with Joshua Fluecke, PE, LEED AP, Associate Principal. They note that engineering design teams are under pressure to adapt a provider’s prescriptive design within an eight- to 12-week window, and to offer construction administration support for an accelerated build schedule that typically falls between seven and nine months.

“Contractors need to use every tool at their disposal to ensure just-in-time delivery of materials and methods like prefabrication to shorten schedules,” says John Arcello, Advanced Tech Core Market Co-Leader with DPR Construction. “The magic will happen in the planning stages: preconstruction and VDC services have the tools to drive the process,” especially in design-build collaborations that he says are more common within this sector.

Another “tool” some AEC firms have availed themselves of is the acquisition of talent and market share to serve a consolidating sector with fewer and bigger players. Last December, the engineering firm Morrison Hershfield merged with CCG Facilities, a mission-critical engineering firm. And last March, HED joined forces with the data-center specialty firm IDG.

 

Hyperscale and edge data center facilities prevail

The sector is polarized between two dominant building types: massive hyperscale facilities and much smaller data centers for edge computing, which are usually located near population centers to ensure smooth content delivery.

Hyperscale data centers are simply getting bigger. Robert Sty, PE, LEED AP, Director of the Tech Sector for HDR, says that it wasn’t too long ago when data centers with 20 MW of capacity were considered large. Now, hyperscale campuses are being planned for 200 to 300 MW of power and millions of square feet. Gary Murphy, a Principal with HED, says data centers are being designed for 500+ MW. “Data centers are becoming more industrialized: as demand grows, so does their scale and performance.”

Water cooling for cabinets is becoming more prevalent, as owners push the envelope on higher allowable temperatures to lower their operational costs. Terence Deneny, Vice President of Structure Tone’s Mission Critical division, has seen some users locate IT racks in parking lots to test equipment tolerances and take advantage of free air cooling. Matt Lamont, HKS’s Vice President and Mission Critical Team Leader–America West Region, adds that a key discussion among clients revolves around driving the power usage effectiveness (PUE) ratio—the power entering the data center over the power used—to sub 1.15 levels.

These hyperscale facilities put pressure on local utilities to provide the power, water, and industrial wastewater required for their operations, says Ken Gilmartin, Jacobs’ Senior Vice President and GM–Advanced Facilities and Federal Solutions.

For one client, construction engineer McKinstry led the testing of four different power generation solutions within a live data center to determine the best solution for a rollout across multiple locations. (The client chose natural gas.) Dan Ronco, McKinstry’s Director of Electrical Construction, adds that more clients are considering renewable energy sources. He cautions, however, that “the hard part is making intermittent renewables work in critical, always-on environments.”

Edge computing facilities support the market’s time-critical functions (e.g., streaming). Coe of Syska Hennessy has seen micro data centers as small as one cabinet within a facility to 150 kW self-contained modular buildings. HKS’s Lamont says that the “maximum load” of edge centers his firm has worked on has been 1,000 kW, and they often run without human personnel.

“These types of facilities must be approached as a product design, and not as a custom solution for each location,” says Bruce Edwards, RA, a Principal with Morrison Hershfield. He elaborates that because edge data centers are pretty similar, their standardized design and construction lend themselves to prefabrication or modular options.

“Prefabrication and modular construction for data centers is becoming more consistent and reliable,” says Annette Allen, Fluor’s Vice President, Business Development–Life Sciences and Advanced Manufacturing. “They can reduce the amount of engineering required, and drive capital efficiencies, meaning cost and scheduling certainty.”

 

MORE FROM BD+C'S 2019 GIANTS 300 REPORT

Tags

Related Stories

Giants 400 | Aug 22, 2023

2023 Giants 400 Report: Ranking the nation's largest architecture, engineering, and construction firms

A record 552 AEC firms submitted data for BD+C's 2023 Giants 400 Report. The final report includes 137 rankings across 25 building sectors and specialty categories.

Giants 400 | Aug 22, 2023

Top 175 Architecture Firms for 2023

Gensler, HKS, Perkins&Will, Corgan, and Perkins Eastman top the rankings of the nation's largest architecture firms for nonresidential building and multifamily housing work, as reported in Building Design+Construction's 2023 Giants 400 Report.

Giants 400 | Feb 9, 2023

New Giants 400 download: Get the complete at-a-glance 2022 Giants 400 rankings in Excel

See how your architecture, engineering, or construction firm stacks up against the nation's AEC Giants. For more than 45 years, the editors of Building Design+Construction have surveyed the largest AEC firms in the U.S./Canada to create the annual Giants 400 report. This year, a record 519 firms participated in the Giants 400 report. The final report includes 137 rankings across 25 building sectors and specialty categories.   

Giants 400 | Feb 6, 2023

2022 Reconstruction Sector Giants: Top architecture, engineering, and construction firms in the U.S. building reconstruction and renovation sector

Gensler, Stantec, IPS, Alfa Tech, STO Building Group, and Turner Construction top BD+C's rankings of the nation's largest reconstruction sector architecture, engineering, and construction firms, as reported in the 2022 Giants 400 Report.

Giants 400 | Feb 6, 2023

2022 Transit Facility Giants: Top architecture, engineering, and construction firms in the U.S. transit facility sector

Walsh Group, Skanska USA, HDR, Perkins and Will, and AECOM top BD+C's rankings of the nation's largest transit facility sector architecture, engineering, and construction firms, as reported in the 2022 Giants 400 Report.

Giants 400 | Feb 6, 2023

2022 Telecommunications Facility Sector Giants: Top architecture, engineering, and construction firms in the U.S. telecommunications facility sector

AECOM, Alfa Tech, Kraus-Anderson, and Stantec head BD+C's rankings of the nation's largest telecommunications facility sector architecture, engineering, and construction firms, as reported in the 2022 Giants 400 Report.

Giants 400 | Feb 6, 2023

2022 Religious Sector Giants: Top architecture, engineering, and construction firms in the U.S. religious facility construction sector

HOK, Parkhill, KPFF, Shawmut Design and Construction, and Wiss, Janney, Elstner head BD+C's rankings of the nation's largest religious facility sector architecture, engineering, and construction firms, as reported in the 2022 Giants 400 Report.

Giants 400 | Feb 6, 2023

2022 Justice Facility Sector Giants: Top architecture, engineering, and construction firms in the U.S. justice facility/public safety sector

Stantec, DLR Group, Turner Construction, STO Building Group, AECOM, and Dewberry top BD+C's rankings of the nation's largest architecture, engineering, and construction firms for justice facility/public safety buildings work, including correctional facilities, fire stations, jails, police stations, and prisons, as reported in the 2022 Giants 400 Report.

Giants 400 | Feb 6, 2023

2022 Parking Structure Giants: Top architecture, engineering, and construction firms in the U.S. parking structure sector

Choate Parking Consultants, Walker Consultants, Kimley-Horn, PCL, and Balfour Beatty top BD+C's rankings of the nation's largest parking structure sector architecture, engineering, and construction firms, as reported in the 2022 Giants 400 Report.

Giants 400 | Feb 3, 2023

Top Workplace/Interior Fitout Architecture, Engineering, and Construction Firms for 2022

Gensler, Interior Architects, AECOM, STO Building Group, and CBRE top the ranking of the nation's largest workplace/interior fitout architecture, engineering, and construction firms, as reported in Building Design+Construction's 2022 Giants 400 Report.

boombox1
boombox2
native1

More In Category


Giants 400

Call for surveys: 2024 Giants 400 Report

Building Design+Construction's annual Giants 400 Report ranks the nation's top architecture, architecture/engineering (AE), engineering/architecture (EA), general contractors, and fee-based construction management (CM) firms, by revenue. You’ll want to be sure your firm is on the Giants 400 lists, as potential clients look to these rankings for prospective firms to design and construct their future projects.


Giants 400

BD+C's Giants 400 Rankings

Every spring, the editors of Building Design+Construction survey the nation's largest architecture, engineering, and construction firms to identify the most prominent design and construction firms across 25 building sectors and specialty categories. Meet the Giants 400.


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021