2012 Reconstruction Award Bronze Winner: Walsh Group Training and Conference Center, Chicago, Ill.

2012 Reconstruction Award Bronze Winner: Walsh Group Training and Conference Center, Chicago, Ill.

With its Building Team partners—architect Solomon Cordwell Buenz, structural engineer CS Associates, and M/E engineer McGuire Engineers—Walsh Construction, acting as its own contractor, turned the former automobile showroom and paperboard package facility into a 93,000-sf showcase of sustainable design and construction.


October 5, 2012
A 1953 Allis-Chalmers bulldozer in the central atrium of the Walsh Training and
A 1953 Allis-Chalmers bulldozer in the central atrium of the Walsh Training and Conference Center, Chicago. The 93,000-sf LEED P
This article first appeared in the October 2012 issue of BD+C.

Two years ago, The Walsh Group, a $4 billion construction firm that traces its roots in Chicago back to 1898, found it needed more space for a new training and conference center. Unfortunately, there was no room at its West Loop headquarters for such a facility.

The fourth-generation, family-run firm could easily have built a new structure. Instead, the Walsh Group chose what it considered to be the more environmentally responsible path and rebuilt an underused 90-year-old warehouse/factory building. The project earned 86 points on the way to achieving LEED Platinum certification—at the time, the sixth-highest number of LEED points ever awarded.

PROJECT SUMMARY


WALSH GROUP TRAINING AND CONFERENCE CENTER
Chicago, Ill.

Building Team
Submitting firm: The Walsh Group (owner)
Architect: Solomon Cordwell Buenz
Structural engineer: CS Associates Inc.
Mechanical/electrical engineer: McGuire Engineers Inc.
General contractor: Walsh Construction Co.

General Information
Size: 93,000 sf
Construction cost: $24 million
Construction time: April 2010 to June 2011
Delivery method: Design-build

With its Building Team partners—architect Solomon Cordwell Buenz, structural engineer CS Associates, and M/E engineer McGuire Engineers—Walsh Construction, acting as its own contractor, turned the former automobile showroom and paperboard package facility into a 93,000-sf showcase of sustainable design and construction.

Most of the original three-story structure, including 30,000 bricks, was salvaged, and 96% of construction waste was diverted from landfill. A fourth story was added, and the designer created a central atrium that provides natural daylighting through a massive skylight in the roof.

Sustainable features included a vegetated roof, a rainwater recovery system, and smart building technology that allows for partially localized environmental control.

Sophisticated MEP systems were employed: an HVAC system that uses solar thermal technology to pre-heat outdoor air before being inducted into the air-handling units, resulting in a projected 42% savings in energy costs; boilers with an 88% efficiency rating; and chemical-free water treatment for the evaporative condenser. The building’s exhaust air provides primary heating for the garage.

In the opinion of BD+C’s Reconstruction Awards jury, The Walsh Group made the right decision, for itself and for its home town. +

Related Stories

Architects | Apr 5, 2018

AIA grants $100,000 to four Upjohn Research Initiative projects

The purpose of the grant is to provide base funds for applied research projects that will advance the design profession’s knowledge and practice.

Architects | Apr 5, 2018

Tech Report 5.0: The Human Touch

Can studying humans at a behavioral level produce better buildings? Cognitive architecture experts are working to find out.

Architects | Apr 4, 2018

How to acquire speaking engagements and hone your skills

So, you understand the benefits, but how do you actually get started with speaking engagements?

Architects | Apr 4, 2018

8 things to consider before using digital media to communicate with employees

The Marlin Company, a visual communications and digital signage provider, published a guide that outlines eight basic questions, along with some advice, about workplace digital signage.

Education Facilities | Mar 30, 2018

How can we design safer schools in the age of active shooters?

How can we balance the need for additional security with design principles that foster a more nurturing next-generation learning environment for students?

Architects | Mar 26, 2018

Designing for homeless facilities: Critical spaces to consider

The City of San Diego is home to the fourth largest homeless population in the U.S.

Education Facilities | Mar 23, 2018

An introvert's oasis: How to create learning environments for all student types

In order to understand why a school day can be so grueling for an introverted student, it’s important to know what it means to be introverted, writes NAC Architecture’s Emily Spiller.

Architects | Mar 22, 2018

The benefits and nuances of integrated design

Achieving integrated design usually means operating under a strong relationship. 

Architects | Mar 14, 2018

Becoming nature: The building design evolution meets the living building revolution

With the environmental movement, sustainability became a marker of innovation in design for the built environment.

Office Buildings | Mar 12, 2018

Sound advice on workplace design

Thoughtful design, paired with a change management program to educate staff, can both enhance connectivity and minimize distractions.  

boombox1
boombox2
native1

More In Category




Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021