200 Fillmore

200 Fillmore

Denver, Colorado


By Maggie Koerth-Baker | August 11, 2010
This article first appeared in the 200610 issue of BD+C.

Built in 1963, the 32,000-sf 200 Fillmore building in Denver housed office and retail in a drab, outdated, and energy-splurging shell—a “style” made doubly disastrous by 200 Fillmore's function as the backdrop for a popular public plaza and outdoor café called “The Beach.”

In 2005, the owner, Western Development Group, determined to pluck 200 Fillmore out from its Class C office space doldrums. To do that, a Building Team headed by the Denver office of Chicago firm 4240 Architecture came up with three goals: maximize the leasable area, improve the building's energy usage, and enhance the appearance of The Beach.

The team ran head-on into problems. First, they discovered the building already exceeded zoning limits on area, so any expansion had to stay within the building's original footprint. Their best option for expansion, then, lay in the cantilevered concrete slab that extended around the outside as part of the original façade. Field tests showed the slab could support a new exterior wall, but only one weighing less than 10 pounds per face square foot. The solution: A terra cotta rainscreen system that gave the building an inviting appearance at a low weight.

This part of the project required better-than-average organizational skills. The terra cotta tiles were not flat, nor did they have clean, straight edges. To make sure the rainscreen was installed with a 3/16-in. joint throughout, the team experimented with a full-size mockup. All this was going on even as ground-floor retail was open and the upper three floors were gutted.

Bumping up the building's energy efficiency led the Building Team to, of all places, the restrooms, which had claustrophobically low seven-foot ceilings that were constrained by undersized air handler units stored in the space above. The team junked those floor-based units in favor of one large roof unit that served the whole building. The result was not only a more efficient HVAC system, but also a person-friendly restroom design—with ceiling heights raised to eight feet.

Improvements to The Beach include tall grasses and seasonal flower landscaping that wrap around the retail and plaza edge. A new wood and steel entry canopy complements the terra cotta rainscreen and steel window treatments, while simultaneously connecting the lobby and outdoors and reducing the building's scale.

All these changes resulted in a radically different building—both inside and out. Gone is the '60s-era façade with its set-back windows framed by a mesh grille and crossed by vertical support bars. In its place are new flush windows on the second and third floors, and a balcony on the fourth floor, which is now residential space for the building's owner. Horizontal trim at the tops of the windows mimic the balcony's railing system.

The Building Team was able to accomplish this complete overhaul—from original design to completed construction—in 12 months. Although the project went $300,000 (7.5%) over the original $4 million budget, the overrun was negated by the fact that the new 200 Fillmore was fully leased on opening day.

Related Stories

Sustainability | May 28, 2019

Carrier’s world headquarters in Florida goes green

The structure is the first commercial building in Florida to achieve LEED Platinum v4 Certification.

Office Buildings | May 14, 2019

Sail on, Royal Caribbean: HOK-designed headquarters celebrates cruise ship industry

The building’s design is inspired by the design of its fleet of cruise ships—with flowing lines.

Mixed-Use | May 2, 2019

A series of green bridges will connect these two towers in Shenzhen, China

Steven Holl Architects designed the project.

Office Buildings | May 2, 2019

HOK’s latest study takes a new look at tech workplaces

The report provides insight into the relative importance of such things as amenities and occupant health for recruiting and retaining workers.

Office Buildings | Apr 25, 2019

Study: Half of corporate and government offices offer wellness programs

Nearly 30% of worksites offer programs for physical activity and fitness, according to the CDC.

Office Buildings | Apr 8, 2019

It’s time for office amenities to get to work

Amenities with the greatest impact on effectiveness and experience are those that directly support the work needs of individual employees and their teams. 

Office Buildings | Apr 8, 2019

Denver office building features 13,000 sf green roof

Dynia Architects designed the building.

Office Buildings | Apr 5, 2019

2019 trends in the workplace

From retention and career advancement to the ethics of inclusion and diversity, these five trends will play a major role this year in design, strategic planning and workplace development.

Industrial Facilities | Mar 10, 2019

The burgeoning Port San Antonio lays out growth plans

Expansions would accommodate cybersecurity, aerospace, and defense tenants, and help commercialize technologies.

Office Buildings | Mar 6, 2019

How to leverage design and culture’s two-way relationship for better workplaces

The relationship between workplace design and company culture isn’t all that different from a tango.

boombox1
boombox2
native1

More In Category

Adaptive Reuse

Detroit’s Michigan Central Station, centerpiece of innovation hub, opens

The recently opened Michigan Central Station in Detroit is the centerpiece of a 30-acre technology and cultural hub that will include development of urban transportation solutions. The six-year adaptive reuse project of the 640,000 sf historic station, created by the same architect as New York’s Grand Central Station, is the latest sign of a reinvigorating Detroit.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021