In the world of tall building construction, projects can stall for any number of reasons—financial, political, cultural—and for long periods of time.
The CTBUH Research team, in the latest installment of Tall Buildings in Numbers, has undertaken to find the top 20 tallest never-completed buildings, and the 15 longest construction periods from 1985 to the present, listing the stop and start dates, and last known status of these 35 projects.
We learned a lot along the way, turning up some interesting findings on familiar names and long-forgotten projects alike, including:
• Now over 28 years since it started construction, Ryugyong Hotel in Pyongang holds the record for longest construction period by over seven years.
• There are 50 buildings 150 meters or taller currently on hold (i.e., construction had started and stopped, but is planned to resume) around the world.
• The Palace of Soviets in Moscow was actually started in 1937, but construction was halted during frame construction with the coming of World War II. It would have been topped with a statue of Joseph Stalin, making it the world’s tallest structure
• Now over 28 years since it started construction, Ryugyong Hotel in Pyongang holds the record for longest construction period by over seven years.
CLICK IMAGE TO ENLARGE Source: CTBUH
CLICK IMAGE TO ENLARGE Source: CTBUH
Related Stories
| Apr 1, 2014
The risks of mismatched fire-rated assemblies
Mismatched fire-rated glass and framing happens more often than you think. Failing to confirm that the tested and listed performance capabilities of the framing system match those of the glazing can create a financial nightmare for the entire building team.
| Apr 1, 2014
Planned global commerce center breaks ground near Phoenix
When completed, PhoenixMart will be one of the largest single-level trade centers in the U.S.
| Apr 1, 2014
Paints, coatings and sealants: Choosing products and procedures for best performance
This course covers life cycle assessment, color selection, emissions, durability, resilience, corrosion resistance, specification standards, and other critical aspects of choosing coatings for interior and exterior walls, ceilings, and roofs.
| Mar 31, 2014
Extreme conversion: Soaring Canadian church transformed into contemporary library
Even before the St. Denys-du-Plateau Church was converted into a library, it was an unusual building, with a towering nave designed to mimic a huge tent inflated by the wind.
| Mar 31, 2014
Tips for creating a competitive bid using codes and loads
Landing a project feels like winning a prize, sort of like finding that forgotten $20 bill in the pocket of a pair of jeans you haven’t worn in a while. But living on the “chance” of winning a job isn’t a great way to pay your electric bill. So, how do you swing the chances in your favor?
Sponsored | | Mar 30, 2014
Ontario Leisure Centre stays ahead of the curve with channel glass
The new Bradford West Gwillimbury Leisure Centre features a 1,400-sf serpentine channel glass wall that delivers dramatic visual appeal for its residents.
| Mar 28, 2014
Crazy commuting: British artist wants to construct 300-foot water slide on city street
Bristol-based artist Luke Jerram hopes that the temporary installation, once funded, will encourage the public to think about "how we want to use the city, and what sort of future we want to see.”
| Mar 27, 2014
Develop strategic thinkers throughout your firm
In study after study, strategic thinkers are found to be among the most highly effective leaders. But is there a way to encourage routine strategic thinking throughout an organization?
| Mar 27, 2014
16 kitchen and bath design trends for 2014
Work on multifamily housing projects? Here are the top kitchen and bath design trends, according to a survey of more than 420 kitchen and bath designers.
| Mar 26, 2014
A sales and service showcase
High Plains Equipment, a Case IH dealership in Devils Lake, N.D., constructs a larger facility to better serve its customers.