flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

2012 Reconstruction Award Bronze Winner: DPR Construction, Phoenix Regional Office, Phoenix, Ariz.

2012 Reconstruction Award Bronze Winner: DPR Construction, Phoenix Regional Office, Phoenix, Ariz.

Working with A/E firm SmithGroupJJR, DPR converted a vacant 16,533-sf one-time “adult-themed boutique” in the city’s reemerging Discovery Triangle into a LEED-NC Platinum office, one that is on target to be the first net-zero commercial office building in Arizona.


October 5, 2012
In addition to achieving net-zero energy use and LEED-NC Platinum certification,
In addition to achieving net-zero energy use and LEED-NC Platinum certification, DPR Constructions Phoenix office provides nume
This article first appeared in the October 2012 issue of BD+C.

As a company, DPR Construction has a deep-seated commitment to sustainability, its employees, and the communities it serves. A couple of years ago, when the lease for its Phoenix office came up, the firm seized the opportunity to create an ultra-green environment for its 101-person Phoenix office and field staff.

Working with A/E firm SmithGroupJJR, DPR converted a vacant 16,533-sf one-time “adult-themed boutique” in the city’s reemerging Discovery Triangle into a LEED-NC Platinum office, one that is on target to be the first net-zero commercial office building in Arizona.

The Building Team—including sustainability consultant DNV KEMA and consulting structural engineer PK Associates—forged numerous paths to energy reduction. They used an 87-foot zinc-clad solar chimney to create a convection current that draws air into the building through four evaporative cooling “shower towers” equipped with internal misters and showerheads. The pre-cooled air then flows through the open office space, and hot air exhausts back through the chimney.

PROJECT SUMMARY


DPR CONSTRUCTION, PHOENIX REGIONAL OFFICE
Phoenix, Ariz.

Building Team
Submitting firm: SmithGroupJJR (architect/MEP engineer), in conjunction with DPR Construction (owner/developer/GC)
Structural engineer: PK Associates Consulting Structural Engineers
Sustainability consultant: DNV KEMA Energy & Sustainability

General Information
Size: 16,533 sf
Construction cost: $3,762,000
Construction time: February 2011 to October 2011
Delivery method: Design-build

Twelve eight-foot-diameter fans, three oversized roll-up doors, and 87 operable windows installed along the east and north façades further support the building’s passive cooling system. Eighty-two solar optical tubes bring additional daylight into the workspace, helping to cut artificial lighting by 70%.

LEDs provide exterior site lighting, but the team decided against using LEDs on the interior because they did not meet the project goal of a maximum 10-year return on investment. A phantom-load reduction “vampire” switch cuts off 90% of plug loads at night.

The tally: Net energy use intensity was cut to 28.85 kBtu/sf/year; lighting power density was reduced to 0.96 watts/sf. Net-zero energy was achieved through the installation of a 79.6 kW PV-covered canopy over half the parking lot.

To further its commitment to the community, DPR has opened its building to host meetings for local business groups, students, and nonprofit organizations. +

Related Stories

| Jan 23, 2014

Adrian Smith + Gordon Gill-designed Federation of Korean Industries tower opens in Seoul [slideshow]

The 50-story tower features a unique, angled building-integrated photovoltaic (BIPV) exterior designed to maximize the amount of energy collected.

| Jan 23, 2014

Think you can recognize a metal building from the outside?

What looks like brick, stucco or wood on the outside could actually be a metal building. Metal is no longer easily detectable. It’s gotten sneakier visually. And a great example of that is the Madison Square retail center in Norman, Okla.

| Jan 23, 2014

3 fatal flaws your architecture firm has right now

After visiting over 200 architecture firms, I was aghast that so many of them were committing these costly sins of mismanagement and miscommunication, without even realizing it. If I can stop even one more firm from shooting its own foot, then this is worth it.

| Jan 22, 2014

SOM-designed University Center uses 'sky quads,' stacked staircases to promote chance encounters

The New School's vertical campus in Manhattan houses multiple functions, including labs, design studios, a library, and student residences, in a 16-story building.  

| Jan 22, 2014

Architecture Billings Index sees first back-to-back decline since mid-2012

The AIA's Architecture Billings Index dipped for the second consecutive month in December—the first consecutive months of contraction since May and June of 2012.

| Jan 21, 2014

Comcast to build second Philadelphia skyscraper, with Norman Foster-designed tower [slideshow]

The British architect last week unveiled his scheme for the $1.2 billion, 59-story Comcast Innovation and Technology Center, planned adjacent to the Comcast Center. 

| Jan 21, 2014

2013: The year of the super-tall skyscraper

Last year was the second-busiest ever in terms of 200-meter-plus building completions, with 73 towers, according to a report by the Council on Tall Buildings and Urban Habitat.

| Jan 20, 2014

BUILDINGChicago/Greening the Heartland Conference 'call for 2014 educational proposals' is now open

The conference and exposition will take place September 29-October 1, 2014, at North America’s largest LEED Gold-certified hotel, the Holiday Inn Chicago Mart Plaza. Deadline for proposals is February 28, 2014.

| Jan 17, 2014

Crystal Bridges Museum will move Frank Lloyd Wright house from New Jersey to Arkansas

Numerous architectural experts have concluded that moving the Bachman Wilson House offers its best hope for long-term survival.

| Jan 17, 2014

Australian project transforms shipping containers into serene workplace

Australian firm Royal Wolf has put its money where its mouth is by creating an office facility out of shipping containers at its depot and fabrication center in Sunshine, Victoria.

boombox1
boombox2
native1

More In Category

Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021