10 design-build best practices

10 design-build best practices

Based on research, case studies, and industry input, DBIA has identified design-build best practices.


By DBIA | April 21, 2014
According to DBIA's new report, design-build requires more than a good contract
According to DBIA's new report, design-build requires more than a good contract and appropriate risk allocation. Photo: Ingolfso

The Design-Build Institute of America (DBIA) has released “Universally Applicable Best Practices Applying to Any Project Type, in Any Market Sector, of Any Size.” Based on research, case studies, and industry input, DBIA has identified design-build best practices.

The 10 Design-Build Done Right Best Practices serve as a single source that clearly defines design-build fundamentals to significantly enhance superior project outcomes,” says Lisa Washington, CAE, Executive Director/CEO, DBIA. “With design-build currently at 40% of all non-residential design and construction, the impetus for owners to engage in Design-Build Done Right is at an all-time high. By applying these ten DBIA Best Practices, owners and practitioners will unlock the inherent value of design-build project delivery.”

Best practices supporting effective design-build start during the owner’s procurement decision-making process and span through project execution. Each DBIA Best Practice is supplemented by several techniques that provide guidance on specific ways to implement the best practice. The combination of best practices and implementing techniques are the basis for Design-Build Done Right.

Design-build requires more than a good contract and appropriate risk allocation. Everyone from the owner to the subcontractors must understand the process, the expectations and fully engage in the collaboration. DBIA categorizes the 10 best practices (and nearly 50 supporting implementing techniques) into three areas:

Procuring Design-Build Services

1. An owner should conduct a proactive and objective assessment of the unique characteristics of its program/project and its organization before deciding to use design-build. 

2. An owner should implement a procurement plan that enhances collaboration and other benefits of design-build and is in harmony with the reasons that the owner chose the design-build delivery system. 

3. An owner using a competitive design-build procurement that seeks price and technical proposals should: (a) establish clear evaluation and selection processes; (b) ensure that the process is fair, open and transparent; and (c) value both technical concepts and price in the selection process.

Contracting for Design-Build Services:

4. Contracts used on design-build projects should be fair, balanced and clear, and should promote the collaborative aspects inherent in the design-build process. 

5. The contract between the owner and design-builder should address the unique aspects of the design-build process, including expected standards of care for design services. 

6. The contracts between the design-builder and its team members should address the unique aspects of the design-build process. 

Executing the Delivery of Design-Build Projects:

7. All design-build team members should be educated and trained in the design-build process, and be knowledgeable of the differences between design-build and other delivery systems. 

8. The project team should establish logistics and infrastructure to support integrated project delivery.

9. The project team, at the outset of the project, should establish processes to facilitate timely and effective communication, collaboration, and issue resolution. 

10. The project team should focus on the design management and commissioning/turnover processes and ensure that there is alignment among the team as to how to execute these processes.

 

DBIA recognizes that there are real-world differences among design-build market sectors (e.g., water/wastewater, transportation, federal projects), and that specific implementation techniques might differ slightly from one market sector to another. For this reason, DBIA is in the process of working with market sector experts on sector-specific documents to supplement the overall best practices released today. These will provide more detailed guidance on how to put these best practices and implementing techniques into use in different design-build market sectors.

DBIA intends to continually update its portfolio of publications, tools and other resources so that design-build stakeholders will have access to leading-edge information that will allow them to achieve Design-Build Done Right in accordance with the concepts expressed in this document.

Related Stories

| Jul 9, 2014

Harvard Business School to build large-scale conference center

Expected to open in 2018, the facility will combine the elements of a large-scale conference center, a performance space, and an intimate community forum. The new building will be designed by Boston-based William Rawn and Associates.

| Jul 9, 2014

Top U.S. cities for design professionals

Though New York and Los Angeles are often seen as the sole hubs for design jobs, other design epicenters are scattered between the coasts.

| Jul 9, 2014

The one misstep that could be slowing your company’s growth

Change. It’s inevitable. And success for any professional may very well depend on how well we adapt to it. SPONSORED CONTENT

| Jul 9, 2014

First Look: SOM's design for All Aboard Florida Fort Lauderdale rail station

The lightweight and luminous design "responds to its setting and creates a striking infrastructural icon for the city," said SOM Design Partner Roger Duffy. 

| Jul 8, 2014

Fast-track naval hospital sparks sea change in project delivery [2014 Building Team Awards]

Through advanced coordination methods and an experimental contract method, the Building Team for Camp Pendleton’s new hospital campus sets a new standard for project delivery.

| Jul 8, 2014

Does Zaha Hadid’s Tokyo Olympic Stadium have a design flaw?

After being criticized for the cost and size of her stadium design for the 2020 Olympics in Tokyo, a Japanese architect points out a major design flaw in the stadium that may endanger the spectators.

| Jul 8, 2014

Frank Lloyd Wright's posthumous gas station opens in Buffalo

Eighty-seven years after Frank Lloyd Wright designed an ornamental gas station for the city of Buffalo, the structure has been built and opened to the public—inside an auto museum. 

| Jul 8, 2014

Lost in the Museum: Bjarke Ingels' maze will make you look up and around

The maze, located in the National Building Museum, is a precursor to an exhibit showcasing some of BIG's projects. To navigate the maze, people must look up.

| Jul 7, 2014

5 factors that can affect thermal stress break risk of insulated glass units

The glass type, glass coating, shading patterns, vents, and framing system can impact an IGU’s risk for a thermal break.

| Jul 7, 2014

Team unity pays off for a new hospital in Maine [2014 Building Team Awards]

Extensive use of local contractors, vendors, and laborers brings a Maine hospital project in months ahead of schedule.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021