In the world of tall building construction, projects can stall for any number of reasons—financial, political, cultural—and for long periods of time.Â
The CTBUH Research team, in the latest installment of Tall Buildings in Numbers, has undertaken to find the top 20 tallest never-completed buildings, and the 15 longest construction periods from 1985 to the present, listing the stop and start dates, and last known status of these 35 projects.
We learned a lot along the way, turning up some interesting findings on familiar names and long-forgotten projects alike, including:
• Now over 28 years since it started construction, Ryugyong Hotel in Pyongang holds the record for longest construction period by over seven years.
• There are 50 buildings 150 meters or taller currently on hold (i.e., construction had started and stopped, but is planned to resume) around the world.
• The Palace of Soviets in Moscow was actually started in 1937, but construction was halted during frame construction with the coming of World War II. It would have been topped with a statue of Joseph Stalin, making it the world’s tallest structure
• Now over 28 years since it started construction, Ryugyong Hotel in Pyongang holds the record for longest construction period by over seven years.
Â
Â
CLICK IMAGE TO ENLARGE Source: CTBUH
Â
Â
CLICK IMAGE TO ENLARGEÂ Source: CTBUH
Â
Related Stories
Office Buildings | Oct 12, 2011
8 Must-know Trends in Office Fitouts
Office designs are adjusting to dramatic changes in employee work habits. Goodbye, cube farm. Hello, bright, open offices with plenty of collaborative space.
| Oct 12, 2011
FMI’s Construction Outlook: Third Quarter 2011 Report
 Construction Market Forecast: The general economy is seeing mixed signs.
| Oct 12, 2011
Bulley & Andrews celebrates 120 years of construction
The family-owned and operated general contractor attributes this significant milestone to the strong foundation built decades ago on honesty, integrity, and service in construction.Â
| Oct 12, 2011
Consigli Construction breaks ground for Bigelow Laboratory Center for Ocean Health
 Consigli to build third phase of 64-acre Ocean Science and Education Campus, design by WBRC Architects , engineers in association with Perkins + Will
| Oct 11, 2011
AIA introduces five new documents for use on sustainable projects
These new documents will be available in the first quarter of 2012 as part of the new AIA Contract Documents service and AIA Documents on Demand.
| Oct 11, 2011
Pink light bulbs donated to Society of Memorial Sloan-Kettering Cancer Center
 For every Bulbrite Pink Light Bulb that is purchased through the Cancer Center Thrift Shop, 100% of the proceeds will be donated to help support breast cancer research, education, screening, and treatment.Â
| Oct 11, 2011
ThyssenKrupp elevator cabs validated by UL Environment
The conclusive and independent third-party validation process is another step toward a green product line.
| Oct 11, 2011
Ballard Spahr launches real estate recovery group
 The new group represents an expansion of the company’s Distressed Real Estate Initiative, which was launched in 2008 to help clients throughout the country plan, adapt and prosper in a challenging economic environment.Â
| Oct 11, 2011
Onex completes investment in JELD-WEN
With the completion of the JELD-WEN investment, Onex Partners III is approximately 40% invested.
| Oct 7, 2011
GREENBUILD 2011: Demand response partnership program announced at Greenbuild 2011
 Program will use USGBC’s newly revised LEED Demand Response credit as an implementation guideline and leverage its relationships with the building community to foster adoption and participation in existing utility and solution provider demand response offerings.Â