10 design-build best practices

10 design-build best practices

Based on research, case studies, and industry input, DBIA has identified design-build best practices.


By DBIA | April 21, 2014
According to DBIA's new report, design-build requires more than a good contract
According to DBIA's new report, design-build requires more than a good contract and appropriate risk allocation. Photo: Ingolfso

The Design-Build Institute of America (DBIA) has released “Universally Applicable Best Practices Applying to Any Project Type, in Any Market Sector, of Any Size.” Based on research, case studies, and industry input, DBIA has identified design-build best practices.

The 10 Design-Build Done Right Best Practices serve as a single source that clearly defines design-build fundamentals to significantly enhance superior project outcomes,” says Lisa Washington, CAE, Executive Director/CEO, DBIA. “With design-build currently at 40% of all non-residential design and construction, the impetus for owners to engage in Design-Build Done Right is at an all-time high. By applying these ten DBIA Best Practices, owners and practitioners will unlock the inherent value of design-build project delivery.”

Best practices supporting effective design-build start during the owner’s procurement decision-making process and span through project execution. Each DBIA Best Practice is supplemented by several techniques that provide guidance on specific ways to implement the best practice. The combination of best practices and implementing techniques are the basis for Design-Build Done Right.

Design-build requires more than a good contract and appropriate risk allocation. Everyone from the owner to the subcontractors must understand the process, the expectations and fully engage in the collaboration. DBIA categorizes the 10 best practices (and nearly 50 supporting implementing techniques) into three areas:

Procuring Design-Build Services

1. An owner should conduct a proactive and objective assessment of the unique characteristics of its program/project and its organization before deciding to use design-build. 

2. An owner should implement a procurement plan that enhances collaboration and other benefits of design-build and is in harmony with the reasons that the owner chose the design-build delivery system. 

3. An owner using a competitive design-build procurement that seeks price and technical proposals should: (a) establish clear evaluation and selection processes; (b) ensure that the process is fair, open and transparent; and (c) value both technical concepts and price in the selection process.

Contracting for Design-Build Services:

4. Contracts used on design-build projects should be fair, balanced and clear, and should promote the collaborative aspects inherent in the design-build process. 

5. The contract between the owner and design-builder should address the unique aspects of the design-build process, including expected standards of care for design services. 

6. The contracts between the design-builder and its team members should address the unique aspects of the design-build process. 

Executing the Delivery of Design-Build Projects:

7. All design-build team members should be educated and trained in the design-build process, and be knowledgeable of the differences between design-build and other delivery systems. 

8. The project team should establish logistics and infrastructure to support integrated project delivery.

9. The project team, at the outset of the project, should establish processes to facilitate timely and effective communication, collaboration, and issue resolution. 

10. The project team should focus on the design management and commissioning/turnover processes and ensure that there is alignment among the team as to how to execute these processes.

 

DBIA recognizes that there are real-world differences among design-build market sectors (e.g., water/wastewater, transportation, federal projects), and that specific implementation techniques might differ slightly from one market sector to another. For this reason, DBIA is in the process of working with market sector experts on sector-specific documents to supplement the overall best practices released today. These will provide more detailed guidance on how to put these best practices and implementing techniques into use in different design-build market sectors.

DBIA intends to continually update its portfolio of publications, tools and other resources so that design-build stakeholders will have access to leading-edge information that will allow them to achieve Design-Build Done Right in accordance with the concepts expressed in this document.

Related Stories

Architects | Mar 5, 2019

Arata Isozaki named 2019 Pritzker Architecture Prize Laureate

The Japanese architect, city planner, and theorist is known for his deep commitment to the “art of space” and transnational methodology.

Architects | Feb 14, 2019

Amazon will not build HQ2 in New York City

The tech giant walks away from a deal, succumbing to opposition over huge tax breaks.

Architects | Feb 12, 2019

The basics of building commissioning

As building system technology increases in complexity and sustainability remains at the forefront of design, the need for commissioning continues to rise. This is the first post in our series examining the basics, benefits and boundaries of building commissioning.

Architects | Jan 28, 2019

9 tech trends to track in 2019

Innovations in voice recognition, cognitive neuroscience, and biometrics are among the trending tech topics for 2019, according to CallisonRTKL's Kristin Tilley.

AEC Tech | Jan 9, 2019

Our robotic future: Assessing AI's impact on the AEC profession and the built environment

This is the first in a series by Lance Hosey, FAIA, on how automation is disrupting design and construction.

Architects | Dec 17, 2018

New toolkit helps architect achieve high-performance buildings

Architects can download a copy of the toolkit online.

Architects | Dec 13, 2018

Social media synergy: Revving up your AEC firm’s content engine

Design firms know that just having a website and a blog aren’t enough, but social media complicates how they communicate.   

Architects | Dec 10, 2018

The art and science of drawing: Humanizing the design process with a bit of controlled mayhem

Hand drawing reveals a dimension beyond those available in a CAD drawing or digital rendering.

Architects | Dec 7, 2018

2019 AIA Gold Medal awarded to Lord Richard Rogers, Hon. FAIA

The Gold Medal honors an individual whose significant body of work has had a lasting influence on the theory and practice of architecture.

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021