10 design-build best practices

10 design-build best practices

Based on research, case studies, and industry input, DBIA has identified design-build best practices.


By DBIA | April 21, 2014
According to DBIA's new report, design-build requires more than a good contract
According to DBIA's new report, design-build requires more than a good contract and appropriate risk allocation. Photo: Ingolfso

The Design-Build Institute of America (DBIA) has released “Universally Applicable Best Practices Applying to Any Project Type, in Any Market Sector, of Any Size.” Based on research, case studies, and industry input, DBIA has identified design-build best practices.

The 10 Design-Build Done Right Best Practices serve as a single source that clearly defines design-build fundamentals to significantly enhance superior project outcomes,” says Lisa Washington, CAE, Executive Director/CEO, DBIA. “With design-build currently at 40% of all non-residential design and construction, the impetus for owners to engage in Design-Build Done Right is at an all-time high. By applying these ten DBIA Best Practices, owners and practitioners will unlock the inherent value of design-build project delivery.”

Best practices supporting effective design-build start during the owner’s procurement decision-making process and span through project execution. Each DBIA Best Practice is supplemented by several techniques that provide guidance on specific ways to implement the best practice. The combination of best practices and implementing techniques are the basis for Design-Build Done Right.

Design-build requires more than a good contract and appropriate risk allocation. Everyone from the owner to the subcontractors must understand the process, the expectations and fully engage in the collaboration. DBIA categorizes the 10 best practices (and nearly 50 supporting implementing techniques) into three areas:

Procuring Design-Build Services

1. An owner should conduct a proactive and objective assessment of the unique characteristics of its program/project and its organization before deciding to use design-build. 

2. An owner should implement a procurement plan that enhances collaboration and other benefits of design-build and is in harmony with the reasons that the owner chose the design-build delivery system. 

3. An owner using a competitive design-build procurement that seeks price and technical proposals should: (a) establish clear evaluation and selection processes; (b) ensure that the process is fair, open and transparent; and (c) value both technical concepts and price in the selection process.

Contracting for Design-Build Services:

4. Contracts used on design-build projects should be fair, balanced and clear, and should promote the collaborative aspects inherent in the design-build process. 

5. The contract between the owner and design-builder should address the unique aspects of the design-build process, including expected standards of care for design services. 

6. The contracts between the design-builder and its team members should address the unique aspects of the design-build process. 

Executing the Delivery of Design-Build Projects:

7. All design-build team members should be educated and trained in the design-build process, and be knowledgeable of the differences between design-build and other delivery systems. 

8. The project team should establish logistics and infrastructure to support integrated project delivery.

9. The project team, at the outset of the project, should establish processes to facilitate timely and effective communication, collaboration, and issue resolution. 

10. The project team should focus on the design management and commissioning/turnover processes and ensure that there is alignment among the team as to how to execute these processes.

 

DBIA recognizes that there are real-world differences among design-build market sectors (e.g., water/wastewater, transportation, federal projects), and that specific implementation techniques might differ slightly from one market sector to another. For this reason, DBIA is in the process of working with market sector experts on sector-specific documents to supplement the overall best practices released today. These will provide more detailed guidance on how to put these best practices and implementing techniques into use in different design-build market sectors.

DBIA intends to continually update its portfolio of publications, tools and other resources so that design-build stakeholders will have access to leading-edge information that will allow them to achieve Design-Build Done Right in accordance with the concepts expressed in this document.

Related Stories

High-rise Construction | Dec 1, 2014

ThyssenKrupp develops world’s first rope-free elevator system

ThyssenKrupp's latest offering, named MULTI, will allow several cabins in the same shaft to move vertically and horizontally.

| Nov 29, 2014

20 tallest towers that were never completed

Remember the Chicago Spire? What about Russia Tower? These are two of the tallest building projects that were started, but never completed, according to the Council on Tall Buildings and Urban Habitat. The CTBUH Research team offers a roundup of the top 20 stalled skyscrapers across the globe.

| Nov 26, 2014

USITT Selects Bahrain National Theatre for Honor Award

The Bahrain National Theatre will be recognized with an Honor Award by the United States Institute for Theatre Technology (USITT) in 2015. 

| Nov 26, 2014

How the 'maker culture' brings the power of design to life

Most people affiliate the maker culture with metal working, welding, ceramics, glass blowing, painting, and soldering. But it also includes coding and online content creation, writes Gensler’s Douglas Wittnebel.

| Nov 26, 2014

U.S. Steel decides to stay in Pittsburgh, plans new HQ near Penguins arena

The giant steelmaker has agreed to move into a new headquarters that is slated to be part of a major redevelopment.

Sponsored | | Nov 26, 2014

It’s time to start trusting your employees more

A recent study published in the journal Psychological Science revealed that employees were 26% more satisfied in their roles when they had positions of power. SPONSORED CONTENT

Sponsored | | Nov 26, 2014

What’s in a coating?

A beautiful coating on metal products can make a strong statement, whether used on a high-end commercial project or an industrial building. SPONSORED CONTENT

Sponsored | | Nov 26, 2014

Virtual reality in 3D models, iPhone thermal imaging: Inside one very cool tech toybox

A little over a year ago, I embarked on a search to find individuals in the AEC space who were putting new hardware to work in the field. 

| Nov 25, 2014

Behnisch Architekten unveils design for energy-positive building in Boston

The multi-use building for Artists For Humanity that is slated to be the largest energy positive commercial building in New England.

| Nov 25, 2014

Study: 85% of employees dissatisfied with their office environment

A vast majority of office workers feel open floor plans cause multiple distractions and that more private spaces are needed in today's offices, according to a new study by Steelcase and research firm IPSOS.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021