In the world of tall building construction, projects can stall for any number of reasons—financial, political, cultural—and for long periods of time.
The CTBUH Research team, in the latest installment of Tall Buildings in Numbers, has undertaken to find the top 20 tallest never-completed buildings, and the 15 longest construction periods from 1985 to the present, listing the stop and start dates, and last known status of these 35 projects.
We learned a lot along the way, turning up some interesting findings on familiar names and long-forgotten projects alike, including:
• Now over 28 years since it started construction, Ryugyong Hotel in Pyongang holds the record for longest construction period by over seven years.
• There are 50 buildings 150 meters or taller currently on hold (i.e., construction had started and stopped, but is planned to resume) around the world.
• The Palace of Soviets in Moscow was actually started in 1937, but construction was halted during frame construction with the coming of World War II. It would have been topped with a statue of Joseph Stalin, making it the world’s tallest structure
• Now over 28 years since it started construction, Ryugyong Hotel in Pyongang holds the record for longest construction period by over seven years.
CLICK IMAGE TO ENLARGE Source: CTBUH
CLICK IMAGE TO ENLARGE Source: CTBUH
Related Stories
Sports and Recreational Facilities | Apr 13, 2015
USTA breaks ground on what will be the country’s largest tennis complex
The 63-acre facility is being positioned as a cornerstone for a sports innovation and performance district in Lake Nona, Fla., a 7,000-acre master planned community that continues to expand.
Building Team Awards | Apr 10, 2015
14 projects that push AEC teaming to the limits
From Lean construction to tri-party IPD to advanced BIM/VDC coordination, these 14 Building Teams demonstrate the power of collaboration in delivering award-winning buildings. These are the 2015 Building Team Award winners.
Building Team Awards | Apr 10, 2015
Prefab saves the day for Denver hospital
Mortenson Construction and its partners completed the 831,000-sf, $623 million Saint Joseph Hospital well before the January 1, 2015, deadline, thanks largely to their extensive use of offsite prefabrication.
Building Team Awards | Apr 10, 2015
Anaheim’s soaring intermodal hub
Anaheim's Regional Transportations Intermodal Center is the largest ETFE project in North America.
Building Team Awards | Apr 10, 2015
Virtual collaboration helps complete a hospital in 24 months
PinnacleHealth needed a new hospital STAT! This team delivered it in two years, start to finish.
Building Team Awards | Apr 10, 2015
New arts venue reinvigorates Virginia Tech's campus
The STV-led Building Team creates a world-class performance and arts venue with learning and entrepreneurial dimensions.
BIM and Information Technology | Apr 9, 2015
A carboard box by Google can bring virtual reality to architecture
The global search engine giant has launched a new product, Google Cardboard, that easily allows users to experience virtual reality.
Building Team Awards | Apr 9, 2015
Multifaced fitness center becomes campus landmark
A sloped running track and open-concept design put this Building Team to the test.
Building Team Awards | Apr 9, 2015
Nation's first LEED-certified bus depot
A bus garage in Harlem shows that even the most mundane of facilities can strut its environmentally sensitive stuff.
Building Team Awards | Apr 9, 2015
Setting the bar for port-of-entry design
Whenever you eat a tomato from Mexico, there’s a one-in-three chance it came through this LEED Gold gateway.