2012 Reconstruction Award Bronze Winner: Walsh Group Training and Conference Center, Chicago, Ill.

2012 Reconstruction Award Bronze Winner: Walsh Group Training and Conference Center, Chicago, Ill.

With its Building Team partners—architect Solomon Cordwell Buenz, structural engineer CS Associates, and M/E engineer McGuire Engineers—Walsh Construction, acting as its own contractor, turned the former automobile showroom and paperboard package facility into a 93,000-sf showcase of sustainable design and construction.


October 5, 2012
A 1953 Allis-Chalmers bulldozer in the central atrium of the Walsh Training and
A 1953 Allis-Chalmers bulldozer in the central atrium of the Walsh Training and Conference Center, Chicago. The 93,000-sf LEED P
This article first appeared in the October 2012 issue of BD+C.

Two years ago, The Walsh Group, a $4 billion construction firm that traces its roots in Chicago back to 1898, found it needed more space for a new training and conference center. Unfortunately, there was no room at its West Loop headquarters for such a facility.

The fourth-generation, family-run firm could easily have built a new structure. Instead, the Walsh Group chose what it considered to be the more environmentally responsible path and rebuilt an underused 90-year-old warehouse/factory building. The project earned 86 points on the way to achieving LEED Platinum certification—at the time, the sixth-highest number of LEED points ever awarded.

PROJECT SUMMARY


WALSH GROUP TRAINING AND CONFERENCE CENTER
Chicago, Ill.

Building Team
Submitting firm: The Walsh Group (owner)
Architect: Solomon Cordwell Buenz
Structural engineer: CS Associates Inc.
Mechanical/electrical engineer: McGuire Engineers Inc.
General contractor: Walsh Construction Co.

General Information
Size: 93,000 sf
Construction cost: $24 million
Construction time: April 2010 to June 2011
Delivery method: Design-build

With its Building Team partners—architect Solomon Cordwell Buenz, structural engineer CS Associates, and M/E engineer McGuire Engineers—Walsh Construction, acting as its own contractor, turned the former automobile showroom and paperboard package facility into a 93,000-sf showcase of sustainable design and construction.

Most of the original three-story structure, including 30,000 bricks, was salvaged, and 96% of construction waste was diverted from landfill. A fourth story was added, and the designer created a central atrium that provides natural daylighting through a massive skylight in the roof.

Sustainable features included a vegetated roof, a rainwater recovery system, and smart building technology that allows for partially localized environmental control.

Sophisticated MEP systems were employed: an HVAC system that uses solar thermal technology to pre-heat outdoor air before being inducted into the air-handling units, resulting in a projected 42% savings in energy costs; boilers with an 88% efficiency rating; and chemical-free water treatment for the evaporative condenser. The building’s exhaust air provides primary heating for the garage.

In the opinion of BD+C’s Reconstruction Awards jury, The Walsh Group made the right decision, for itself and for its home town. +

Related Stories

Building Team Awards | Apr 9, 2015

Setting the bar for port-of-entry design

Whenever you eat a tomato from Mexico, there’s a one-in-three chance it came through this LEED Gold gateway.

Building Team Awards | Apr 9, 2015

Big D’s billion-dollar baby: New Parkland Hospital Tops the Chart | BD+C

Dallas’s new $1.27 billion public hospital preserves an important civic anchor, Texas-style.

Building Team Awards | Apr 9, 2015

IPD-driven fusion facility serves science and student life in Chicago

In dire need of modern science labs and a student union, North Park University built both—in the same building.

Building Team Awards | Apr 9, 2015

‘Prudent, not opulent’ sets the tone for this Catholic hospital

This Building Team stuck with a project for seven years to get a new hospital built for a faithful client.

Building Team Awards | Apr 9, 2015

9/11 museum triumphs over controversy

The Building Team for this highly visible project had much more than design, engineering, and construction problems to deal with.

Building Team Awards | Apr 7, 2015

Unique test facility will help make wind power more feasible

A new facility at Clemson University makes it possible to test the huge stresses that large-scale wind turbines must be able to withstand.

Cultural Facilities | Apr 7, 2015

Mies’ Martin Luther King Jr. Library to get makeover

The architects say the modernization aims to improve “Mies in a contemporary Miesian way.”

Cultural Facilities | Apr 6, 2015

Berkeley’s West Branch Library generates more energy than it uses

The 9,400-sf facility is California's first Net Zero Energy-certified building.

Codes and Standards | Apr 6, 2015

Industry groups petition for change order reform on federal projects

Nine design and construction associations ask for assurance that funds available for additional work.

High-rise Construction | Apr 6, 2015

Melbourne tower will light up depending on weather

The tower will be illuminated by 164-foot-tall beams of LED light based on weather updates from the Bureau of Meteorology. 

boombox1
boombox2
native1

More In Category

Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021