As a company, DPR Construction has a deep-seated commitment to sustainability, its employees, and the communities it serves. A couple of years ago, when the lease for its Phoenix office came up, the firm seized the opportunity to create an ultra-green environment for its 101-person Phoenix office and field staff.
Working with A/E firm SmithGroupJJR, DPR converted a vacant 16,533-sf one-time “adult-themed boutique” in the city’s reemerging Discovery Triangle into a LEED-NC Platinum office, one that is on target to be the first net-zero commercial office building in Arizona.
The Building Team—including sustainability consultant DNV KEMA and consulting structural engineer PK Associates—forged numerous paths to energy reduction. They used an 87-foot zinc-clad solar chimney to create a convection current that draws air into the building through four evaporative cooling “shower towers” equipped with internal misters and showerheads. The pre-cooled air then flows through the open office space, and hot air exhausts back through the chimney.
PROJECT SUMMARY
DPR CONSTRUCTION, PHOENIX REGIONAL OFFICE
Phoenix, Ariz.Building Team
Submitting firm: SmithGroupJJR (architect/MEP engineer), in conjunction with DPR Construction (owner/developer/GC)
Structural engineer: PK Associates Consulting Structural Engineers
Sustainability consultant: DNV KEMA Energy & SustainabilityGeneral Information
Size: 16,533 sf
Construction cost: $3,762,000
Construction time: February 2011 to October 2011
Delivery method: Design-build
Twelve eight-foot-diameter fans, three oversized roll-up doors, and 87 operable windows installed along the east and north façades further support the building’s passive cooling system. Eighty-two solar optical tubes bring additional daylight into the workspace, helping to cut artificial lighting by 70%.
LEDs provide exterior site lighting, but the team decided against using LEDs on the interior because they did not meet the project goal of a maximum 10-year return on investment. A phantom-load reduction “vampire” switch cuts off 90% of plug loads at night.
The tally: Net energy use intensity was cut to 28.85 kBtu/sf/year; lighting power density was reduced to 0.96 watts/sf. Net-zero energy was achieved through the installation of a 79.6 kW PV-covered canopy over half the parking lot.
To further its commitment to the community, DPR has opened its building to host meetings for local business groups, students, and nonprofit organizations. +
Related Stories
| Apr 12, 2011
Rutgers students offered choice of food and dining facilities
The Livingston Dining Commons at Rutgers University’s Livingston Campus in New Brunswick, N.J., was designed by Biber Partnership, Summit, N.J., to offer three different dining rooms that connect to a central servery.
| Apr 12, 2011
Retail complex enjoys prime Abu Dhabi location
The Galleria at Sowwah Square in Abu Dhabi will be built in a prime location within Sowwah Island that also includes a five-star Four Seasons Hotel, the healthcare facility Cleveland Clinic Abu Dhabi, and nearly two million sf of Class A office space.
| Apr 12, 2011
Luxury New York high rise adjacent to the High Line
Located adjacent to New York City’s High Line Park, 500 West 23rd Street will offer 111 luxury rental apartments when it opens later this year.
| Apr 12, 2011
College of New Jersey facility will teach teachers how to teach
The College of New Jersey broke ground on its 79,000-sf School of Education building in Ewing, N.J.
| Apr 12, 2011
Mental hospital in Boston redeveloped as healthcare complex
An abandoned state mental health facility in Boston’s prestigious Longwood Medical Area is being transformed into the Mass Mental Health Center, a four-building mixed-use complex that includes a mental health day hospital, a clinical and office building, a medical research facility for Brigham and Women’s Hospital, and a residential facility.
| Apr 12, 2011
Miami courthouse design does justice to children and the environment
Suffolk Construction broke ground recently for the Miami-Dade County Children’s Courthouse, a $328 million project the firm has a 30-month contract to complete.
| Apr 12, 2011
Long-awaited San Francisco center is music to jazz organization’s ears
After 28 years, SFJAZZ is getting its first permanent home. The San Francisco-based nonprofit, which is dedicated to advancing the art of jazz through concerts and educational programs, contracted local design firm Mark Cavagnero Associates and general contractor Hathaway Dinwiddie to create a modern performance center in the city’s Hayes Valley neighborhood
| Apr 12, 2011
Entrance pavilion adds subtle style to Natural History Museum of Los Angeles
A $13 million gift from the Otis Booth Foundation is funding a new entrance pavilion at the Natural History Museum of Los Angeles County. CO Architects, Los Angeles, is designing the frameless structure with an energy-efficient curtain wall, vertical suspension rods, and horizontal knife plates to make it as transparent as possible.
| Apr 12, 2011
BIM Grows Up: Separating Hype from Reality in a 3D World
While BIM adoption still lags in both design and construction, some enterprising owners, architects, and contractors are unlocking the potential of this dynamic technology.
| Apr 12, 2011
Metal cladding: Enhancing design with single-skin panels, MCMs, and IMPs
Single-skin metal panels, metal composite panels, and insulated metal panels can add both aesthetic and functional value to your projects, if you use them correctly.